Skip to content
Georgia Commons
Menu

City: Williamson

Williamson City Council work session, April 23, 2026

1 page

These are the minutes as Williamson City Council posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Williamson City Council.

This record was posted as scanned images, read here by OCR: a letter or a number may be misread. The file the body posted is linked below.

Copy for LLM, View as markdown, and Send to AI use the Markdown version: the summary Georgia Commons wrote, under a heading that names it, then the record as posted. View raw is the record alone.

Records of this meeting

Each link opens the body's own website or meeting portal.

  • MinutesMinutes (www.cityofwilliamsonga.org) · shown on this page

Summary

Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.

Council voted 3-0 to contract with McLeRoy to complete the city's amphitheatre after reviewing and eliminating several other bids.

At a work session with the mayor and three council members present, the council reviewed bids for the city's amphitheatre. The mayor provided a spreadsheet comparing bids on materials, electrical work, conformity to the original design, and completion time. The council eliminated several contractors for not following the RFP or the design, or for cost. One resident spoke during public comment and urged eliminating contractors that did not follow the full design. The council discussed adding a concrete pad at the back access door and more outlets, including ceiling outlets. A council member then moved to contract with McLeRoy to complete the amphitheatre as specified, and the motion carried 3-0. The minutes say the work may be complete in time for a July 4 celebration.

Topics taken up: amphitheatre bid review; McLeRoy contract; contractor disqualifications; concrete pad and outlets; July 4 completion timeline; public comment on amphitheatre.

Decisions the minutes record (1)

Each decision is followed by the sentence of the minutes that records it, copied word for word.

  1. Contract with McLeRoy to complete the amphitheatre as specified

    Adopted3-0

    The minutes: “CB moved to contract with McLeRoy to complete the amphitheatre as specified and SL seconded.”

Answers are written by AI from this document, and every quotation is checked against it. Not legal advice.

The minutes

As posted on www.cityofwilliamsonga.org, read November 12, 2026. Nothing below is written by Georgia Commons.

The City of Williamson

P.O. Box 9 Williamson, Georgia 30292 Steve Fry, Mayor John Smithson, City Council Post 3 Stephen Levin, City Council Post 1 Carol Berry, City Council Post 4 Bob Harrison, City Council Post 2 Vacant, City Council Post 5

MINUTES

Workshop

23 April 2026 7:00 PM

**Mayor and all council except B. Harrison in attendance**

I. WELCOME.......... Mayor Steve Fry-7:00p

Il. APPROVAL OF THE AGENDA (0.C.G A. § 50-14-1 (e) (1))-CB/SL 3-0

III. BUSINESS

A. Review and Discussion of Amphitheatre Bids-Mayor provided a spreadsheet simplifying data from all bids for comparison. Discussed materials, electrical, conformity to original design specifications, and completion timeframes. Council eliminated MMC Contracting from consideration since they did not address many of the points outlined in the RFP. Headley was disqualified as cost was prohibitive and they did not follow design provided. Riley Contracting was excluded as plans listed wood beams instead of steel, which caused concern over carpenter bees and upkeep. Flint Contracting was the most competitive bid but deviated from the original plans and utilized wood beams. McLeRoy bid was responsive to RFP and may be able to complete work in 60 days dependent on steel fabrication but did not include electrical outlets. May be complete in time for a July 4" celebration. Discussed ease of adding outlets and need to also install outlets in the ceiling for lighting or other future needs.

Motion to allow public comment CB/SL 3-0. Mr. Pugh was the only citizen in attendance, and he suggested eliminating any contractors that did not follow the city’s total design. McLeRoy and Southern Venture Partners were noted as the only two that met this criteria. He expressed desire to complete the amphitheatre, and it was advised other citizens have also wanted to see it done.

Southern Venture is out of Forsyth while McLeRoy is in Pike. Discussed use of local contractor.

Noted great price and good work done by McLeRoy. Southern Venture bid is over $100K more.

Addition of concrete pad on back at access door was deliberated. Worth the extra cost to add a concrete pad and more outlets.

CB moved to contract with McLeRoy to complete the amphitheatre as specified and SL seconded.

Further discussion in which McLeRoy’s proposal was read in its entirety. Motion carried 3-0.

IV. ADJOURNMENT-SL/JS 3-0 7:28p

APPROVED

ev.(B/% 40 pate: 3:'7-26

i

C4 U Lene ful, xO A PLS 24April 2026

Machine-readable https://georgiacommons.org/meetings/2026-04-23/williamson-city-council-work-session.md · https://georgiacommons.org/meetings/local/index.md · MCP https://mcp.georgiacommons.org/mcp

Williamson City Council work session, April 23, 2026 | Georgia Commons