Towns County · Code of Ordinances
Part II - CODE OF ORDINANCES / Chapter 40 - SUBDIVISIONS / Article III - PROCEDURES AND REQUIREMENTS FOR APPROVAL OF PLATS
Sec. 40-76. Review of preliminary plat.
About this text
- As published by Municode, current through 2019-07-26
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) The chairman or a designated member of TCPC shall check the plat for compliance with these and other relevant county regulations and ordinances and report findings and recommendations to the TCPC in public session. However, a review and/or of approval of the preliminary plat shall not be construed to mean that the plat meets all requirements as set forth within those regulations. It is the responsibility of the owner or developer to secure all access requirements and comply with all rules and regulations. The planning commission may rely on representations on the plat and those made by developer and/or representatives as being true and correct; however, this reliance does not bind the planning commission to approval or acceptance as to any terms and conditions which may later be determined to be incorrect.
(b) No preliminary plat shall be acted upon by TCPC except in public session. Such sessions or hearings must be held at least monthly and are generally held on the second Monday of each month. The field representative is not empowered to act or speak for the TCPC in approving or disapproving preliminary plat requests.
(c) TCPC shall take no action on a preliminary plat if the applicant or a designated representative is not present at the hearing.
(d) At the public hearing the TCPC shall take one of the following actions, which shall be recorded, with reason for disapproval where appropriate, in the minutes:
(1) Approve the preliminary plat.
(2) Approve the preliminary plat on conditions that necessary modifications are made (such required modifications must be recorded on the plat and in the minutes).
(3) Disapprove the preliminary plat.
(4) Table. A vote on a preliminary plat may be tabled twice then the planning commission must take action as set forth in subsections (1) through (3) of this section.
(e) The action of the TCPC shall be noted on two copies of the preliminary plat. One annotated copy of the plat shall be returned to the subdivider or agent and one copy permanently filed in TCPC records. Both must clearly record approval or disapproval and reasons for disapproval.
(f) All preliminary plat approvals shall be limited by these qualifications.
(1) The approval is a tentative approval only, pending submission of a final plat.
(2) The approval is valid for one year and maybe extended for six months if requested, and shall be null and void after that date. However, all extensions must be requested prior to the expiration of the current approval period. Second six-month extension is only for good cause shown and may not be due to delay of developer). If final plat is not received by the end of this period a new preliminary plat request shall be submitted before a final plat request can be accepted.
(g) Preliminary plat approval constitutes authorization for subdivider to advertise to begin physical improvement to property being subdivided, and to request land disturbing permit.
(h) Posting of permits. Before work begins on a subdivision, a copy of the preliminary plat permit along with a copy of the erosion and sediment control permit must be posted at the site in view to eliminate confusion which may arise regarding the obtaining of the proper permits.
(Amdt. of 5-21-2015, § 404)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.