Sec. 65-4. Road maintenance and improvement policy.

About this text

  • As published by Municode, current through 2026-09-08
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) New roads and streets will be accepted at the discretion of the Stephens County Board of Commissioners through a motion in an opening meeting and a formal acceptance and recording of right-of-way deeds. The county assumes no obligation to improve the quality or character of the roadway or street above that which was accepted for maintenance. Nothing in the section shall imply that any private road or street in the unincorporated area of the county will be accepted into the County Road System by the Stephens County Board of Commissioners. The following stipulations apply when accepting a private road into the county road system:

(1) Required submittals before consideration may occur:

a. A traffic impact study prepared by a Georgia-licensed professional engineer analyzing projected traffic volumes, level of service, sight distances, and access points.

b. A drainage study and plan showing all cross-lot drainage originating from the proposed county right-ofway, including calculations, flow paths, and proposed mitigation

measures to prevent adverse impacts on adjacent properties.

(2) A developer may not petition the county for road acceptance and maintenance

until at least 90 percent of the total lots/units in the development are built and issued certificates of occupancy, or upon specific approval by the board of

the commissioners.

(3) A developer must provide right-of-way deeds for the road with a minimum of

60-foot deeded right-of-way, where possible, and upon the discretion of the board of commissioners, to be voted upon for recording in an open meeting at the

time the road is to be considered for acceptance into the county road system.

(4) A developer must ensure that any signage or traffic control markings comply with the current edition of the Manual

on Uniform Traffic Control Devices

(MUTCD).

(5) Prior to acceptance, the county shall conduct a final inspection, for which the cost is to be paid by the developer, which must confirm that:

a. The road meets all county standards, including the following:

1. Base layer: A minimum of six inches of graded aggregate base

(GAB).

2. Binder layer: A minimum of two inches of (19mm) asphalt binder course.

3. Surface layer: A minimum of one and one-half inches of (9.5mm) asphalt surface course.

b. There are no significant defects, including potholes, cracking, drainage issues, or other structural failures.

c. Proper drainage infrastructure, sidewalks (if applicable), and other required improvements are complete and in line with the submitted drainage study.

(6) A developer must maintain all roads within the development, including repairs, until the county formally accepts them.

(7) If a developer fails to maintain the roads properly, the county may withhold building permits or certificates of occupancy until the necessary repairs are made.

(b) Existing county roads and streets located within dedicated rights-of-way accepted by the county shall be maintained at a reasonable level of service so as to provide egress and ingress to abutting property owners; however, the county shall not be obligated to widen, pave or make other improvements to such roads and streets which increase the value of the abutting property.

(c) Existing roads and streets which have become public through the operation of prescriptive rights of the public users, and on which maintenance work has been historically performed by the county, shall continue to be maintained by the county to a level of service that will provide reasonable egress and ingress to abutting properties; however, the county shall not make substantial improvements on such roads and streets until appropriate rights-of-way have been granted, accepted and properly filed for record.

(d) Existing private roads, streets and driveways shall not be maintained by the county, nor shall new private roads and streets be constructed by the county. However, safety of the traveling public is a high priority, therefore, from time to time it may be desirable in the interest of safety to perform a limited amount of maintenance to provide positive drainage and sight distance at private road, street, and driveway approaches.

This act shall not obligate the county to perform future maintenance at these locations.

(e) With respect to road and street improvements, the county recognizes its responsibility to expend public funds for road and street improvements on roads which are primarily intracounty traffic conductors. With respect to the improvement of residential streets and other roads primarily residential in nature, it shall be the policy of the county to assign priority to those roads and streets where the benefiting property owners substantially contribute to the payment of the cost of improvements.

(f) In the event that an outside contractor or utility company damages a county street through boring or installation, the following standards shall apply for repair:

(1) Note #1: At their expense, they shall mill two inches in depth (+/- 100 feet x +/- 20 feet) at bump, and 50 feet on each side of the bump location. They shall replace

with two inches of the same type material as the existing surface (following GDOT paving standards) or as directed

by the county. Restriping of the roadway is required at the repair area.

(2) Note #2: If asphalt is removed and does not meet required depth at bore location when milled, the bore location must be

repaired according to GDOT Standard 1401 or as directed by the county.

(3) Note #3: The repaired area must be left two inches below the top of the surface

coarse to allow for Note #1 or as directed by the county. If dip in roadway occurs, the same repair shall be used as stated in Note #2 and Note #3.

(4) The county shall be given 48 hours' notice before repair work is scheduled.

All repair work shall be completed by a GDOT-approved contractor.

History

The history line the source prints at the end of the section.

(Ord. of 11-10-2020; Res. No. 2026-25, 9-8-2026)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:stephens-county/code/65-4@2026-09-08-0c242c5366

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Stephens County Code of Ordinances, Sec. 65-4. Road maintenance and improvement policy | Georgia Commons