Skip to content
Georgia Commons
Menu

County: Bartow County

Bartow County Commissioner meeting, October 1, 2025

6 pages

These are the minutes as Bartow County Commissioner posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Bartow County Commissioner.

Copy for LLM, View as markdown, and Send to AI use the Markdown version: the summary Georgia Commons wrote, under a heading that names it, then the record as posted. View raw is the record alone.

Records of this meeting

Each link opens the body's own website or meeting portal.

Summary

Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.

Commissioner approves zoning ordinance amendments including data center rules, a Copart vehicle storage permit, a rezoning, and grant and contract items.

The sole county commissioner approved a long list of items at a short public meeting. The largest was a package of eleven amendments to the Bartow County Zoning Ordinance, covering accessory structures, lot splits, data centers on at least 200 acres as a conditional use, storage facilities, and conditional use resubmission waits. The commissioner also approved a Copart conditional use permit for vehicle storage on Beasley Road and a rezoning of 199 Road No. 2 from A-1 to R-1. Other actions included amendments to the 2023 Joint Comprehensive Plan, a $150,250.00 archery range design contract, a $500,000 trail grant, a $915,309.00 transit funding application, two alcohol licenses, two board reappointments, road acceptances in two subdivisions, and the final FY 2024 budget amendments. No vote counts were recorded for the commissioner's own actions.

Topics taken up: zoning ordinance amendments; data center conditional use; Copart vehicle storage permit; rezoning of 199 Road No. 2; Joint Comprehensive Plan amendments; archery range design contract; Wilderness Camp bike trail grant; Materials Recovery Facility grant application; road acceptances; alcohol licenses; FY 2024 budget amendments; Extension Services agreements.

Decisions the minutes record (15)

Each decision is followed by the sentence of the minutes that records it, copied word for word.

  1. Eleven amendments to the Bartow County Zoning Ordinance, including data centers, accessory structures, lot splits, and storage facilities

    Adopted

    The minutes: “The Planning Commission recommended approval with a 6-0 vote. There were no registered speakers for the amendments. Commissioner Taylor approved the amendments as presented.”

    Read this item in the minutes

  2. Conditional use permit for Copart of Connecticut vehicle storage on 15 acres on Beasley Road

    Adopted

    The minutes: “Commissioner Taylor approved the Application as presented.”
  3. Rezoning of 1 acre at 199 Road No. 2 from A-1 to R-1 for a single-family home

    Adopted

    The minutes: “Z-25-00037; an application by Kailah Dempsey requesting to rezone a 1 acre lot at 199 Road No. 2 from A-1 to R-1 in order to separate the parcel from the parent parcel and build one single-family home.”

    Read this item in the minutes

  4. Amendments to the 2023 Joint Comprehensive Plan

    Adopted

    The minutes: “Commissioner Taylor approved and adopt amendments to the 2023 Joint Comprehensive Plan as presented by the Bartow County Grant Writing Department.”
  5. Contract with Croy Engineering for $150,250.00 for archery range design services

    Adopted

    The minutes: “A contract with Croy Engineering in the amount of $150,250.00 for design services for a proposed Archery Range Facility on County Greenspace property located at Cassville-Pine Log Road (adjacent to the Cass-White Industrial Park) was approved as presented.”
  6. Acceptance of $500,000 grant for third phase of Wilderness Camp Mountain Bike Trail

    Adopted

    The minutes: “Commissioner Taylor authorized the acceptance of a $500,000 Grant from the Georgia Department of Natural Resources through the Land and Water Conservation Fund to construct the third phase of the Wilderness Camp Mountain Bike Trail on Bartow County’s Wilderness Camp Greenspace property.”
  7. Grant application for $2.5 million for a Materials Recovery Facility at the landfill

    Adopted

    The minutes: “Commissioner Taylor authorized a grant application to be submitted to the Solid Waste Trust Fund requesting a $2.5 million grant to facilitate the development of a Materials Recovery Facility at the Bartow County Landfill.”
  8. FY 2026-27 Transit 5307 Funding Application of $915,309.00

    Adopted

    The minutes: “The FY 2026-27 Transit 5307 Funding Application in the amount of $915,309.00 was approved as presented.”
  9. Final amendments to the FY 2024 Budget after the 2024 Audit

    Adopted

    The minutes: “Commissioner Taylor approved the final amendments to the FY 2024 Budget as presented and recommended by the County’s CPA firm of Rushton and Company upon their completion of the 2024 Audit.”
  10. FY2026 Juvenile Justice Incentive Grant Funding of 250,000.00

    Adopted

    The minutes: “Commissioner Taylor approved and accepted the FY2026 Juvenile Justice Incentive Grant Funding in the amount of 250,000.00 to continue providing Juvenile Justice Incentive services through the Juvenile Court System.”
  11. Acceptance of Laurel Park Subdivision roads into the County Road System

    Adopted

    The minutes: “Edna Drive and Marion Drive in the Laurel Park Subdivision were accepted into the County Road System.”
  12. Acceptance of Aubrey Park Subdivision roads into the County Road System

    Adopted

    The minutes: “Graham Circle, Gardner’s Ridge, Denton Drive and Larry Lane in the Aubrey Park Subdivision, Phases I and II were also accepted into the County Road System.”
  13. Alcohol licenses for Quick Trip #1771 and Forno D’Oro Restaurant

    Adopted

    The minutes: “Commissioner Taylor approved the following alcohol licenses:”
  14. Amended MOU with the University System of Georgia for Extension Services

    Adopted

    The minutes: “Commissioner Taylor approved the MOU as presented.”
  15. Reappointments to the Construction Board of Adjustments & Appeals and the Development Authority of Bartow County

    Adopted

    The minutes: “Mr. Brian McCollum was re-appointed to serve another term on the Construction Board of Adjustments & Appeals.”

Agenda items (11)

Found in the minutes by their headings. Where an outcome is shown, it was read by rule from the item's own words: a guide to the text, not part of the record.

  1. I. Article V, Section 5.3.3, to be amended to add the following:
  2. II. Article V., Section 5.3.5 (A) to be deleted and replaced with the following:
  3. III. Article V, Section 5.3.5 (C) to be deleted and replaced with the following:
  4. IV. Article V, Sec. 5.7 to be deleted and replaced with the following:
  5. V. Article VII, Sec. 7.1.7 (B) to be deleted and amended with the following:
  6. VI. Article VII, Sec. 7.1.9 (Conditional Uses) to be amended by adding new paragraph (I.I.)
  7. VII. Article VII, Sec. 7.1.10 to be deleted and replaced with the following:
  8. VIII. Article VII, Sec. 7.11.9 Paragraph C to be deleted and replaced with the following:
  9. IX. Article X to be amended by adding Sec. 10.2
  10. X. Article X to be amended by adding Sec. 10.4
  11. XI. Article XVI to be amended by deleting Sec. 16.5 and replacing with the following:A vote

Sections of the code these records refer to (1)

Found by rule from the words of the records on this page. A reference is a pointer to the section, not a statement that the section applies, was changed, or is in force.

Answers are written by AI from this document, and every quotation is checked against it. Not legal advice.

The minutes

As posted on www.bartowcountyga.gov, read November 25, 2026. Nothing below is written by Georgia Commons.

MINUTES

PUBLIC MEETING

BARTOW COUNTY COMMISSIONER

September 3, 2025 - 10:00 a.m.

After calling the public meeting to order, Commissioner Taylor presented the following items of business:

MINUTES:

• Minutes of the July and August Public Hearings and the July 31st and August 8th Public Meetings was approved as presented.

ALCOHOL LICENSES:

Commissioner Taylor approved the following alcohol licenses:

• AL25-00010; a Retail Package License for Quick Trip # 1771, Burnt Hickory Road

• AL25-00009; a Consumption on the Premises License for Forno D’Oro Restaurant, Hamilton Blvd.

APPOINTMENTS:

• Mr. Brian McCollum was re-appointed to serve another term on the Construction Board of Adjustments & Appeals.

• Mr. Carlos Calhoun was re-appointed to serve another term on the Development Authority of Bartow County.

COMMUNITY DEVELOPMENT

• Commissioner Taylor approved and adopt amendments to the 2023 Joint Comprehensive Plan as presented by the Bartow County Grant Writing Department.

COMMUNITY SERVICES INITIATIVES

• The FY 2026-27 Transit 5307 Funding Application in the amount of $915,309.00 was approved as presented.

• Commissioner Taylor authorized a grant application to be submitted to the Solid Waste Trust Fund requesting a $2.5 million grant to facilitate the development of a Materials Recovery Facility at the Bartow County Landfill.

• Commissioner Taylor authorized the acceptance of a $500,000 Grant from the Georgia Department of Natural Resources through the Land and Water Conservation Fund to construct the third phase of the Wilderness Camp Mountain Bike Trail on Bartow County’s Wilderness Camp Greenspace property.

• A contract with Croy Engineering in the amount of $150,250.00 for design services for a proposed Archery Range Facility on County Greenspace property located at Cassville-Pine Log Road (adjacent to the Cass-White Industrial Park) was approved as presented.

• County Extension Agent Paul Pugliese presented an amended MOU with the University System of Georgia related to the Georgia Extension Services. Commissioner Taylor approved the MOU as presented.

• Mr. Pugliese also presented personnel agreements for SNAP Educators Karen Martin and Patricia Hall, and Directors Angelica Davis and Katie Martin for the Commissioner’s approval. Commissioner Taylor approved the agreements as presented.

• Mr. Pugliese’s final document was to amend the Extension Services financial budget to provide for the previously presented personnel agreements. Commissioner Taylor approved and authorized the amendment as presented.

COURT SERVICES

• Commissioner Taylor approved and accepted the FY2026 Juvenile Justice Incentive Grant Funding in the amount of 250,000.00 to continue providing Juvenile Justice Incentive services through the Juvenile Court System.

ENGINEERING - MPO - ROADS

• Edna Drive and Marion Drive in the Laurel Park Subdivision were accepted into the County Road System.

• Graham Circle, Gardner’s Ridge, Denton Drive and Larry Lane in the Aubrey Park Subdivision, Phases I and II were also accepted into the County Road System.

FINANCE

• Commissioner Taylor approved the final amendments to the FY 2024 Budget as presented and recommended by the County’s CPA firm of Rushton and Company upon their completion of the 2024 Audit.

ZONING:

The following applications were presented by the Zoning Department for Commissioner Taylor action:

• Z-25-00035; a request by Bartow County Zoning Department staff to amend the following sections of the Bartow County Zoning Ordinance, Appendix A of the Official Code of Bartow County:

I. Article V, Section 5.3.3, to be amended to add the following:

On lots less than two acres, no accessory structure shall exceed fifty (50) percent 75 percent of the size of the principal building or structure.

II. Article V., Section 5.3.5 (A) to be deleted and replaced with the following:

No more than one (1) accessory dwelling unit per lot. A single-family principal dwelling unit must exist on the lot or have a building permit issued for a principal dwelling, which must have passed the Rough-in/Framing Inspection.

III. Article V, Section 5.3.5 (C) to be deleted and replaced with the following:

Heated floor area shall not exceed fifty (50) percent of the heated floor area of the principal building, or one thousand (1,000) square feet, whichever is less on lots less than 1 acre. Lots greater than 1 acre but less than 10 acres are allowed 75 percent of the heated floor area of the principal building, or 1,500 square feet, whichever is less.

IV. Article V, Sec. 5.7 to be deleted and replaced with the following:

Sec. 5.7 LOT SPLITS; SUBDIVISIONS; RECORDING OF PLATS

A lot split is a tract of land divided into two lots. A lot split may be signed by the Community Development Director or his or her designee, upon review as stated below. If, after December 5, 2012, either the parent parcel or the sub-parcel is proposed to be further split, this division shall follow the submittal process and requirements as found in appendix B (Development regulations).

A subdivision is a tract of land divided into three or more lots. A subdivision of land divided into three or more lots shall follow the submittal process and requirements as found in appendix B (Development regulations). Existing subdivision lots that have been platted on a Final Plat in an existing common development, cannot be subdivided further.

No plat proposing to subdivide/split, reconfigure, or combine a lot shall be recorded in the office of the Clerk of Superior Court of Bartow County without a signature of approval on the following signature block:

This plat meets the requirements of the Bartow County Zoning Ordinance and Development Regulations and is authorized to be recorded.

_______________________________ __________ Signature Date A boundary retracement survey that does not create a new lot and does not change existing property lines does not require review by community development staff.

Such signature block shall only be signed by the Community Development Director or his or her designee, upon review that the lots shown on the proposed plat meet the requirements for road frontage, minimum lot size, and all other applicable requirements of the Bartow County Code of Ordinance, appendix A (Zoning ordinance) and appendix B (Development regulations). Any plat recorded after the effective date of this amendment without such signature block shall be an illegal plat and shall vest no rights in the property owner. The county reserves the right to take legal action to reverse illegal lot creations, illegal lot splits, or other actions in violation of this section, including creation of substandard-sized lots or remnants.

V. Article VII, Sec. 7.1.7 (B) to be deleted and amended with the following:

Subdivision lot restrictions: A subdivision is a tract of land divided into three or more lots. A subdivision of land divided into three or more lots shall follow the submittal process and requirements as found in appendix B (Development regulations). Any proposed further subdivision of an individual lot in an A-1 subdivision existing as of November 9, 2005, or created subsequent to that date, shall require approval of an administrative adjustment shall not be eligible to be further subdivided.

VI. Article VII, Sec. 7.1.9 (Conditional Uses) to be amended by adding new paragraph (I.I.)

(I.I.) Data Centers, on a minimum of 200 acres. Data Centers must meet all development standards set forth in the Article III of this Ordinance (see Definitions, Sec 3.2 “Data Centers”). The data center must also maintain a 200- foot buffer, either undisturbed or improved as required by the Zoning Administrator to provide adequate visual screening for neighbors. Data Centers are unique developments that sometimes do not require a traditional Industrially-zoned property, as they do not create a high amount of traffic, and require power infrastructure that may not be found in developed industrial areas. Applicants must describe in their application why the property in question is better served by being issued a Conditional Use in the A-1 District than rezoning to I-1, I-2, or BPD. The applicant should provide a utility inventory showing the power line easements as part of their Concept Plan submittal that exhibits why the site is suitable for a Data Center. The Planning Commission will consider if the issuance of the Conditional Use Permit will have any negative impacts on the surrounding area. The Planning Commission can place additional requirements as conditions, including increased setbacks, buffers, noise and lighting restrictions to limit the impact of a Data Center on neighboring residents.

VII. Article VII, Sec. 7.1.10 to be deleted and replaced with the following:

In the A-1 zoning district, a property owner with at least 5 acres may convey to his or her child, stepchild, grandchild, step grandchild, mother, mother-in-law, father, father-in-law, grandmother, grandfather, grandparent (in-law), step-parent, brother, sister, brother-in-law, sister-in-law, stepbrother, stepsister, aunt, uncle, niece or nephew a building lot of at least 1 acre without having to rezone. The tract shall have at least 100 feet of road frontage and shall not violate the county’s easement and driveway restrictions. The tract may not be split from an existing A-1 subdivision lot. Only one lot shall be split under this exemption, future splits shall meet the required 2 acre minimum in the A-1 district or be rezoned. A plat or survey shall be prepared by a licensed land surveyor, with a note designating the tract is created under Sec. 7.1.10 of the Bartow County Zoning Ordinance.

Only uses permitted in the R-1 district shall be allowed – as an example, manufactured homes are prohibited with newly created lots under the family exemption.

VIII. Article VII, Sec. 7.11.9 Paragraph C to be deleted and replaced with the following:

Storage Facilities. “Storage facilities” shall mean mini-warehouses and storage yards, including building materials, timber and lumber, and shall include storage yards for boats, RVs, and self-service storage facilities. Commercial vehicle parking, including tractor-trailer parking, where there is no primary structure and parking is the primary use of the lot, is also classified as a storage facility.

Self-service storage facility is defined as a fully enclosed facility containing independent bays, which are leased to individuals exclusively for storage of goods or personal property. In addition to standard commercial buffers, a 75-

foot landscaped strip fronting the right-of-way shall be required. If abutting a commercial or industrial zoned property, the property shall include a 20-foot landscaped strip in the side and rear lot. All landscape strips shall have one tree planted every 20 feet, at least 5-foot tall at time of planting. If abutting residential districts, a 75-foot buffer applies and shall remain undisturbed, in addition to a six-foot fence to be installed at the buffer. Buildings may only take up 30 percent of the ground area of the lot.

When filing for the Conditional Use Permit, the applicant shall submit a site plan showing all standard buffers and proposed landscaping, including types of trees to be used. In addition to a site plan, an artistic rendering of the landscape strip from ground view must be submitted. The Planning Commission or County Commissioner may condition the application to increase buffers, setbacks, landscaping or other items. Existing Storage Facilities are made nonconforming by this provision and therefore shall need to file a conditional use application to expand.

IX. Article X to be amended by adding Sec. 10.2

Any lot zoned A-1 that is greater than 10 acres and has at least 100 feet of contiguous public road frontage is allowed to have an additional conventional single-family home.

X. Article X to be amended by adding Sec. 10.4

When replacing an existing residential structure—whether conventional, industrialized, or manufactured—with a new residential structure, a building permit for the new structure may be issued prior to the demolition or removal of the existing structure, provided that the subject property is one (1) acre or larger in size. The existing residential structure must be fully removed prior to the final erosion control inspection.

All building permits issued pursuant to this provision shall be subject to the time limitations set forth in Section 18-168; must be completed within 12 months from the date of permit issuance.

XI. Article XVI to be amended by deleting Sec. 16.5 and replacing with the following:

An application for a conditional use which was denied shall not be resubmitted for a period of 12 months, counting from the date of denial to the date of renewed application. If an application is withdrawn after the Planning Commission’s hearing, a new application may not be resubmitted for consideration for a period of six (6) months, counting from the date of renewed application. Unless withdrawn at the hearing, the withdrawal must be in writing, signed and dated by the applicant.

The Planning Commission recommended approval with a 6-0 vote. There were no registered speakers for the amendments. Commissioner Taylor approved the amendments as presented.

• Z-25-00036; an application by Copart of Connecticut, Inc. requesting a Conditional Use permit for retail storage of operable and inoperable vehicles on 15 acres located on Beasley Road (Tax Parcel #0052-0972-007). The Planning Commission recommended approval with a 5-0 vote with 1 Commission member abstaining. Commissioner Taylor approved the Application as presented.

• Z-25-00037; an application by Kailah Dempsey requesting to rezone a 1 acre lot at 199 Road No. 2 from A-1 to R-1 in order to separate the parcel from the parent parcel and build one single-family home. The Planning Commission recommended approval with a 6-0 vote.

There were no registered speakers. Commissioner Taylor approved the application as presented.

Having no further business to address, the meeting adjourned at 10:15 a.m.

Signature on File Kathy Gill, County Clerk

APPROVED:

Signature on File Steve Taylor, Sole Commissioner 10/1/2025 Date