Whitfield County · Code of Ordinances
Chapter 15 - UNIFIED SUBDIVISION REGULATIONS / Article II - PROCEDURE FOR PLAT SUBMITTAL AND APPROVAL
Sec. 15-26. Submittal, review and approval procedure for a major subdivision.
About this text
- As published by Municode, current through 2026-05-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) Preliminary plat. Following a presubmittal conference but before any grading, site development, or construction shall commence, the developer/subdivider shall submit a preliminary plat, as follows:
(a) A preliminary plat and site plan which has been prepared in accordance with
subsection (g) of this section, together with prescribed fee, shall be submitted to the Whitfield County Engineer. A
minimum of six copies of the preliminary plat (eight copies where the subdivision is proposed for access to a state highway) and supporting documentation shall be
submitted. The submission shall occur not less than 15 working days prior to the meeting date of the planning commission at which the developer/subdivider desires preliminary plat review and
approval.
(b) If access to a state highway is proposed then the Georgia Department of
Transportation (GDOT) shall receive two copies of the proposed plat to determine the feasibility of such access in accordance with O.C.G.A. § 32-6-150 et seq. The
planning commission and/or the Whitfield County Engineer shall include any requirements of the Georgia Department
of Transportation (GDOT) in any action taken upon such proposed plat.
(c) In the event that the developer/subdivider desires or is required to obtain approval
of the Federal Housing Administration (FHA,) Housing and Urban Development (HUD), or other federal or state agency, such approval shall be secured prior to the submission of a preliminary plat, if possible. If such permission is not secured prior to the submission, the time period
for preliminary plat approval may be required to be extended.
(d) All applicable county departments shall conduct individual reviews of the plat.
The Whitfield County Engineer shall review the plat for compliance with minimum preliminary plat specifications set forth at subsection (g) of this section and with any other provision of this
chapter.
(e) Within 30 days after the date of review by the planning commission, the
preliminary plat shall be approved or disapproved. If the planning commission shall fail to act within 30 days following the date of review, such plat shall be
deemed approved preliminarily; provided, however, the developer/subdivider may waive this requirement and consent in writing to an extension of the period.
(f) The grounds for disapproval of any preliminary plat shall be stated in writing upon the records of the planning commission and a copy of the grounds
provided to the applicant. After official action by the planning commission, a letter shall be issued by Whitfield County or its designee to the subdivider notifying the subdivider of the official action.
Any conditions attached to the official action shall be stated, and if the preliminary plat is denied, the reasons for denial shall also be stated.
(g) Preliminary plat specifications. The preliminary plat shall be prepared by a Georgia Registered Land Surveyor; if a professional engineer contributed to the plat, then such shall be indicated upon the plat. The plat shall be drawn at a scale not smaller than 100 feet to one inch. However, where the size of the proposed subdivision exceeds 100 acres, the scale may be no smaller than 200 feet to one inch. The plat shall be drawn in permanent ink upon reproducible material and unless specifically waived, in whole or in part by the Whitfield County
Engineer, shall include:
1. The proposed name of the subdivision, new roads and existing roads;
2. The name, address, and telephone number of the person to be notified of action;
3. The name, address, and license number of the registered land surveyor responsible for the preparation of the plat;
4. The graphic scale, north arrow, and date of plat preparation;
5. The total acreage in single parcel ownership by the developer/ subdivider, the total number of acres being subdivided, the total number of lots created, and the total length of roads;
6. A general location map at a scale not less than one inch equals 1,000 feet, showing the proposed development in relation to other adjacent properties and existing roads in
Whitfield County;
7. The location, zoning classification(s), and dimensions of all boundary lines
of the parcel to the nearest hundredth of a foot and the deed record names of adjacent owners or subdivisions shall be identified;
8. The location and dimensions of existing rights-of-ways, easements, streams, drainage structures, or utilities, buildings, bridges, lakes, and lands subject to flooding; if
applicable, the 100-year floodplain should be shown;
9. Topography by contours at vertical intervals of not more than five feet;
prominent drainage features, such as lakes, depressions, streams, etc., which may affect subdivision design shall be shown; engineering data showing the high water elevation and how it was established shall be submitted with the plat. The contour requirement may be waived or the interval adjusted up or down based upon the need, as determined by the Whitfield County Engineer;
10. A master drainage plan shall be submitted with technical design criteria;
11. The layout and scaled dimensions of all lots and roads; the location, purpose, and dimensions of all existing and future drainageways and easements;
12. The location and dimension of all areas proposed to be set aside for recreation use, open space, green space, or other public use, with designation of the purpose thereof, and conditions, if any, of the dedication or reservation;
13. The centerline profile of all proposed roads showing natural and finished
grades and proposed road names, and a cross-section of the proposed road design;
14. Front and rear structure or building setback lines;
15. There shall be a statement upon the plat to indicate whether the applicable water service to the proposed development shall be by individual water supply or by public treated water and whether the applicable sewage disposal service shall be by on-site sewage management systems or by sanitary sewer.
Sanitary sewer main size and water main size shall be determined by the appropriate utility;
16. Environmentally sensitive areas:
location of major river corridors, water supply watersheds, groundwater recharge areas, wetlands, the boundary and elevation of the 100-year floodplain, as determined by past history of flooding or the best available data;
17. Locate and size all drainage areas and future drainage tiles affecting the proposed subdivision;
18. Where a proposed subdivision is to be developed in phases with additional plat(s) to be submitted later, a preliminary plat shall be accompanied by a future tract plan, depicting reasonably the entire lot or parcel to be divided, the future road system, and topography thereon.
(2) Final plat. Subsequent to approval of the preliminary plat, a developer/subdivider shall submit a final plat, which is in conformity with the previously approved preliminary plat, to the Whitfield County Engineer, pursuant to the following sequence of submittal, review, and approval:
(a) Before a final plat is submitted, all public utility extensions or public or private
roads which were approved in the preliminary plat shall be completed in accordance with approved Whitfield County standards, and certificates of satisfactory completion have been obtained from appropriate authority(ies).
In lieu thereof, the developer/subdivider may submit a performance bond, irrevocable letter of credit, or funds in escrow in an amount not less than 110 percent of the estimated expenses of construction to proper standards and shall complete construction within one year of the issuance of the first building permit for a lot or parcel along such road. Under such
circumstances, the developer/subdivider shall indemnify Whitfield County, including, but not limited to all elected officials, employees, agents, attorneys, and anyone acting on behalf of Whitfield County from any and all liability associated with any failure of the developer/ subdivider in connection with his or her status as a permit holder with NPDES.
(b) A minimum of six copies of the final plat and site plan and all supporting
documentation shall be submitted within two years from the date of approval of the preliminary plat; if final plat approval is not sought within two years of
preliminary approval, a preliminary plat must be resubmitted.
(c) If the developer/subdivider places restrictions upon any of the lots or parcels contained in the subdivision greater than
those required by this chapter, such restrictions or reference thereto shall be identified upon the plat.
(d) Approval procedures. Within ten working days after submittal of the final plat and site plan and all supporting documentation, data, and certifications, the final plat and/or site plan shall be approved or disapproved by the Whitfield County
Building, Zoning and Development Department. If no action is taken within such period, the plat shall stand approved.
The Whitfield County Building, Zoning and Development Department may disapprove any such final plat if any portion of the proposed subdivision is in violation of any applicable ordinance, law, rule, or
regulation of any governmental unit having jurisdiction.
(e) Approval of the final plat and/or site plan by the Whitfield County Building, Zoning
and Development Department shall not be deemed an acceptance by the county or the public of the dedication of any road, right-of-way, or other real property shown upon the plat or site plan. The
developer/subdivider must prepare deeds of conveyance for each right-of-way or other public space and separate action is required by the Whitfield Board of Commissioners to accept such deeds of conveyance.
(f) Completeness. If any of the specifications or facts required herein are omitted or
misrepresented, the Whitfield County Building, Zoning and Development Department or the planning commission may refuse to review such plat and may return such submittal to the developer/ subdivider for completion or revision.
(g) Approval duration. Construction drawings shall be submitted within one year of preliminary plat approval. If construction has not commenced within one year of plat approval, said approval shall expire unless extended in writing by the Whitfield County Engineer. If such approval shall expire, then a new preliminary plat
must be submitted in accordance with then-current regulations.
(h) Final plat specifications. The final plat shall be prepared by a Georgia Registered
Land Surveyor. If a professional engineer, licensed to practice in Georgia, shall
contribute to the plat, then appropriate seals shall be shown. The plat shall be drawn at a scale appropriate to show details but no smaller than 200 feet to one inch. The plat shall be drawn in permanent ink on reproducible material upon a sheet or sheets not exceeding 17 by 22 inches, in compliance with Georgia law, and unless specifically waived in whole or in part by the Whitfield County Engineer, shall include:
1. The name of the subdivision and road names;
2. The name, address, and telephone number of the person to be notified of action;
3. The name, address, seal, and license number of the registered land surveyor; the original signature of the surveyor shall be across the seal for the plat to be valid; also, professional engineers or civil engineers, if appropriate;
4. The date of the plat drawing, graphic scale, north point, notation as to the reference of bearings to magnetic, true north, or grid north and indication whether bearings shown are calculated from angles turned or
taken from compass readings;
5. The location of the parcel (land district and land lot) giving total acreage being subdivided, total number of lots created and total length of new roads within the development;
6. A general location map at a scale not less than one inch equals 1,000 feet, showing the relationship of the plat to other existing roads and properties in Whitfield County;
7. The index map where more than one sheet is required to present the plat (Note: multiple sheets shall each be named to conform with the title sheet and designated, for example: one of three, two of three, and three of three);
8. Identify the point of beginning (POB) tied to the nearest existing road intersection or nearest land lot line or district line;
9. Exact boundary lines and zoning classification(s) of the parcel shall be in compliance with the Georgia Plat Act, O.C.G.A. § 15-6-67;
10. City, county or land lot lines accurately tied to the lines of the subdivision by distance and angles when such lines traverse the subdivision;
11. Road center lines, showing angles of deflection and standard curve data of intersection, radii, length of tangents and arcs, and degree of curvature;
12. Lot lines with dimensions to the nearest one-hundredth foot and bearings to the nearest minute, arcs, and chords and tangent or radii of
rounded corners;
13. Front and rear structure or building setback lines; side setback lines may be noted upon the survey, but
shall not be required to be shown upon each lot;
14. Lots or parcels numbered in numerical order or numbered in relationship to each phase of development;
phase development lines;
15. A master drainage plan shall be submitted to the Whitfield County Engineer with technical design criteria, as set forth herein. Location, dimensions and purpose of all drainage structures and of any easements; including slope easements, and public service utility right-ofway lines, and any areas to be reserved, donated, or dedicated to
public use or sites for other than residential use with notes stating their purpose and limitations; and of any areas to be reserved by deed covenant for common uses of all property owners;
16. Final sanitary sewer easements (if applicable) with existing manhole locations;
17. Final water supply system easements (if applicable) with location of existing fire hydrants;
18. Locations of monuments and markers to the degree of accuracy required of professional engineers and/or
registered land surveyors pursuant to Georgia law;
19. The boundary and elevation of the 100-year floodplain as determined by F.I.R.M. and/or best available data, as determined by the Whitfield County Engineer;
20. Applicable certificates and statements as specified in this chapter;
21. If restrictions apply to the subdivision, then such restrictions shall be shown or noted on the final plat;
22. The location and dimension of all areas proposed to be set aside for recreational use, open space, green space, or other public use, with designation of the purpose thereof, and conditions, if any, of the dedication or reservation;
23. The Whitfield County Tax Assessor's map and parcel numbers for G.I.S. purposes;
24. A complete list of any deviation(s) from the approved preliminary plat.
i. Final plat certificates of approval. Each final plat submitted shall carry certificates of approval appropriate to the particular
development and signed by the appropriate departmental authorities. The following certificates may apply; if not, then statements appropriate to the development may be prepared after consultation with the Whitfield County Engineer:
1. Certificate of Ownership—Public Dedication I (we) hereby certify that I am (we are) the owner(s) of the property shown and described hereon and that I (we) hereby adopt this plan of subdivision and restrictions thereto.
I (we) further certify that it is our intent to dedicate to Whitfield County, at the appropriate time all rights-of-way, easements, roads, drains, and public grounds shown hereon.
Owner:
Date:
2. Certificate of Ownership—Private Road System I (we) hereby certify that I am (we are) the owner(s) of the property shown and described hereon and that I (we) hereby adopt this plan of subdivision [adopt restrictions applicable thereto], and establish a property owner's association, (name) to retain and to maintain for private use all roads, parks, drains, easements, and common grounds, shown hereon.
Owner:
Date:
3. Final Accuracy and Design Certificate It is hereby certified that this plat is true and correct and was prepared from an actual survey of the property made by me or under my supervision: that all monuments shown hereon actually exist and their location, size, type, and material are correctly shown; and that all requirements of the Whitfield County Subdivision Regulations have been
fully complied with, and approval hereof does not relieve me of any liability associated with inaccuracies or improper design.
By:
Registered Georgia Land Surveyor No. and Seal Date:
4. Certificate of Approval for Public Water System I hereby certify that the water system serving the public roads on this final plat has been installed (or sufficient surety has been provided to install) in accordance with the requirements of Dalton Utilities.
Dalton Utilities:
Date:
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.