Toccoa City Commission work session, July 22, 2024
3 pages
These are the minutes as Toccoa City Commission posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Toccoa City Commission.
This record was posted as scanned images, read here by OCR: a letter or a number may be misread. The file the body posted is linked below.
Records of this meeting
Each link opens the body's own website or meeting portal.
- MinutesMinutes (www.cityoftoccoa.com) · shown on this page
Summary
Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.
Commission agreed by consensus to pay a corrected engineering invoice and move forward with a donated downtown street clock.
At a work session with no formal votes, the commission heard several presentations and reached agreement by consensus on three matters. On an engineer's invoice, the engineer explained that earlier billing used incorrect design and bidding fees, which led to an $82,000.00 bill, and the board agreed by consensus to pay it. On Phase II of the Eastanollee Creek wastewater plant upgrades, the engineer said the project came in over budget and a second loan of $3,500,000.00 was offered through the Georgia Fund; the board agreed by consensus to add the item to the regular agenda. The board also heard about water sale agreements and a downtown parking study, with businesses to be given a chance to weigh in on proposed two hour parking. For a proposed street clock offered by a family for $31,000.00, the board agreed by consensus to move forward, with the city covering the foundation, electrical work and a plaque.
Topics taken up: engineer service invoice; GEFA loan for wastewater plant; Eastanollee Creek Phase II upgrades; water sale agreements; downtown parking study; two hour parking; street clock donation; 150th celebration.
Decisions the minutes record (3)
Each decision is followed by the sentence of the minutes that records it, copied word for word.
Payment of corrected engineering services invoice for wastewater project
The minutes: “After further discussion the board agreed by consensus to pay the invoice.”
Adding GEFA second loan funding for Eastanollee Creek wastewater plant Phase II to the regular agenda
The minutes: “By consensus the board agreed to add the item to the regular agenda.”
Donated downtown street clock honoring Mr. Irvin, with city covering foundation, electrical and plaque
The minutes: “Board of Commissioners agreed by consensus to move forward and Fredda to approve”
Agenda items (4)
Found in the minutes by their headings. Where an outcome is shown, it was read by rule from the item's own words: a guide to the text, not part of the record.
The minutes
As posted on www.cityoftoccoa.com, read November 19, 2026. Nothing below is written by Georgia Commons.
CITY OF TOCCOA
CITY COMMISSION
MINUTES e JULY 22, 2024
Work Session
City Commission/Court Room
92 North Alexander, Toccoa, GA 30577
3:30 PM
I. CALL TO ORDER
Mayor Gail Fry called the meetin
g to order at 3:30 pm
Att Te ean — - oP eis Litle Status Arrived Temy Carter | Vice Mayor. cn a a _— | Mayor resent = ON | Commissioner __ | Present — Bon Matheson ~ | Commissioner <a Michelle Jamieson | Commissioner __| Present atedda O. Wheeler ___ | City Manager | Present J _ fohn Dic __ ___| Attorney | Present | Beth Rider | City Clerk - | Present T oO
Il. AGENDA ITEMS
1. Discussion of Engineers Service Invoice
Alex Wiseman stated he had submitted a cover letter with an invoice attached for previous billing errors for incorrect fee amounts. Mayor Fry stated we received notice the bill was paid in full and then an $82,000.00 bill came in, that is the question we have. Mr. Wiseman stated they sent periodic invoices on the project since they initiated the design phase. He stated they invoiced 100 percent for the design phase and 100 percent for the bidding phase; that was
based on a fee of $213,000 for the design phase and $15,000.00 for the bidding phase. Mr.
Wiseman stated he did not catch that the fees were incorrect and they should have been
$285,000.00 for the design phase and $25,000.00 for the bidding phase . The error did not get
discovered until they were moving into the construction phase. After further discussion the board agreed by consensus to pay the invoice.
{
| RESULT: PRESENTATION
2. Discussion of GEFA Funding for Phase II of Eastanollee Creek Wastewater Treatment Plant Upgrades
Alex Wiseman discussed the GEFA funding for Phase If of Eastanollee Creek Wastewater Plant upgrades. They bid the project at the end of 2022 and have moved into the construction phase and the project came in over budget than what was on the GEFA Loan Fund. He stated they have a second loan to cover the $3,500,000.00 difference, they could not extend the loan under the original terms and offered the $3,500,000.00 under the Georgia Fund. Mr.
Wiseman stated it has a different interest rate but was able to get the 30 year procurement term. By consensus the board agreed to add the item to the regular agenda.
RESULT: PRESENTATION
| sowee. saree = eu
3. Discussion of Water Sale Agreements
City of Toccoa
ty
on indiv; . . _ aihsemeetn ea ic the committee. Commissioner Jamieson stated she would like for the
- ce to take into consideration which direction we i i ; need to go to continue using t CPI Index or the cost of the water when negotiating contracts. meine
RESULT: PRESENTATION
4. Discussion of the Downtown Parking Study
Stacy Estes, Ginger Herring and Mary Zimmerman of First Franklin Financial discussed downtown parking and presented the board with a map of the downtown parking areas with concerns of designation of the two hour parking. Commissioners discussed the parking areas
and stated the two hour parking being proposed is only in front of retail stores. Mayor Fry stated we are just discussing this today, we would like businesses to have an opportunity to
talk to us and what it would mean to them.
Jeremy Ward, Planning/Development Director discussed the Downtown Parking Study and results.
RESULT: PRESENTATION
5: Other Items of Discussion
Vice-Mayor Carter stated the Commissioners were contacted by the Irvin Family about the possibility of installing a street clock in honor of Mr. Irvin. They like the idea of where the magnolia tree was placing a four sided clock that will have the date of 1874 and it will chime. They asked if the City would place a plaque at the bottom recognizing the family and the contributions Mr. Irvin made while in office. They have agreed to pay 100 %, it is $31,000.00; they are asking the City to cover the foundation, electrical and install the plaque.
Vice-Mayor Carter stated it is a nice way to commemorate our 150th Celebration and a very generous contribution the family is willing to make to the City. We would need to take a small amount from CRA for the foundation and electrical, in comparison of what the cost would be and the impact it would make on City Hall and all of downtown it would be a
small amount.
Board of Commissioners agreed by consensus to move forward and Fredda to approve
amount under $5,000.00
City of Toccea Page 2 Updated 7/31/2024 2:47 PM
Minutes City Commission July 22, 2024
| RESULT: PRESENTATION |
1. ADJOURN :
Mayor Fry adjourned meeting at 4:55 p.m.