Unless otherwise specifically set forth in these regulations, all of the materials, methods of construction, and workmanship used in street construction shall conform to GDOT's "Standard Specifications for the Construction of Transportation Systems," latest edition and any amendments thereto. (a) Pre-construction meeting. A mandatory preconstruction meeting is required for all development, construction and land disSupp. No. 6 CD332:14 turbing activities, unless this requirement is specifically waived by the department. The applicant or developer shall contact the department to schedule the pre-construction meeting. The department will ensure the attendance of all necessary county staff. The applicant or developer must, at a minimum, have the following project personnel attend the preconstruction meeting: (1) On-site project representative on behalf of the applicant or developer. (2) General and/or grading contractor. (3) Sub-contractors performing drainage system installation, base course construction and asphalt paving. (4) Other specialty contractors performing a significant portion of the work. (5) Design professional responsible for project design. (b) Clearing and grubbing. Before grading is started, the entire right-of-way area shall be first cleared and grubbed of all trees, stumps, roots, brush, debris and other objectionable materials. Specific trees that are intended for preservation shall be indicated on the design plans and subject to the review and approval of the department. All clearing limits shall be marked and tree protection fence installed prior to the pre-construction meeting. All erosion control measures shall be installed as required by the approved plans and in accordance with this chapter. (c) Rough grading. (1) Grading activities shall be performed in accordance with the lines and grades shown on the approved construction plans. Grading plans shall include a plan view of the proposed roadway, showing existing and proposed contour lines at an interval of no more than two feet, as well as a profile of the street centerline and all applicable curve and design data. Grading plans shall outline those areas required to remain undisturbed (i.e., tree protection areas, buffers, etc.) and shall indicate protective fencing or staking to be placed surrounding such areas. (2) Cut or fill slopes shall not exceed three horizontal units to one vertical unit, unless otherwise approved by the director based on site-specific topographic and geotechnical conditions. Flatter slopes shall be provided, where possible, to better accommodate utility installation and maintenance activities. (3) Erosion and sediment control best management practices (BMPs) shall be installed in accordance with the approved construction plans, prior to or concurrent with all land disturbing activities. Alternate or additional BMPs may be required by the county inspector, if it is deemed that current measures do not provide adequate protection. ( 4) All suitable material from roadway cuts may be used in the construction of fills, approaches or at other places as needed. Excess or unsuitable materials, including organics, soft clay, etc., shall be removed from within the right-of-way and for a distance not less than one foot on each side of the road surface for each vertical foot of unsuitable material at the right-ofway line. (5) Fill material shall be placed in uniform horizontal layers or "lifts," not to exceed a compacted thickness of more than six inches. Moisture content shall be adjusted as necessary to compact material to 95 percent of maximum dry density. The top 12 inches of sub-grade material under any roadway, drive or parking area shall be compacted to 98 percent of standard proctor density. (d) Final grading and sub-grade preparation. (1) After rough grading, storm sewer and utility installation is complete and the back-fill in all such ditches is thoroughly compacted, the sub-grade shall be brought to the lines, grades, and typical roadway section shown on the plans. (2) All utility crossings shall be installed prior to sub-grade approval. If utility installation cannot be completed at this time, the developer shall coordinate the installation of casings or conduits to accommodate subsequent utility installation without disturbance to the sub-grade. Utility trenches cut in the sub-grade shall be backfilled and compacted as specified herein. The county inspector may require additional compaction tests at utility crossings to verify compaction. (3) Prior to sub-grade inspection and approval, the design professional shall certify in writing to the department that the lines and grades of the proposed street or streets are within six inches of design grades. This letter shall be submitted prior to sub grade inspection by county personnel. (4) Sub-grade testing and inspection: Subgrade compaction shall be tested by the county inspector, prior to construction of the graded aggregate base course. Compaction testing shall be accomplished by visual inspections of actual live axle loads, commonly referred to as a "roll test." The developer or contractor shall schedule all compaction tests with the county inspector no less than 24 hours in advance. The developer or contractor also shall provide an adequate testing vehicle, minimum 18-ton hauling capacity, fully loaded. All areas or sections of the sub-grade that do not pass visual live load compaction testing, at the discretion of the county inspector, shall be corrected. Once the developer or contractor makes all necessary corrections, it shall be his/her responsibility to re-schedule any and all subsequent roll tests. (5) Provisions shall be made to provide adequate drainage of the road surface during the course of construction, including temporary four-inch drain lines in all concrete gutters. (e) Graded aggregate base course construction. (1) The base course shall consist of graded aggregate, of a minimum thickness as required based on the street classification. Minimum base course thickness is provided in subsection 332-6(h). The base course shall be constructed in accordance with the lines, grades and typical cross sections shown on the approved construction plans. All aggregate materials shall be secured from GDOT- approved sources and shall comply with section 815 of the "Standard Specifications for the Construction of Transportation Systems," latest edition. (2) All base course material shall be spread uniformly with a mixture spreader, or other approved means, to the proper depth to obtain the required thickness. The maximum thickness of base course material to be placed in one course shall be six inches compacted. If the design thickness of the base course is more than six inches, it shall be constructed in two or more courses of approximate equal thickness. With sufficient and suitable equipment, the county inspector may allow base material to be placed in lifts up to eight inches. (3) The moisture content of the aggregate material shall be uniformly distributed and shall be adequate to allow compaction to a minimum of 100 percent of the maximum dry density based on the modified proctor method. Immediately following the spreading of the graded aggregate, all material shall be compacted to the full width by rolling with a smooth-wheel, vibratory roller weighing seven to ten tons, or an equivalent sheepsfoot packer. Rolling shall progress gradually from the edge to the center, parallel with the centerline of the street and lapping uniformly each preceding track by one-half the width of such track. Rolling shall continue until the entire surface is smooth, closely knit, free from cracks, conforming to the prescribed line, grade and cross section, within the limits specified. ( 4) Any irregularities, areas of segregation or depressions that develop under such rolling shall be corrected by loosening the material at these locations and adding or removing material until the surface is smooth and uniform. The application of water, applied uniformly over the base course, may be required to achieve adequate compaction. Shaping and rolling shall be performed alternately, as required to prepare a uniform compacted base. (5) Along curbs, headers, walls and at all locations not accessible to the roller, the base course material shall be compacted thoroughly with mechanical tampers or approved hand tampers. (6) No base material shall be deposited or shaped when the sub-grade is frozen, thawing, or during other unfavorable weather conditions. (f) Graded aggregate base course testing and inspection. (1) Cross section. The cross section and crown slope shall be verified at intervals or locations determined by the county inspector. The developer or contractor shall provide a string line and dedicated personnel to pull the line and allow verification measurements to be made by the county inspector. Those areas or portions of the roadway, which do not comply with the design cross section or crown slope, shall be corrected and verified by county personnel prior to base course approval. (2) Roll test. Base course compaction shall be tested by the department prior to the application of bituminous asphalt paving. Compaction testing shall be accomplished by visual inspections of actual live axle loads (roll test). The developer or contractor shall schedule all compaction tests with the county inspector no less than 24 hours in advance. The developer or contractor also shall provide an adequate testing vehicle, minimum 18-ton hauling capacity, fully loaded. All areas or sections of the base course that do not pass visual live load compaction testing, at the discretion of the county inspector, shall be corrected. Once the developer or contractor makes all necessary corrections, it shall be his/her responsibility to re-schedule any and all subsequent roll tests. (3) Prime coat. At the completion of base course construction, testing and approval by the county inspector; the base course shall be primed and sealed with 0.25 gallon of R.C. 70 per square yard. This requirement may be waived by the county inspector, if the placement of asphalt paving is anticipated within the following three to five days and prior to any significant rainfall event. ( 4) Additional inspections due to weather conditions. If a significant weather or rainfall event occurs following the approval of base construction but prior to asphalt paving, the county inspector may require additional roll testing to re-verify the structural integrity of the road base. The developer or contractor shall be subject to comply with such additional inspections, at the discretion of the county inspector. (g) Bituminous asphalt paving. (1) Bituminous asphalt production, handling, transportation and placement shall meet or exceed the requirements of the GDOT's "Standard specifications construction of transportation systems," latest edition and any amendments thereto. Asphalt pavements shall be of the superpave mix design, as specified herein; and the use of conventional mix designs will not be permitted, unless otherwise approved by the director. (2) Equipment. a. Mechanical pavers. Mechanical pavers used for the placement of hotmix asphalt shall be capable of spreading and finishing all courses to the indicated widths and depths, true to line, grade and cross section, and shall be capable of striking a smooth finish, uniform in density and texture. Mechanical pavers shall be equipped with extendable screeds, capable of spreading at the width of each travel lane in one pass. b. Compaction equipment. The compaction equipment must be in good mechanical condition and capable of compacting the mixture to the required density. The number, type, size, operation, and condition of the compaction equipment shall be subject to the approval of the county inspector. At a minimum, a smooth drum vibratory roller (minimum eight tons) and a separate pneumatictired roller shall be provided. An additional finish roller or larger equipment may be required by the county inspector, based on visual observations of surface texture or density tests. (h) Paving operations. (1) The county inspector will require that a copy of the detailed asphalt mix design be submitted prior to asphalt paving. Only asphalt produced by a GDOT-approved plant may be utilized. Plant production, transportation and paving operations shall be so coordinated that a uniform continuity of operation is maintained. If the spreading operations are interrupted for one hour or more, a transverse joint shall be constructed. Asphalt shall be delivered to the job site at a temperature that is within ± 20° F (± 11 ° C) of the temperature of the job mix formula. The county inspector may reject any asphalt load that does not meet temperature requirements, contains segregated material or does not comply with mix design requirements. (2) Weather limitations. The mixing and placement of bituminous asphalt pavement shall not be performed when the existing surface is wet or frozen. For all courses, the air temperature for placement of the mix shall be in accordance with the "Table of Air Temperature for Placing Asphalt Pavement." Table of Air Temperature for Placing Asphalt Pavement Minimum Temperature Lift Thickness (Inches) (OF) 1 or Less 55 1.1 to 2.0 45 Minimum Temperature Lift Thickness (Inches) (OF) 2.1 to 3.0 40 3.1 to 4.0 35 4.1 to 8.0 328 Note a: Temperature must be rising and base material may not be frozen. (3) Bituminous tack coat. Tack shall be applied prior to the placement and compaction of all subsequent courses of asphalt pavement, in accordance with GDOT Standards, Section 413. On curbed streets, the edge of the gutter shall be tacked to provide a water-resistant seal at the joint. Special care shall be taken to avoid the application of bituminous tack to portions of the curb and gutter that are to be visible following construction. (4) Wearing course must be placed at the earliest of the following times: a . Upon completion (final inspection) of principal structures on 80 percent of the buildable lots in the subdivision. b. Two years after recording of the final plat for the subdivision. c. At an earlier time by the mutual consent of the developer and the department. (5) Prior to installation of the surface pavement course and bituminous tack coat, the county inspector shall inspect existing asphalt pavement for damage from traffic and construction activities. Any areas found shall be repaired to the inspector's satisfaction prior to final paving. (i) Concrete streets. Concrete streets are not allowed. (j) Rural cross section. Certain local residential roads may be constructed without curb and gutter as provided in this chapter. On all such rural streets, the road base shall be extended one foot beyond the edge of the pavement. (k) Typical sections. All streets and roadways shall be constructed to the typical sections specified in the Rockdale County Standard Design and Construction Details, based on street classification category. (1) Copies of test results are to be made available to the county inspector as needed for verification of standards and specifications.