County: Upson County

Upson County Board of Commissioners work session, August 7, 2024

10 pages

These are the minutes as Upson County Board of Commissioners posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Upson County Board of Commissioners.

4 of this record's 10 pages were scanned images, read here by OCR: a letter or a number on them may be misread. The file the body posted is linked below.

Copy for LLM, View as markdown, and Send to AI use the Markdown version: the summary Georgia Commons wrote, under a heading that names it, then the record as posted. View raw is the record alone.

Records of this meeting

Each link opens the body's own website or meeting portal.

Summary

No summary has been written for this record yet.

Agenda items (7)

Found in the minutes by their headings. Where an outcome is shown, it was read by rule from the item's own words: a guide to the text, not part of the record.

  1. I. CALL TO ORDER
  2. II. ATTENDANCE
  3. III. NEW BUSINESS
  4. III. NEW BUSINESS
  5. 1. Road Resurfacing Project
  6. 2. Thurston Well Project
  7. 3. Civic Center – Water Intrusion through Racquetball Court
  8. IV. ADJOURNMENTA motion

Answers are written by AI from this document, and every quotation is checked against it. Not legal advice.

The minutes

As posted on upsoncountyga.org, read November 26, 2026. Nothing below is written by Georgia Commons.

UPSON COUNTY BOARD OF COMMISSIONERS

Work Session Wednesday, August 7, 2024 9:00 A.M.

Thomaston/Upson County Airport Meeting Room

AGENDA

I. CALL TO ORDER

Chairman Norman Allen

II. ATTENDANCE

Chairman Norman Allen Commissioner Lorenzo Wilder Commissioner Benjamin Watson Commissioner Paul Jones County Manager Jason Tinsley County Clerk Jessica Jones County Finance Director Allen Salter County Attorney Heath English Commissioner James Ellington was not in attendance.

III. NEW BUSINESS

a. Update on G.D.O.T Bridge Projects Adam Smith with G.D.O.T gave the board the following updates.

The bridge on Jeff Davis and Ten Mile Creek has ongoing utility work.

The completion date is set for October 31, 2025. The closing plans are for early spring with a maximum 180 closing period. Closure notices will be sent out in advance.

The Highway 36 Jerry Reeves Creek culvert will be replaced with a bridge.

This project has a 2026 construction and is scheduled for 2028 funding.

These dates are subject to change.

Elkins Creek bridge has approved concept plan and will acquire right of way 2025 summer, the project will go to bid for construction in the fall of 2026. The funding is currently in the fall of 2028. There will be an onsite detour.

The Hannahs Mill Bridge project is approved with no local match required.

The concept has been submitted and construction is estimated to scheduled for FY27. The estimated cost is $4-5 million.

The Chairman questioned if the project could be competed sooner if the county funded it completed. Mr. Smith advised that it could probably be completed sooner if the county has the fund to fund it completely, but the process would need to be started from the beginning.

The 5-way roundabout is estimated to be completed by winter of 2025.

b. Presentation by Schneider Electric on the 60% design package for the Drake Building and Civic Center Ballfield Renovations

Jen Miller gave the board the presentation below.

EST. ANNUAL COSTS & POTENTIAL SAVINGS

Year Annual Savings Cumulative Savings

Annual Cost of Operations }=—————-——__» 1 $286,877 $286,877 2 $295,483 $982,360

3 $304,347 $886,707

4 $313,478 $1,200,185

9 $322,882 $1,523,067

6 $332,569 $1,855,636

7 $342,546 $2,198,181

8 $352,822 $2,551,004

Annex Building Juvenile Justice = DOT Building 9 $363,407 $2,914,410 10 $374,309 $3,288,719

11 $385,538 $3,674,258

12 $397,104 $4,071,362

13 $409,018 $4,480,379

14 $421,288 $4,901,667

15 $433,927 $9,335,594

16 $446,944 $9,782,539

7 $460,353 $6,242,891

18 $474,163 $6,717,055

19 $488,388 $7,205,443

20 $503,040 $7,708,483

Project Details & Scope Considerations

Ball Field Modernization

VISION & SCOPE OVERVIEW

Vision Upgrade ball field complex: modernizing the athletic environment,

expanding field sizes, and addressing long-standing challenges with drainage & irrigation.

Scope

* Drainage Remediation

* Laser grading of infield with fill for Fields #1, #3, & #13

* Rebuilding Field #2

* Installing trench drains at dugouts and backstops

* Installing outfield drainage and reworking swales

* General Work for Field #2

* New fencing including foul poles

* New dugouts

* New bases

* Lighting

* Updating existing MUSCO poles on Fields #1 & #3 with new MUSCO Light- 7 Structure System Retrofit See ee

* Installing new MUSCO Light-Structure System from foundation to pole top on

Fields #2 & #13 Lie'sOn | Schneide

* Electrical infrastructure upgrades as needed

FIELD DRAWINGS & CONSIDERATIONS

Scope Considerations

¢ Haul Off: intent is to balance the site with cut and fill scope. Minimal haul off is anticipated at this time.

Infield Dirt Mix: basis of design is SAF Marmix. Blended mix of 70% sand & 30% clay.

Drainage System:

* Consists of 12”,15” & 18” HDPE piping and ADS style plastic drain system for site drains

* Catch basins and trough drains

¢ Dugout construction: concrete foundation, CMU block walls, brick exterior fagade, sloped shingled roofing.

Fencing: 25’ at backstop, 6’ sideline, 4’ outfield

¢ Bases: design calls for 3 sets of bases going back in the infield on drawings

Still in development:

¢ Site Civil Design

* Erosion control plan in progress- planning to submit by EOW

Custom Logos & Signage ee

COMMUNITY FIELDS

Bright lights, | big plays.

Get ready for brighter nights and weekends at the ballpark as we install new, more efficient LED lights on each field!

THOMASTON,

-UPSON,

COMMUNITY FIELDS

ectric

DESIGN & CONCEPTUAL CONSTRUCTION TIMELINES

ID Task Name Start Finish 3rd¢ May Jun.

1 Notice to Proceed Wed 6/19/24 Wed 6/19/24 0 2 Design Development Wed 6/19/24 Fri 2/28/25 3 Design Development Plans Wed 6/19/24 Wed 7/24/24

4 Submit DD Plans to Owner Wed 7/24/24 Wed 7/24/24

5 Owner Review Thu 7/25/24 Wed 7/31/24

6 Construction Drawings Thu 7/25/24 Wed 8/14/24

7 100% Set Production Thu 7/25/24 Wed 8/14/24

8 internal QA/QC Set Wed 8/7/24 Wed 8/7/24

9 100% Modifications Thu 8/8/24 Wed 8/14/24

10 Submit 100% Construction Drawings to OwnerWed 8/14/24 Wed 8/14/24

11 Procurement & Construction Thu 8/15/24 Fri 2/28/25

12 Pre-construction (estimated) Thu 8/15/24 Thu 9/12/24

13 Permits Thu 8/15/24 Fri 10/25/24

14 Civil LOP Permit Thu 8/15/24 Fri 10/25/24

15 Submit LPD Set Thu 8/15/24 Thu 8/15/24

16 LDP Review Fri 8/16/24 Fri 9/27/24

17 LDP Revision #1 Mon 9/30/24 Fri 10/4/24

18 LDP Revision #1 Review Mon 10/7/24 Fri 10/25/24

19 LDP Approval Fri 10/25/24 Fri 10/25/24

20 Construction (estimated) Mon 10/28/24 Fri 1/31/25

21 Ballfield Drainage and New Field Rebuild Mon 10/28/24 Fri 1/31/25

22 Sports Lighting Installation Mon 10/28/24 Fri 1/17/25

23 Closeout Mon 2/3/25 Fri 2/28/25

24 Punchlist Mon 2/3/25 Fri 2/14/25

25 O&M Manuals & Owner Training Mon 2/3/25 Fri 2/28/25

The timeline for the construction of the ballfield is short to avoid the interference of the spring season. The board asked Jen to add the cost to do the concession stand and bathrooms.

County Consolidation Initiative

TAX COMMISSIONER

TAX ASSESSOR

D? FURNITURE PLAN - LEVEL 1

SCALE: /8"=1-0"

County Consolidation Initiative

Basement {' Floor Facllities Elections Natural Resources Conservation Service ars is A rr) Toe -| Ee S ms {1,269 sftotal f) = SSS. (0 g ‘otal

VAILABLE SQ FT

BUILDING & ZONING

4H/EXTENSION

(OR ELECTIONS)

Departments

+ County Manager's office

* Elections

* Facilities

+ Natural Resources Conservation Service

* Storage

2d Floor

County Manager Potential Storage

REQSTRAR

i ais sf total

OOM

B

ar

County Consolidation Initiative

Vision

Minimal renovation to vacate Annex. Focus on Tax Commissioner space &

relocate Assessor to current DA offices.

Option B Scope Considerations:

¢ Mechanical

« — Removal of one existing WSHP unit and installation of two new WSHP units

* — Existing ductwork to be re-usedto *

the extent possible

« — New supply and return ductwork, registers, grilles, diffusers

¢ — Impact of partial renovation on system

¢ Fire Protection

¢ Addressing later will require disturbance

of newly renovated space

¢ Electrical

* New circuits for WSHPs, lighting, switches, & receptacles

* New 2x4 LED flat panel lighting

General Construction

Moving and adding sprinkler heads to accommodate new floor plan

Demo of existing walls, doors, & acoustical ceiling

Turnkey construction including:

* New walls & doors

* Carpet tile flooring ¢ — Walkup window

* Acoustical ceiling

MAGISTRATE.

CLERK

JUDGE icc] =

COURT OFFICE =O

TAX COMMISSIONER Une ot BUILDING & ZONING | oar 4 DA to TAX ASSESSOR F en ms

“4 -~PDO [ms re ee oo tn at oan fo rr q — Tau HOLDING HOLDING ; “= rice} Tou ee TT 2 ® OF" RECEPT. corripor “) JANITOR ELEC. CORRIDOR LE FILE rite ete ay ine ea, Terr] “a on Tee] (ea vee oar farm t I [En (9) [ = (or) Tee] x) [ei B ; %

(ca) dT a Y M Oe = Tea @ on eR] oe pe cad» od Sepa Labs = ai< cos. © m=) “ ol g ts hy \entey cc 1 @ yy BE SE Ve a [one] es + 2) esi ve. ane ter wee oe clos cub @ ‘le, @ a ey a © i Ne e — © {eh

- = i ————\— = but was b 4 : L Vacant entry ||| Possibly Vacant (soil _|[_OFFICE 4H/Extension CO. EXTENSI Vacant oa elections ion ¢ Elections (formerly “ conservation could = (formerly used _ testing) environmental Be || Moveto basement) a SHAKE BLING DATE by DA's office) — health)- could SHAE STORY , |

be temp.

housing for facilities

4 STORAGE

An Onno -

- I i C il | I LU L LILI a ( (| I i i I

SHARED CONFERENCE ROC.

y

WOMEN'S RESTROOM:

JANITOR

c. Updates for EMC Engineering

1. Road Resurfacing Project

There are some additional roads that Commissioners would like to be considered, but they will be considered as an add on so the paving project won’t be delayed. The pre-bid meeting will be held on August 21st and the bid opening will be held on September 4

th .

2. Thurston Well Project

The pre-bid meeting will be held on August 21st and the bid opening will be September 4

th .

3. Civic Center – Water Intrusion through Racquetball Court

EMC is working on options to stop the water intrusion.

Commissioner Jones asked EMC to check on a well on Skelton Road that was drilled several years ago that may need to be abandon.

d. Discussion on Sprewell Bluff Maintenance Staffing The county manager asked the board to consider allow a maintenance employee to stay in a RV at the Bluff without charge in order to have staff there after hours and during peak days/season.

e. Presentation/Demonstration from Code Enforcement on Civic Gov The Code Enforcement officer gave the board a presentation on how to operate Civic Gov. This new system will allow the board to see current information on Code Enforcement, Planning and Zoning and Road Department Permits.

IV. ADJOURNMENT

A motion was made by Commissioner Watson with a second from Commissioner Jones to adjourn the meeting.

______________________________ __Was Not in Attendance_________ Chairman Norman Allen Commissioner James Ellington ______________________________ _______________________________ Commissioner Benjamin Watson Commissioner Lorenzo Wilder _______________________________

Commissioner Paul Jones

Machine-readable https://georgiacommons.org/meetings/2024-08-07/upson-county-board-of-commissioners-work-session.md · https://georgiacommons.org/meetings/local/index.md · MCP https://mcp.georgiacommons.org/mcp