(a) General provisions. Excessive soil erosion and resulting sedimentation can take place during land-disturbing activities if requirements of the ordinance and the NPDES general permit are not met. Therefore, plans for those landdisturbing activities which are not exempted by this ordinance shall contain provisions for application of soil erosion, sedimentation and pollution control measures and practices. The provisions shall be incorporated into the erosion, sedimentation and pollution control plans. Soil erosion, sedimentation and pollution control measures and practices shall conform to the minimum requirements of subsections (b) and (c). The application of measures and practices shall apply to all features of the site, including street and utility installations, drainage facilities and other temporary and permanent improvements.

Measures shall be installed to prevent or control erosion, sedimentation and pollution during all stages of any land-disturbing activity in accordance with requirements of this ordinance and the NPDES general permit.

(b) Minimum requirements/BMPs.

(1) Best management practices as set forth in this subsection and subsection (c) of this ordinance shall be required for all land-disturbing activities. Proper design, installation, and maintenance of best

management practices shall constitute a complete defense to any action by the Director or to any other allegation of noncompliance with paragraph (2) of this subsection or any substantially similar

terms contained in a permit for the discharge of storm water issued pursuant to O.C.G.A. § 12-5-30(f), the �Georgia Water Quality Control Act�. As used in

this subsection the terms �proper design� and �properly designed� mean designed

in accordance with the hydraulic design specifications contained in the �Manual for Erosion and Sediment Control in Georgia� specified in O.C.G.A. § 12-7- 6(b).

(2) A discharge of stormwater runoff from disturbed areas where best management

practices have not been properly designed, installed, and maintained shall constitute a separate violation of any land-disturbing permit issued by a local issuing authority or of any state general permit issued by the division pursuant to O.C.G.A.

§ 12-5-30(f), the �Georgia Water Quality Control Act�, for each day on which such discharge results in the turbidity of receiving waters being increased by more than 25 nephelometric turbidity units for

waters supporting warm water fisheries or by more than ten nephelometric turbidity units for waters classified as trout waters. The turbidity of the receiving

waters shall be measured in accordance with guidelines to be issued by the director. This paragraph shall not apply to any land disturbance associated with the construction of single family homes which are not part of a larger common plan of

development or sale unless the planned disturbance for such construction is equal to or greater than five acres.

(3) Failure to properly design, install, or maintain best management practices shall constitute a violation of any land- disturbing permit issued by a local issuing authority or of any state general permit issued by the division pursuant to O.C.G.A.

§ 12-5-30(f), the �Georgia Water Quality Control Act�, for each day on which such failure occurs.

(4) The director may require, in accordance with regulations adopted by the board,

reasonable and prudent monitoring of the turbidity level of receiving waters into which discharges from land disturbing activities occur.

(5) The LIA may set more stringent buffer requirements than stated in subsection c (15), (16) and (17), in light of O.C.G.A.

§ 12-7-6(c).

(6) Construction site operators must control waste at the construction site, such as

discarded building materials, concrete washout, chemicals, litter and sanitary waste.

(c) The rules and regulations, ordinances, or resolutions adopted pursuant to O.C.G.A. § 12- 7-1 et seq. for the purpose of governing landdisturbing activities shall require, as a minimum, protections at least as stringent as the state general permit; and best management practices, including sound conservation and engineering practices to prevent and minimize erosion and resultant sedimentation, which are consistent with, and no less stringent than, those practices contained in the Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil and Water Conservation Commission as of January 1 of the year in which the landdisturbing activity was permitted, as well as the following:

(1) Stripping of vegetation, regrading and other development activities shall be

conducted in a manner so as to minimize erosion;

(2) Cut-fill operations must be kept to a minimum;

(3) Development plans must conform to topography and soil type so as to create the lowest practicable erosion potential;

(4) Whenever feasible, natural vegetation shall be retained, protected and

supplemented;

(5) The disturbed area and the duration of exposure to erosive elements shall be

kept to a practicable minimum;

(6) Disturbed soil shall be stabilized as quickly as practicable;

(7) Temporary vegetation or mulching shall be employed to protect exposed critical

areas during development;

(8) Permanent vegetation and structural erosion control practices shall be installed as soon as practicable;

(9) To the extent necessary, sediment in run-off water must be trapped by the use of debris basins, sediment basins, silt

traps, or similar measures until the disturbed area is stabilized. As used in this paragraph, a disturbed area is

stabilized when it is brought to a condition of continuous compliance with the requirements of O.C.G.A. § 12-7-1, et

seq.;

(10) Adequate provisions must be provided to minimize damage from surface water to

the cut face of excavations or the sloping of fills;

(11) Cuts and fills may not endanger adjoining property;

(12) Fills may not encroach upon natural watercourses or constructed channels in

a manner so as to adversely affect other property owners;

(13) Grading equipment must cross flowing streams by means of bridges or culverts

except when such methods are not feasible, provided, in any case, that such crossings are kept to a minimum;

(14) Land-disturbing activity plans for erosion, sedimentation and pollution control shall include provisions for treatment or control of any source of sediments and

adequate sedimentation control facilities to retain sediments on-site or preclude

sedimentation of adjacent waters beyond the levels specified in subsection (b)(2) of this section;

(15) Except as provided in paragraph (16) and

(17) of this subsection, there is established a 25-foot buffer along the banks of all

state waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action, except where the director determines to allow a variance that is at least as protective of natural resources and the environment, where otherwise

allowed by the director pursuant to O.C.G.A. § 12-2-8, where a drainage structure or a roadway drainage structure must be constructed, provided that

adequate erosion control measures are incorporated in the project plans and specifications, and are implemented; or where bulkheads and sea walls are installed to prevent shoreline erosion on Lake Oconee and Lake Sinclair; or along

any ephemeral stream. As used in this provision, the term 'ephemeral stream' means a stream: that under normal circumstances has water flowing only during and for a short duration after precipitation events; that has the channel located above the groundwater table year round; for which ground water is not a source of water; and for which runoff

from precipitation is the primary source of water flow, unless exempted as along

an ephemeral stream, the buffers of at least 25 feet established pursuant to part 6 of Article 5, Chapter 5 of Title 12, the �Georgia Water Quality Control Act�, shall remain in force unless a variance is

granted by the director as provided in this paragraph. The following requirements shall apply to any such buffer:

a. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its natural, undisturbed state of vegetation until all land-disturbing activities on the construction site are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or trimmed of vegetation as long as a protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed; provided, however, that any person constructing a single-family residence, when such residence is constructed by or under contract with the owner for his or her own occupancy, may thin or trim vegetation in a buffer at any time as long as protective vegetative cover remains to protect water quality and aquatic habitat and a

natural canopy is left in sufficient quantity to keep shade on the stream bed; and

b. The buffer shall not apply to the following land-disturbing activities, provided that they occur at an angle, as measured from the point of crossing, within 25 degrees of perpendicular to the stream; cause

a width of disturbance of not more than 50 feet within the buffer; and adequate erosion control measures are incorporated into the project plans and specifications and are implemented:

(i) Stream crossings for water lines; or (ii) Stream crossings for sewer lines; and

(16) There is established a 50 foot buffer as measured horizontally from the point

where vegetation has been wrested by normal stream flow or wave action, along the banks of any state waters classified as �trout streams� pursuant to Article 2 of Chapter 5 of Title 12, the �Georgia

Water Quality Control Act�, except where a roadway drainage structure must be

constructed; provided, however, that small springs and streams classified as trout

streams which discharge an average annual flow of 25 gallons per minute or less shall have a 25 foot buffer or they may be piped, at the discretion of the

landowner, pursuant to the terms of a rule providing for a general variance promulgated by the board, so long as any such pipe stops short of the downstream

landowner's property and the landowner complies with the buffer requirement for any adjacent trout streams. The director may grant a variance from such buffer to allow land-disturbing activity, provided that adequate erosion control measures

are incorporated in the project plans and specifications and are implemented. The

following requirements shall apply to such buffer:

a. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its natural, undisturbed, state of vegetation until all land-disturbing activities on the construction site are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or trimmed of vegetation as long as a protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed: provided, however, that any person constructing a single-family residence, when such residence is constructed by or

under contract with the owner for his or her own occupancy, may thin or trim vegetation in a buffer at any time as long as protective vegetative cover remains to protect water quality and aquatic habitat and a

natural canopy is left in sufficient quantity to keep shade on the stream bed; and

b. The buffer shall not apply to the following land-disturbing activities, provided that they occur at an angle, as measured from the point of crossing, within 25 degrees of perpendicular to the stream; cause

a width of disturbance of not more than 50 feet within the buffer; and adequate erosion control measures are incorporated into the project plans and specifications and are implemented:

(i) Stream crossings for water lines; or (ii) Stream crossings for sewer lines; and

(17) There is established a 25 foot buffer along coastal marshlands, as measured

horizontally from the coastal marshlandupland interface, as determined in accordance with Chapter 5 of Title 12 of this title, the Coastal Marshlands Protection Act of 1970. And the rules and regulations promulgated thereunder,

except where the director determines to allow a variance that is at least as protective of natural resources and the environment, where otherwise allowed by the director pursuant to Code Section 12-2-8, where an alteration within the buffer

area has been authorized pursuant to Code section 12-5-286, for maintenance of any currently serviceable structure, landscaping, or hardscaping, including bridges, roads, parking lots, golf courses, golf cart paths, retaining walls, bulkheads, and patios; provided, however, that if

such maintenance requires any landdisturbing activity, adequate erosion control measures are incorporated into

the project plans and specifications and such measures are fully implemented,

where a drainage structure or roadway drainage structure is constructed or maintained; provided, however, that if such maintenance requires any landdisturbing activity, adequate erosion control measures are incorporated into

the project plans and specifications and such measures are fully implemented, on

the landward side of any currently serviceable shoreline stabilization structure, or for the maintenance of any manmade

storm-water detention basin, golf course pond, or impoundment that is located

entirely within the property of a single individual, partnership, or corporation;

provided, however, that adequate erosion control measures are incorporated into

the project plans and specifications and such measures are fully implemented.

For the purposes of this paragraph maintenance shall be defined as actions necessary or appropriate for retaining or restoring a currently serviceable improvement to the specified operable condition to achieve its maximum useful life.

Maintenance includes emergency reconstruction of recently damaged parts of a currently serviceable structure so

long as it occurs within a reasonable period of time after damage occurs.

Maintenance does not include any modification that changes the character, scope or size of the original design and serviceable shall be defined as usable in its current state or with minor

maintenance but not so degraded as to essentially require reconstruction.

a. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its natural, undisturbed, state of vegetation until all land-disturbing activities on the construction site are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or trimmed of vegetation as long as a protective vegetative cover remains to protect water quality and aquatic habitat; provided, however, that any person constructing a single-family residence, when such residence is constructed by or under contract with the owner for his or her own occupancy, may thin or trim vegetation in a buffer at any time as long as protective vegetative cover

remains to protect water quality and aquatic habitat; and

b. The buffer shall not apply to crossings for utility lines that cause a width of disturbance of not more

than 50 feet within the buffer, provided, however, that adequate erosion control measures are incorporated into the project plans and specifications and such measures are fully implemented.

c. The buffer shall not apply to any land-disturbing activity conducted pursuant to and in compliance with a valid and effective land-disturbing permit issued subsequent to April 22, 2014, and prior to December 31,

2015; provided, however, that adequate erosion control measures are incorporated into the project plans and specifications and such measures are fully implemented or any lot for which the preliminary plat has been approved prior to December 31, 2015 if roadways, bridges, or water and sewer lines have been extended to such lot prior to the effective date of this act and if the requirement to maintain a 25

foot buffer would consume at least 18 percent of the high ground of the platted lot otherwise available for development; provided, however, that adequate erosion control measures are incorporated into the project plans and specifications and such measures are fully implemented.

d. Activities where the area within the buffer is not more than 500 square feet or that have a minor buffer impact as defined in 391-3-7-.01(r), provided that the total area of buffer impacts is less than 5,000 square feet are deemed to have an approved buffer variance by rule. Bank stabilization structures are not eligible for coverage under the variance by rule and notification shall be made to the division at least 14

days prior to the commencement of land disturbing activities.

(d) Nothing contained in O.C.G.A. § 12-7-1 et seq. shall prevent any local issuing authority from adopting rules and regulations, ordinances, or resolutions which contain stream buffer requirements that exceed the minimum requirements in subsections (b) and (c) of this section.

(e) The fact that land-disturbing activity for which a permit has been issued results in injury to the property of another shall neither constitute proof of nor create a presumption of a violation of the standards provided for in this chapter or the terms of the permit.

History

The history line the source prints at the end of the section.

(Ord. of 12-12-16(1); Ord. of 12-11-17(1))

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:whitfield-county/code/5-73@2026-05-11-7eadbe7712

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.