Washington County · Code of Ordinances

Part II - CODE OF ORDINANCES / Chapter 26 - PUBLIC PROPERTIES / Article II - COUNTY RIGHTS-OF-WAY / Division 3 - RESIDENTIAL AND COMMERCIAL DRIVEWAYS

Sec. 26-111. General restrictions.

About this text

  • As published by Municode, current through 2026-07-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

No driveway approach or other improvements constructed on county ROW, as an exercise of the permit, shall be relocated or have its dimensions altered without the written permission of the county.

(1) A letter from the county approving the change should be obtained by the applicant who received a copy of the original permit.

(2) Parking is prohibited on county ROW except those instances where a temporary conditional special encroachment permit is approved for parking on the county ROW.

(3) Driveways should not be provided within the county ROW for purposes of parking, loading, servicing, etc.

(4) Geometric and safety requirements shall be maintained as stipulated in the permit and shall not be altered by the applicant.

(5) The applicant must take possession of an approved permit within 60 days of approval.

If not, the permit will be canceled.

(6) Work under the permit shall begin within 90 days after approval. Failure to begin work will be cause for the permit to be canceled.

(7) Construction work authorized by an approved permit shall be completed within 12 months following approval of the permit. Permitted work not completed within 12 months, for just reasons, may be officially extended, by the county, for an additional six months. If the permitted work is not completed, action will be taken to secure the bond, escrow or letter of credit in order to complete the work or restore the county ROW.

(8) Once a permit has been canceled or voided, it cannot be reactivated or reinstated for any reason. A new permit must be submitted when the applicant is ready to begin work. This also includes the appropriate number of copies of up-to-date plans and all related documentation needed to review the application.

(9) New driveways to new businesses should not be opened for use by the traveling public until the final inspection and release of any bond or escrow by the county. In order to insure a timely release, the applicant is encouraged to coordinate all phases of work with the county.

§ 26-110

(10) It is the responsibility of the property owner to provide routine maintenance of the commercial driveway up to the roadway edge of pavement without making improvements to it as governed by the permit process. Maintenance or replacement of the side drain pipe installed by the permittee will be their responsibility.

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.