(a) Required. All streets, roads, and alleys shall be graded by the subdivider in such a manner that pavements and other improvements (sidewalks and curb and gutter, if provided or required) can be constructed to the required cross section. The minimum width of grading shall be the pavement width as specified in section 78-379, plus six feet on each side measured from the back of curb or pavement edge. Deviation from the this section will be allowed only when due to special topographical conditions. (b) Preparation. Before grading is started the entire right-of-way area shall be first cleared of all stumps, roots, brush, and other objectional materials and all trees not intended for preservation. (c) Cuts. All tree stumps, boulders, and other obstructions shall be removed to a depth of two feet below the subgrade. Rock, when encountered, shall be scarified to a depth of 12 inches below the subgrade. (d) Fill. All suitable material from roadway cuts may be used in the construction of fills, approaches, or at other places as needed. Excess materials, including organic materials, soft clay, etc., shall be removed from the roadway. The fill shall be spread in layers not to exceed 12 inches, loose and compacted. The filling of utility trenches and other places not accessible to the roller shall be mechanically tamped. (e) Subgrade. The subgrade shall be properly shaped, rolled and uniformly compacted to conform with the lines, grades, and typical cross sections as shown on drawings, if required, and approved by a department or official designated by the county commissioners. Unsuitable material shall be excavated and replaced with acceptable compacted material.