Sec. 26-3. Permit required.

About this text

  • As published by Municode, current through 2019-11-04
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

All utility companies are required to obtain a permit for use of county rights-of-way. Any permit for which the work is not completed in a three-month period shall be voided, to require an additional permit.

History

The history line the source prints at the end of the section.

(Ord. of 11-6-2000)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:talbot-county/code/26-3@2019-11-04-a80471f173

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Talbot County Code of Ordinances, Sec. 26-3. Permit required | Georgia Commons