(a) Requirements generally. No regulated activity will be allowed within the wetland protection district without written permission from the county board of commissioners in the form of a local development permit. Issuance of a local development permit is contingent on full compliance with the terms of this article and other applicable regulations. All activities that are not identified in subsection (b) of this section or by other local development ordinances shall be prohibited without prior issuance of a local development permit. If the area proposed for development is located within 25 feet of the wetland protection district boundary, as determined from the generalized wetland protection map, a U.S. Army Corps of Engineers determination shall be required. If the Corps determines that wetlands are present on the proposed development site and that a section 404 permit or letter of permission is required, a local development permit will be issued only following issuance of the section 404 permit or letter of permission. To find out whether the activity requires a 404 permit, or to request a jurisdictional determination from the U.S. Army Corps of Engineers, mail inquiries to:
U.S. Army Corps of Engineers Regulatory Branch P.O. Box 889 Savannah, Georgia 31402-0889.
1-800-448-2402
(b) Requirements within the wetland district setback. Prior to issuance of any development permit for any activity within 25 feet of a wetland, the applicant must include, with the site plans for the proposed action, documentation for which the following postdevelopment conditions will prevail at the site:
(1) The rate of stormwater runoff, volume of stormwater runoff, and peak runoff from the site will not exceed predevelopment levels.
(2) The amount of the following pollutants carried with runoff from the site will not exceed predevelopment conditions:
a. Phosphorus;
b. Nitrogen;
c. Zinc;
d. Lead.
In addition, biological oxygen demand (BOD) and turbidity (TSS) shall not exceed predevelopment levels.
(3) In addition to other fees assessed, the applicant may be held liable for costs incurred by the county enviornment control office during evaluation of the performance standards evaluation.
(c) Permissible uses (uses as of right). The following uses shall be allowed as of right within a wetland to the extent that they are not prohibited by any other ordinance or law, including laws of trespass, and provided that they do not require structures, grading, fill, draining or dredging except as provided in this article:
(1) Conservation or preservation of soil, water, vegetation, fish and other wildlife, provided that they do not affect waters of the state or of the United States in such a way that would require an individual 404 permit.
(2) Outdoor passive recreational activities, including fishing, bird watching, hiking, boating, horseback riding and canoeing.
(3) Forestry practices applied in accordance with best management practices approved by the state forestry commission and as specified in section 404 of the Clean Water Act.
(4) The continued cultivation of agricultural crops. Agricultural activities shall be subject to best management practices approved by the state department of agriculture and an undisturbed vegetated setback/buffer of 25 feet shall be maintained between the agriculture practice and the wetland.
(5) The pasturing of livestock, provided that riparian wetlands are protected, that soil profiles are not disturbed and that approved agricultural best management practices are followed, provided that there is an undisturbed vegetated setback/buffer of 25 feet between the pasturing activities and the wetland.
(6) Education, scientific research and nature trails.
(7) Temporary emergency permit. A temporary emergency permit can be issued by the county environment control office for the following reasons:
a. Maintenance or repair of lawfully located roads or structures and of facilities used in the service of the public to provide transportation, electric, gas, water, telephone, telegraph, telecommunication or other services, provided that such roads, structures or facilities are not materially changed or enlarged and written notice prior to the commencement of work has been given to the county environment office and provided that the work is conducted using best management practices to ensure that flow and circulation patterns and chemical and biological characteristics of the wetland are not impaired and that any adverse effect on the aquatic environment will be minimized.
b. Temporary water-level stabilization measures associated with ongoing agricultural operations.
c. Limited ditching, tilling, dredging, excavating or filling done solely for the purpose of maintaining or repairing existing drainage systems necessary for the cultivation of agricultural crops, provided that the maintenance or repair activity does not result in the impairment, alteration or loss of wetlands not previously subject to agriculture and agricultural use under the terms and provisions of subsection (c)(4) of this section.
d. Limited excavating and filling necessary for the repair and maintenance of piers, walkways, nature trails, observation decks, and wildlife management shelters, provided that they are built on pilings to allow unobstructed flow of water and preserve the natural contour of the wetland.
(d) Site plans. Applications for a local development permit within the generalized wetland protection district shall include a site plan, drawn at a scale of one inch equals 50 feet, with the following information:
(1) A map of all planned excavation and fill, including calculations of the volume of cut and fill involved, cross sectional drawings showing existing and proposed grades. Elevations, horizontal scale and vertical scale must be shown on the cross sectional drawings.
(2) A map of any wetland boundaries occurring within the site must be provided. This boundary may be included on other maps provided by the applicant.
(3) Location, dimensions and area of all impervious surfaces, both existing and proposed, on the site and adjacent to the site for a distance of 50 feet.
(4) The orientation and distance from the boundaries of the proposed site to the nearest bank of an affected perennial stream or water body.
(5) Elevations of the site and adjacent lands within 200 feet of the site at contour intervals of no greater than two feet; and no greater than one foot for slopes less than or equal to two percent.
(6) Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally released hazardous or toxic materials.
(7) All proposed temporary disruptions or diversions of local hydrology.
(e) Activities to comply with site plan. All development activities or site work conducted after approval of the site plan shall conform with the specifications of such site plan. The site plan may be amended only with the approval of the county environment control office which may require additional information deemed necessary to verify compliance with the provisions of this article or to evaluate the proposed use in terms of the purposes of this article.
(f) Subdivision approval in the wetland protection district. Any application for a subdivision approval shall include a jurisdictional determination approved by the U.S. Army Corps of Engineers. If the Corps determines that wetlands are present and that a section 404 permit or letter of permission is required, subdivision approval will be issued only following issuance of the section 404 permit or letter permission.
(g) Subdivision design options in the wetland protection district. Any subdivision that includes jurisdictional wetlands shall be allowed and encouraged to use the following options:
(1) Lot size averaging. Lot size averaging is encouraged in single-family detached subdivisions as a means to work around wetland areas. The county environment control office may allow a reduction in lot size, provided that the same number of lots in the same subdivision are oversized by an equal or greater area. The maximum permissible reduction shall not exceed 25 percent of the minimum required lot area.
The number of lots with areas reduced shall not exceed 25 percent of the total number of lots in the subdivision. The county environment control office shall allow no more than a 25 percent adjustment of rear, side and front setbacks for each affected lot.
(2) Cluster development. Clustering of residential development is encouraged. When considering subdivision approval, the county environment control office will allow incorporation of wetland or other significant natural areas as open space in the subdivision plan. Such plans should designate at least 25 percent of the gross land area as open space. Density shall be calculated by subtracting from the total acreage of a parcel all land dedicated or in use for private or public roads, including all vehicular rights-of-way. The resultant acreage will then be divided by the minimum allowed lot size of the district to derive the number of lots permissible.
(h) Filing fee. At the time of the application, the applicant shall pay a filing fee specified by the county environment control office. Filing fees up to a maximum of $180.00 may be required to evaluate the application. This fee may be used to retain expert consultants who will provide services pertaining to functional assessment, mitigation and wetland boundary determinations as deemed necessary by the county environment control office.
(i) Enforcement authority. The environment control officer is hereby established as the administrator of this article.
(j) Review procedures. The application shall be made to the environment control officer and will be reviewed within 30 days. The review period shall begin upon determination by the environment control officer that the application submitted is complete. The review period shall include the preparation of findings (approval or disapproval) by the environment control officer. The applicant will receive written notification of the findings of the county environment control office. If the review process is not completed within 60 days, the application is considered to be approved.
(k) Appeals. Decisions on permit applications made by the environment control officer may be appealed to the environment control office. The appeal must be made within ten days of the decision rendered by the environment control officer. A public hearing shall be held for appeals.
Public announcement of the hearing shall be printed in a local newspaper of general circulation at least 14 days prior to the hearing. Any person may offer testimony at the hearing. Decisions on permit applications made by the county environment control office may be appealed to the county board of commissioners. The appeal must be made within ten days of the decision rendered by the environment control officer. A public hearing shall be held for appeals. Public announcement of the hearing shall be printed in a local newspaper of general circulation at least 14 days prior to the hearing. Any person may offer testimony at the hearing. The decision of board of commissioners may be appealed to a court of competent jurisdiction, as discussed in section 26-118.
(l) Duration of permit validity.
(1) If construction described in the development permit has not commenced within 12 months from the date of issuance, the permit shall expire.
(2) If construction described in the development permit is suspended or abandoned after work has commenced, the permit shall expire 12 months after the date that work ceased.
(3) Written notice of the pending expiration of the development permit shall be issued by the environment control officer.
History