(a) The applicant shall notify the BOC and the zoning administrator requesting a letter of assurance for a solid waste facility as outlined in this article and participate in public meeting as required herein.

(1) The BOC shall give notice of the meeting published in a newspaper of general circulation at least once per week for two weeks preceding the date of the meeting.

The cost of publication shall be the applicant's responsibility.

(2) The notice shall state the time, place, and purpose of the meeting.

(3) The purpose of the public meeting shall be to discuss the waste management needs of the local government, to describe the siting process to be followed, to allow for public input, and to determine compliance with this article.

(4) The meeting shall be conducted by the county board of commissioners.

(b) The applicant shall submit to county board of commissioners and the planning and zoning commission eight copies of all information required by federal and state agencies for the facility for which it requests a county solid waste facility permit. The review procedure shall not begin nor shall the solid waste facility application be designated as complete until such time as all required data is submitted and the appropriate fees are paid. All information submitted shall reference the applicable ordinance and section and be in the same order as outlined in the ordinance.

(c) A designee of the board of county commissioners or the Zoning Administrator shall compile copies of all reports, applications, minutes of meetings, reports by consultants and similar materials. These materials shall be placed in one location with free access to the public and be made available for copying any portion or all of any document at cost.

(d) Within 60 days of the recommendation from the planning and zoning commission for a solid waste facility application, the county board of commissioners shall set a time for public hearing so that the applicant can present his plans and answer questions regarding the same.

(e) The applicant shall be required to pay for notice to be published at least twice in the county's legal organ prior to the hearing. Notice shall be published beginning at least seven but not more than 45 days prior to the date of the hearing. The notice shall state the time, place, and purpose of the hearing. Copies of all ads or a certification from the publisher must be submitted to the board prior to each hearing.

(f) Reserved.

(g) Once a completed solid waste facility application is submitted to the county the applicant shall be required to send a letter via first class mail to all adjoining property owners, as shown on the tax records of the county on the date of the application, and to all property owners where any portion of their property is within 1,000 feet of the boundary of the facility. This notice shall be required to state that the applicant is seeking a letter of assurance for a solid waste management facility. Certification of this notice must be provided to the board, along with a list of all owners prior to the public meeting for public comment on the completed application.

(h) Each completed solid waste facility application shall require an analysis conducted by the zoning administrator and a consultant or consultants, engineers and lawyers as selected by the county board of commissioners. The cost of consultants, engineers and lawyers shall be reimbursed to the county by the developer as outlined in section 62-115. The analysis shall be completed within 90 days from the day the application is determined to be complete.

The zoning administrator shall notify the applicant when the solid waste facility application is determined complete. The completed analysis of the completed solid waste facility application shall be presented to the planning and zoning commission by the zoning administrator and consultants within 30 days of the completed analysis. The planning and zoning commission can request additional time and information if needed to make a proper determination of the request because of its complexity. The planning and zoning commission shall determine if the solid waste facility application is consistent with the solid waste ordinance and recommend approval, deny or approve with conditions of the solid waste facility application to the BOC. In certain instances where the complexity of the application requires more than the usual 90 days for analysis, the zoning administrator, the planning and zoning commission and/or consultant may request an additional 60 days from the county board of commissioners, and the proponent has the option of requesting the county board of commissioners to extend the analysis period to allow time for responding to staff and/or consultant requests for additional information on a completed application.

(i) The zoning administrator and each consultant may make reports on the application to the county board of commissioners at their meetings.

(j) After the applicant has received approvals for the zoning conditional use, the subdivision major development plan and the recommendation from the planning and zoning commission for the completed solid waste facility application required in this article, the BOC shall call a public hearing as outlined in the following.

(k) The county board of commissioners shall call a public meeting for public comment on the completed solid waste facility application along with the analysis of zoning administrator, consultants and the recommendation of the planning and zoning commission. The purpose of this meeting shall be for public review of the completed solid waste facility application. The zoning administrator shall give notice by regular mail of the time and place of the public meeting to the owner and adjacent property owners as specified on the map.

Said notice shall be mailed not less than 14 days prior to the date specified thereon. Notice of a public meeting shall be posted by the applicant on the proposed facility property on each and every street of access not less than 14 days prior to the date specified thereon. Said posted notice shall be at intervals of not greater than 1,500 feet. The applicant shall also place notice in the county newspaper not less than 14 days prior to the dates specified thereon.

(l) At the public meeting for public comment the applicant shall again present its completed solid waste facility application, and any supplemental information requested by the board of commissioners. The board members shall have the opportunity to ask questions of the zoning administrator, consultants, any experts, the applicant, supporters and opponents. The hearing shall be transcribed or recorded so that it may be transcribed later if necessary. The applicant and supporters shall be granted equal time as opponents. The minimum time allowed per side is 15 minutes. The board may allow more time than the minimum if the application is complex, or the number of witnesses warrants a further extension. If the board determines that there are a great number of opponents with the same interest (for example, members of the same neighborhood), the board may require that a spokesman be designated. The opponents may also be represented by an attorney. The applicant, supporters and opponents shall have the right to provide testimony, including expert testimony, in support of their position. Each party shall have a reasonable opportunity to ask questions of the other side, in an orderly manner as controlled by the board.

(m) After the hearing and receipt of the final analysis, complete solid waste facility application, public comment, the recommendation of the planning and zoning commission, the departmental review and recommendation of the zoning administrator and consultants, screven county board of commissioners shall determine whether to accept the application, deny it, or accept it with modifications or conditions.

History

The history line the source prints at the end of the section.

(Ord. of 3-16-2021, § 2)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:screven-county/code/62-116@2021-06-08-ab530c5d07

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.