Each user of the Authority's sewer system will be levied a charge for payment of bonded indebtedness of the Authority and for the user's proportionate share of the operation, maintenance, and replacement (OM&R) costs of the sewer system. A surcharge may be levied against those users with wastewater that exceeds the strength of normal wastewater. (1) The OM&R user charge will be computed from a base charge plus a surcharge. The base charge will be the user's proportionate share of the costs of OM&R for handling its periodic volume of normal wastewater plus the user's share of the bond amortization costs of the Authority. (2) Computation of charges. Each user's share of OM&R costs will be computed by the following formula: Cu = Ct (Vu) Vt Where: Cu = User's charge for OM&R per unit of time. Ct = Total OM&R cost per unit of time, less cost recovered from surcharges. Vt = Total volume contribution from all users per unit of time. Vu = Volume contribution from a user per unit of time. (3) Bonded indebtedness charges. Each user's share of bonded indebtedness costs will be based on a schedule which reflects the user's volumetric and/or waste strength contribution to the system. (4) User surcharges. The surcharge will be the user's proportionate share of the OM&R costs for handling its periodic volume of wastewater which exceeds the strength of BOD5 , SS, and/or other elements in normal wastewater as defined by section 28-419. The amount of the surcharge will be determined by the following formula: Cs = (Bc x B + Sc x S + Pc x P) 8.34 Vu Where: Cs = Surcharge for wastewaters exceeding the strength of normal wastewater expressed in dollars per billing period. Bc = OM&R cost for treatment of a unit of BOD5 expressed in dollars per pound. B = Concentration of BOD5 from a user above that of normal wastewater, expressed in mg/l. Sc = OM&R cost for treatment of a unit of SS expressed in dollars per pound. S = Concentration of SS from a user above that of normal wastewater, expressed in mg/l. Pc = OM&R cost for treatment of a unit of any pollutant which the POTW is committed to treat by virtue of an NPDES Permit or other regulatory requirement, expressed in dollars per pound. P = Concentration of any pollutant from a user above that of normal wastewater, expressed in mg/l. Base levels for pollutants subject to surcharges will be established by the Authority. Vu = Volume contribution of a user per billing period in million gallons based on a 24-hour average for billing period. a. The concentrations of any pollutant of an industrial user and the volume contribution of that user shall be calculated from discharge monitoring reports subject to verification by the Authority, from records maintained by the industrial user, and from reliable information obtained from any other source. b. The values of parameters used to determine user charges may vary from time to time. Therefore, the Authority is authorized to modify any parameter or value as often as is necessary. Review of all parameters and values shall be undertaken when necessary, but in no case less frequently than annually. (5) Pretreatment program charges. Industrial users may be required to pay a separate pretreatment program charge. The pretreatment program charge will be based on the user's proportional share of the costs of administering the POTW pretreatment program, which includes costs incurred by the Authority for verification monitoring, analysis, and reporting. Each user's share of the pretreatment program costs will be computed by the following formula: Cu = Ct (Vu) Vt Where: Cu = User's charge for POTW pretreatment program per unit of time. Ct = Total POTW pretreatment program costs per unit of time. Vt = Total volume contribution of permitted industrial users per unit of time. Vu = Volume contribution from a permitted industrial user per unit of time. (6) Multi-unit complexes. To provide more equality between single-family and multi-unit dwellings (with just 1 or less number of water meters than the total number dwelling units in complex), sewer service charges to multi-unit apartment complexes served by master meters or any combination of meters totaling less than the number of units served shall be charged by the following formula: U[adj] x S[c] x O[c] Where: U[adj] = U[tot]/O[c] U[tot] = Total usage of individual meter or master meter. O[c] = The number of units served by the referenced meter times a 90 percent occupancy rate. S[c] = The user charge as detailed in this section.