Sec. 34-112. Performance bonds.

About this text

  • As published by Municode, current through 2026-09-08
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

If the ponds are intended to be accepted by Stephens County, a performance bond is required prior to the issuance of a permit in the amount of 100 percent of the cost of construction of the stormwater management system. The developer or contractor shall be liable for all repairs and maintenance for a minimum of two year period after the project's completion date but prior to county acceptance. Prior to acceptance, the county will perform an inspection and said inspection shall not be performed any sooner than 18 months or later than 24 months from the project's completion date. The bond shall be held for a minimum of two years from the project's completion date or until all repairs noted in the final inspection have been corrected and approved by the county. If required repairs are not completed in time specified at inspection, bond may be used to complete repairs.

History

The history line the source prints at the end of the section.

(Ord. No. 2010-34-2, 10-12-2010)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:stephens-county/code/34-112@2026-09-08-70f63b3945

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Stephens County Code of Ordinances, Sec. 34-112. Performance bonds | Georgia Commons