(a) If, on or before the 15th day as described in section 70-96, the county deems an application complete, the county shall approve or deny said completed application within 14 calendar days of the county's determination of completeness, unless a joint meeting between the applicant and the county is deemed reasonably necessary by the county. (b) If a joint meeting is deemed reasonably necessary by the county, the joint meeting shall occur within 15 calendar days of the county's issuance of the notification of completion. The joint meeting shall include: (1) Where the applicant is going to conduct work; (2) When the work will be conducted; (3) What type of work will be performed; (4) Who the county may contact for specific details or related questions; and (5) Any permit seeking approval under the application. Following a joint meeting between the applicant and the county, the county shall deny or approve the application within 14 calendar days of such meeting. (c) Upon the county's final approval of an application, any required permit shall be deemed issued.