Sec. 14-51. Pavement standards.
About this text
- As published by Municode, current through 2026-05-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) The following Georgia DOT Specification Sections shall apply to alternative base materials indicated on the standard detail typical road sections:
(a) Soil cement base;
(b) Chert construction;
(c) Concrete pavement.
(2) The engineering study will include traffic counts for the anticipated completed development. For flexible pavements and
totally rigid pavements use the AASHTO Guide for Design of Pavement Structures. For partially rigid pavements (soil cement with asphaltic concrete overlay) use the PCA Thickness Design
for Soil-Cement Pavements and SoilCement Construction Handbook. All specifications for the materials and
construction of the proposed design are required to be submitted.
(a) Pavement design period to be 20 years;
(b) Minimum AADT for design purposes:
Residential streets + 4% annual growth rate 2,500 AADT (minimum 0.5% truck volume) Non-residential streets and collector streets + 4% annual growth rate determined by traffic counts (minimum 2.0% truck volume) Arterial + 6% annual growth rate determined by traffic counts (minimum 1.5% truck volume)
(c) Minimum asphaltic concrete thickness is to be not less than 1 /2 inch
after compaction.
(d) Minimum portland cement concrete thickness is to be not less than four inches after compaction.
(e) Minimum soil cement thickness is to be not less than six inches after compaction.
(f) Minimum graded aggregate base is not to be less than six inches after compaction.
(g) Minimum bituminous material base is not to be less than two inches after compaction.
History
(Res. of 6-9-03, § 4-6)