Sec. 20-84. Response to claim.
About this text
- As published by Municode, current through 2021-09-21
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Within 30 days of receipt of the written claim described in section 20-83, the person or firm against whom the claim is submitted may:
(1) Repair such damage at his or its own expense with the approval and supervision of the governing authority of the county or its designee. When repairs are completed to the satisfaction of the governing authority or its designee, the governing authority or its designee shall provide a written notification of satisfactory completion within five business days to the responsible person or firm and to the surety issuing the bond or the bank issuing the letter of credit, thereby terminating the claim.
(2) In the event of inclement weather or other factors preventing repair of the damage, request a 30-day extension to repair the damage from the governing authority of the county, provided that no extensions shall exceed 90 days from the date the claim was tendered. Approval of any extension shall be at the discretion of the governing authority of the county or its designee.
(3) Appeal the claim to the magistrate court of the county. Any such appeal must name the issuer of the bond or letter of credit as a party, who shall be served with all pleadings in the action and shall have the right to appear. The magistrate court will hear evidence and arguments within 30 days of the written appeal and issue a ruling within ten days of such hearing. Any such appeal shall toll the 30-day period, or any extension thereof, required by section 20-83. If the magistrate court rules in favor of the person or firm against whom the claim was made, the county shall have no right to recover any proceeds of the bond or letter of credit, and judgment shall be entered against the county. If the magistrate court rules in favor of the county the court shall determine the amount of damages to which the county is entitled to recover and enter judgment;
accordingly, the governing authority of the county shall be authorized to call the bond or letter of credit and recover from the proceeds thereof an amount equal to the judgment entered by the court, up to the total amount of the bond or letter of credit.
The portion of any judgment entered in favor of the county that exceeds the amount of the bond or letter of credit shall be subject to collection by any additional remedies at law or equity.
(b) In the event the person or firm against whom the claim has been submitted fails to take any of the actions allowed under subsection (a)(1), (2) or (3) of this section within the time required therein, such person or firm shall be deemed to have waived any and all rights to contest the call of the bond or letter of credit.
History
(Ord. No. 02092021, § 9, 2-9-2021)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.