BURKE COUNTY BOARD OF COMMISSIONERS PUBLIC WORKS COMMITTEE MARCH 18, 2026 The Public Works Committee of the Burke County Board of Commissioners met on Wednesday, March 18, 2025, at 9:00 a.m. in the Training Room. The meeting was called to order by Committee Chairman Tommy Nix at 9:00 a.m. Committee members Art Lively and Rodney Braswell, along with Commissioners Terri Lodge Kelly, Evans Martin, County Manager Merv Waldrop, and Assistant County Manager Adam Flakes, were in attendance. Ron Smith, Public Works Director, reported that the Cobb Road project is anticipated to be completed by April 14, 2026. Assistant Manager Flakes advised that the estimated cost for crusher run materials to complete the project is $155,000 but that continued maintenance needs to be considered. There was a consensus to contact the landowner in the Magruder Road area to discuss establishing an easement clean-out agreement to support future maintenance. Flakes noted that funding for the crusher run will be provided from the General Fund, while the purchase of a mini excavator will be funded through SPLOST III. Manager Waldrop reported that the roundabout project at Olympic Drive and Southside Drive has expanded due to several modifications to the original plan. The initial cost estimate for the project, prior to these changes, was $1.5 million. He further noted that the School Board is unable to contribute funding toward the project. As the County remains interested in acquiring approximately seven acres at the Olympic Drive and Southside Drive location, there was a consensus to contact School Board members to determine a land value that could be applied as the School Board’s share of project funding. The Board discussed the list of large projects, during which Ron Smith reported that ten rights-of-way on Glisson Road are still outstanding and noted that several property owners have indicated no intention of signing. The Board discussed whether the road could be paved without the required rights-of-way. Additional discussion included Williams Circle, Susie Bailey Road, Walnut Street, Perkins Mill Road, and Perkins Road, with consideration given to the number of houses impacted, traffic volume, and the potential for project modifications. Manager Waldrop recommended that the Road Department compile a list of roads it deems necessary for paving. Following discussion, consensus was reached to modify the top six major paving projects to include Glisson Road, Perkins Mill Road, Perkins Road, Walnut Street, Susie Bailey Road, and Williams Circle, with Susie Bailey Road and Williams Circle to receive crusher run pending the outcome of the Cobb Road project. The Board then discussed the small project paving list. Following consideration of survey data and right-of-way requirements, the list was revised to identify the top five priorities as Manderson Circle, Plantation Road, Lawson Road, Utley Road, and Raes Bridge Road. It was noted that Lawson Road and Utley Road will require utility line relocations, which will necessitate additional right-of-way acquisition. Consensus was to contract this project out. Nathaniel Howard Road was added to the requested road paving list. Ron Smith provided an update on the Middleground Road project. LMIG 2026 projects were discussed. These projects include Reddick Road, Collins Road, Claxton Lively Road, Ridge Point Drive, Meadow View Lane, and Bayberry Court. Commissioner Braswell inquired about the petition to close Neely Circle and expressed opposition to the proposed closure. Commissioner Nix requested that the petition be placed on a future agenda for a vote to determine whether to proceed. There being no further business, the meeting was adjourned at 10:23 a.m. _______________________________ ________________________________ R. Tommy Nix, Committee Chairman Art Lively, Commissioner _________________________________ ________________________________ Rodney Braswell, Commissioner Merv Waldrop, County Manager