(a) A collocation application entitled to streamlined processing under article VIII, subsection 75-50(a)(6) shall be deemed complete unless the

county notifies the applicant within 30 days of submission (or within some other mutually agreed upon timeframe) that the submission is incomplete. Notices of application incompleteness shall identify specifically the deficiencies in the application, which, if cured, would make the application complete. Upon notice of deficiency, the timeline for a decision shall be tolled until the applicant

resubmits to correct such deficiency. The county shall, within ten days of resubmission, notify the applicant of continuing deficiencies or the application will be deemed complete. The timeline for a decision shall be likewise tolled during the additional resubmission deficiency period until the second resubmission. Approval or denial of a

complete application shall be in writing and shall be postmarked to the applicant by the sixtieth day after the initial submission, excluding any tolling period.

(b) A collocation application entitled to streamlined processing other than under article VIII, subsection 75-50(a)(6) shall be deemed complete

unless the county notifies the applicant within 30 days of submission (or within some other mutually agreed upon timeframe) that the submission is incomplete. Notices of application incompleteness shall identify specifically the deficiencies in the application, which, if cured, would make the

application complete. Upon notice of deficiency, the timeline for a decision shall be tolled until the applicant resubmits to correct such deficiency.

The county shall, within ten days of resubmission, notify the applicant of continuing deficiencies or the application will be deemed complete.

The timeline for a decision shall be likewise tolled during the additional resubmission deficiency period until the second resubmission. Approval or denial of a complete application shall be in writing and shall be postmarked to the applicant by the ninetieth day after the initial submission,

excluding any tolling period.

(c) Upon resubmitting of the revised application the county shall follow the process identified in this section, above, until all deficiencies identified are deemed cured.

(d) If the county does not respond in writing to the applicant for a collocation under this section 75-80 as set forth above within the specified timeframe under this section 75-80 as set forth above, then the application shall be deemed approved. If the county does not respond in writing to the applicant for a collocation under section

75-81 below within the specified timeframe under section 75-81 below, the applicant has available the remedies established by federal regulations.

(e) Application entitled to the streamlined review process shall not be subject to design or placement requirement, or public hearing review.

All applications shall be initially submitted to the planning department for review and processing.

History

The history line the source prints at the end of the section.

(Ord. of 3-10-2015)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:stephens-county/code/75-80@2026-09-08-fd806512a8

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.