Sec. 50-75. Inspection; installation of required culverts.

About this text

  • As published by Municode, current through 2026-03-17
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Upon receipt of the information required by section 50-74, the county public works director (CPWD) shall, within two days, inspect each such site to determine if a culvert is required to provide ingress and egress from the county road to the tract and, if so, the length and diameter of the culvert. Should a culvert be required, it shall be installed at the expense of the applicant under the supervision of the CPWD. Applicants shall have the right to remove any culvert

installed by them upon completion of the tree removal.

(b) After the initial inspections, the CPWD will complete the condition of road report and send a copy to the applicant and a copy to the county administrator of the county (CA). The CPWD will keep the original.

History

The history line the source prints at the end of the section.

(Ord. of 12-12-95, § 3; Ord. of 11-13-18(3), § 1)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:sumter-county/code/50-75@2026-03-17-46f94833de

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Sumter County Code of Ordinances, Sec. 50-75. Inspection; installation of required culverts | Georgia Commons