Skip to content
Georgia Commons
Menu

City: Monroe

Monroe City Council regular meeting, July 12, 2026

9:00 AM · 5 pages

These are the minutes as Monroe City Council posted them, read from the file on its own website. Georgia Commons is independent and is not affiliated with Monroe City Council.

This record was posted as scanned images, read here by OCR: a letter or a number may be misread. The file the body posted is linked below.

Copy for LLM, View as markdown, and Send to AI use the Markdown version: the summary Georgia Commons wrote, under a heading that names it, then the record as posted. View raw is the record alone.

Records of this meeting

Each link opens the body's own website or meeting portal.

  • MinutesCity Council (monroega.granicus.com) · shown on this page

Summary

Written by an AI model (claude-sonnet-5-5) from the minutes below. It is not the record: the minutes are.

Council retreat reviewed a proposed 6.465 mill tax rate and city projects; no policy votes were taken, with adoption set for August 4.

The Mayor and Council held their annual retreat, a day of staff presentations and discussion with no votes on policy matters. The City Administrator reviewed a property tax study, which found large increases in assessed value for 63 commercial and apartment properties, and presented a proposed millage rate of 6.465 mills; Council is to meet August 4, 2026 to adopt the rate. Staff gave updates on grants, water, gas, electric, sidewalk and transportation projects, the wastewater treatment plant, fiber expansion, and downtown parking. Council asked for a second appraisal of 118 West Spring Street. A request to shut down the RF system on January 4, 2027, and a procurement policy update, are to come to Council in August. The retreat also covered police presence, homelessness, and staffing needs. The only recorded vote was to adjourn.

Topics taken up: property tax digest and millage rate; tax study of commercial properties; wastewater treatment plant bonds; fiber expansion and RF shutdown; downtown parking study; city property development; Alcovy River park project; additional police presence; procurement policy changes; future staff position needs; House Bill 434 airport zoning; Transportation Alternative Program projects.

Agenda items (8)

Found in the minutes by their headings. Where an outcome is shown, it was read by rule from the item's own words: a guide to the text, not part of the record.

  1. A. Property Assessment and Tax Digest Update and Discussion — Logan PropesA presentation
  2. B. Project Updates and DiscussionA presentation
  3. C. Waste Water Treatment Plant Update and DiscussionA presentation
  4. D. Organizational Chart Updates and DiscussionA presentation
  5. E. Red Flag Notification System
  6. F. Solid Waste — Transfer Station Agreements, Recycling Services, & 2026/2027 Capital Expense
  7. G. Welcome Center / 1821 Shoppe / Monroe Museum & Downtown UpdatesA presentation
  8. H. Storm Water Master PlanAdopted

Answers are written by AI from this document, and every quotation is checked against it. Not legal advice.

The minutes

As posted on monroega.granicus.com, read November 17, 2026. Nothing below is written by Georgia Commons.

BRwNtivs,

The Mayor and Council met for their annual Council Retreat.

Those Present: John Howard Mayor Lee Malcom Vice Mayor Julie Sams Council Member Adriane Brown Council Member Tyler Gregory Council Member Greg Thompson Council Member David Dickinson Council Member Logan Propes City Administrator Chris Bailey Assistant City Administrator Laura Powell City Clerk

Absent: Myoshia Crawford Council Member

Staff: Rodney Middlebrooks and Beth Thompson

Visitors:

None in attendance.

I. CALL TO ORDER — JOHN HOWARD

Il. WELCOME AND OPENING REMARKS

Mr. Logan Propes, City Administrator, welcomed everyone, and stated they were blessed to be operating in a City with cohesion and good working relationships. The goal, to provide the best level of service.

Ill. ITEMS OF DISCUSSION

A. Property Assessment and Tax Digest Update and Discussion — Logan Propes

Mr. Propes provided an overview of the City’s Property Tax Study and outcomes. He reminded Council that

the land values were undervalued, a reassessment of designated properties was conducted, and the results were discussed.

Key points of discussion:

Single-family homes have been taking the hardest hit for a decade plus.

Survey of Notable Commercial/Industrial Properties was presented and the findings were as follows:

o Forty commercial/industrial properties surveyed yielded an increase to the digest of $134.2+ million.

© The average increase to fair market value was 70%.

o Ifthese increases were to be taken County wide, billions would be saved.

Survey of Notable Apartment Complexes was presented and the findings were as follows:

o Twenty-three properties yielded an increase to the digest of $56.5+ million.

© The average increase to fair market value was 236%.

Survey Totals:

o The sixty-three properties assessed produced total digest assessment increases of $190,788,614.00, around 100% FMV.

o At the current tax rate of 6.934 mills, this could mean an additional $529,171 from these properties alone.

© Information is from preliminary tax digest, pre-appeals.

The 2026 Preliminary Tax Digest and the 2026 Final Tax Digest were presented.

Proposed a 6.465 millage rate, which is a record low.

Council will meet August 4, 2026 to adopt the millage rate.

B. Project Updates and Discussion

1. CDBG Community Block Grant

Mr. Middlebrooks updated Council that the 2024 CDBG — Sewer/Stormwater project will go out for bid late August.

2. Natural Gas - NGDISM / PHMSA Application for the Natural Gas - NGDISM/PHMSA grants have been submitted. These are 100% grant, no match. Bid documents are currently being prepared.

3. Natural Gas Rebate & Financing Program The Natural Gas Rebate & Financing Program was discussed. The rebate amounts will be updated, qualifying features will be added, and a campaign for natural gas is coming up.

4. Electric Substation (WEAG)

Mr. Middlebrooks stated that the engineers are done and the overhead needs to be placed undergrown.

Currently waiting on materials to complete project. ,

5. Electric - DOE / GRIP / GRID Resilience / GEFA Mr. Middlebrooks provided an update on grant projects:

- Grant M2982 to M25642: Years 1-3 were all funded; Breedlove Drive will be completed in 3-4 weeks.

- Grant M2122 to M1822: Currently completing the engineering portion;

6. Cherry Hill Water Tank Project is complete; two fittings are causing issues, and will be around 2 weeks to resolve issue, then testing.

7. AT&T Cellular Update — Wayne Street Water Tank Mr. Bailey mentioned the historical review due to the location, and that there is a process and waiting period. July 15" will be the restart of the installation plan.

8. West Spring Street Mural

Mr. Bailey stated that the proposed mural would be 518 linear feet on the retaining wall on West Spring Street. The mural will be funded through the Convention & Visitors Bureau (CVB), the design has been approved, and currently waiting on quotes from muralists.

9, Blaine Station

Council discussed details of the selection process (prior to engagement). Once a grant writer is chosen, it was suggested that all groups meet, for clarity and negotiation to begin the process. The first takedown is scheduled for September 2026.

10. Hammond Park Redevelopment Mr. Bailey shared that they are currently in the review process and should be finished with said process by year-end or beginning of 2027.

11. City Property Development Projects

a. 116 South Wayne Street

b. 125 South Wayne Street

c. 140 South Broad Street

d. 118 West Spring Street

e. 216 Davis Street

Mr. Bailey presented slides on the various properties and potential renderings. Council would like a second appraisal for 118 West Spring Street.

12. Downtown Hotel RFQ/P and Downtown Hotel Conceptual Design Historical calendar dates for the project were presented.

Mr. Propes reiterated a few of the specs for the project.

Project has slowed a bit due to interest rates.

There was a brief discussion on rates and budget.

'

13. Childers Park Updates Mr. Bailey presented the Rainbow Bridge Memorial Project.

14. Georgia Outdoor Stewardship Program / Alcovy River Project

Mr. Bailey shared that there is a meeting on July 21, 2026 with DNR. The goal is to have an agreement to Council in August or September 2026. Mr. Bailey shared that the total project is estimated to be completed in five years. There is a need for four additional employees, as well as park staff to monitor overnight.

15. Downtown Parking and Wayne Street Block Parking

Mr. Bailey shared Placer AI data and results from a study completed by Kromberg Urbanists + Architects from February 2023. Next, he presented a comparison of the amount of current parking spaces from the amount in 2023. The City of Monroe (COM) has seen an increase of 131 regular spaces and 20 handicap spaces. The parking deck equivalent for 131 spaces equals around $3.93M. There was a brief discussion.

16. Transportation Alternative Program (TAP) Mr. Bailey provided an update on grant projects:

- PI 0016630 — Lumpkin/Highland/Broad: cost estimate $3,871,203.00; 540 days for completion, beginning September 2025.

- PI 0019856 — Davis/Madison/Mears: cost estimate $3,865,000.00; Phase II completed in June 2026;

supplemental agreement in the month of August.

- PI 0019857 ~McDaniel/Childers/City Limits: cost estimate $2,500,000.00; Phase Il completed in April 2026; supplemental agreement in the month of August.

17. Streetscape, Storm Water, and Sidewalk Projects Mr. Bailey provided an update on grant projects:

- North Madison Streetscape and Storm Water: working on a grant for the cemetery fencing with Kim Mulkey-Smith.

- Church Street Streetscape

CITY COUNCIL RETREAT July 12, 2026 9:15A4.M.

- Midland Avenue Sidewalk Rehabilitation: design completion in May 2026; Materials ordered in June 2026; and Construction to start late July 2026. The City of Monroe (COM) will redo the sidewalks and the business owners will take care of everything else.

- Mr. Bailey shared a sidewalks overlay diagram of TAP projects.

18. SR 11/ US 78 Intersection Signalization

- The GDOT permit was submitted and the State Engineering Office approved.

~ The data study update occurred April/May 2026.

- The revised TE Study was submitted to GDOT Di June 12, 2026.

19. Northern Bypass Arc Project Administration will meet with Oglethorpe Power on Friday, July 17, 2026.

20. Charlotte Rowell Boulevard & Drake Drive Intersection A diagram of a possible roundabout was presented.

21. LMIG & LRA Funds Mr. Bailey shared the state funds and footages of paving since 2020 improved by the use of these funds.

22. Obstruction Removal Plans — LiDar Study and Airport Growth Mr. Bailey shared diagrams and timelines for the obstruction removals by the airport. The creation of a landscape proposal, for residents near the airport, was suggested to ensure this does not happen again. A

ten-year comparison of growth was shared and it was announced that Monroe would host the GAA conference in January 2027.

23. Georgia Army National Guard and Armory

Mr. Propes shared that there is an agreement for a land swap with the current National Guard location and Coker Park, near the airport. This type of agreement is the first of its kind in the State of Georgia. The City will take over the building on Washington Street and High School Avenue when the other facility is

completed. The current building may be used as a community room during business hours, and the park needs expansion.

24, Fiber Expansion

Mr. Bailey presented a colored diagram depicting the areas of completion, and summarized RF Decommission Status’ as follows:

Remaining Customers: 709 Total

Fiber Ready: 394 (fiber service is readily available, not swapped)

Not Active: 111 (Good Hope area and is currently being built)

Housing Authority: 204 (not allowed to install infrastructure, cancel or no contact)

A request was made, and will be added to the August Council Agenda for approval, to disconnect/shutdown the entire RF system on January 4, 2027. The shutdown will eliminate issues caused by deterioration of RF system and reduce costs of multiple system maintenance.

25. Telecomm Equipment Upgrades and Projects

Mr. Bailey spoke about the Accelecom Agreement that was signed in June 2026. The agreement “rents” eight fibers to Social Circle with the COM receiving $2,000.00/month in return. The COM also received a circuit upgrade (40 gig to 100 gig) at no cost.

Mr. Bailey presented a few other upgrades and projects:

- Arista Core Equipment to replace the old Cisco 9600 equipment. The change would provide various benefits in the case of disaster.

- In regards to an internal data center, a new plan, Adtran Mosaic (2027 CIP) to replace the old plan, ZCourm Tru Vision (Third Party). The reason for this change is historically, ZCourm has been a little difficult to work with, and Adtran allows internal controls.

- Telecomm wants to migrate to a Public [P. The current system is CGNAT and has issues with bandwidth bottlenecking. The new migration system, Public IP, would reduce this issue, as well as VPN issues.

C. Waste Water Treatment Plant Update and Discussion

Mr. Propes updated Council that the COM is working on the bonding portion and the engineering report. Next steps include the rating agency’s evaluation and the selling of bonds in October 2026. Mr. Middlebrooks added that the equipment has been purchased. A few important dates were mentioned: applications for bidder pre-qualification due by July 31, 2026, final report due the last week of July, and renewal of the Moratorium in September 2026. Once started, the buildout will take two years. There was a brief discussion.

D. Organizational Chart Updates and Discussion

Mr. Propes asked for this discussion to be pushed to the end of the meeting.

IV. OTHER GENERAL DISCUSSION

A. Open Record Requests

Mr. Bailey shared the stats for ORR. In the past year, Public Safety received 3,500+, Municipal Court received 25+, and City Hall Utilities received 350+.

B. Monroe Development Prospects

Mr. Bailey listed new prospects to the COM:

~ Sano Handtrucks

- Dycom Ridgeline Training Facility

- Tucker Door Expansion

- Athens Tech Campus Renovation

- MAP Pavilion Development

- MGM Products

C. Walton County Development Authority Buildings

Mr. Bailey shared the two properties for sale by the Walton County Development Authority:

- 111 East Spring Street — former USDA Office Building

- 203 Milledge Avenue — former Walton County Jail

Mr. Propes shared that four groups came for building walkthroughs.

D. House Bill 434 Airport Development

Mr. Bailey read, “Aviation and land-use law that requires local governments and airport sponsors to identify ‘airport affected areas’ and enact specific zoning regulations to prevent obstructions and protect safe airspace around public-use airports.”

Key mandates and deadlines:

- January 1, 2027 — Airport sponsors are required to formally identify the areas surrounding their airports that are affected by operations and notify the governing bodies of these locations.

- July 1, 2027 — Counties and municipalities (governing bodies) are required to hold public hearings and adopt specific land-use and zoning regulations for these affected areas.

Mr. Bailey presented several regulatory requirements as well.

E. Red Flag Notification System

Mr. Bailey detailed the notification system, from Telecomm, and it was explained to Council.

F. Solid Waste — Transfer Station Agreements, Recycling Services, & 2026/2027 Capital Expense

There was discussion on cost for hauling, potential decrease in frequency, possible partnership with Walton County, satellite-recycling locations, opt-in/opt-out options for recycling, and the ability for staff to make approvals.

G. Welcome Center / 1821 Shoppe / Monroe Museum & Downtown Updates

The 1821 Shoppe made $11,975.00 in the past year, and the Monroe Museum saw 3,507 visitors, with October being the busiest month (1,178 visitors).

Downtown Monroe was named a Georgia’s Exceptional Main Street (GEMS) community again. The Georgia Downtown Association 2026 Awards will be announced on July 17, 2026. The Downtown Development Authority (DDA) Stakeholder’s Event will be held, Tuesday, July 28, 2026, from 6-8 pm, at the Wayfarer Music Hall. Lastly, there was a brief discussion on small events versus big events.

H. Storm Water Master Plan

Mr. Bailey spoke about the Storm Water Master Plan and the items being developed and analyzed. However, there is certainly a need for public education.

I. Future Position Needs

The need for the following positions were presented:

- Main Street Events Coordinator ~ Secondary Position, Events, Main Street backup

- Digital Media Specialist — Social Media Assistant, Marketing Services, Narrative Coordination

- Social Media / Advertising —3™ Party Contractor, Internships, Marketing Communication Assistance

- Downtown Officers — Existing Efficiency, Dedicated Positions, Shifts

- Grant Specialist — Application, Management, Reporting, Procurement Coordination

- Parks Maintenance — Alcovy River Park, 2-4 additional positions

- Utility GIS Coordinator — Manage Current System, Data Input for Development

J. Special Event Permit & Assembly Permit Applications Mr. Bailey shared a few changes and that the process was going smoothly for the most part.

K. Procurement Policy Changes (State & Federal)

Mr. Bailey stated that there was an update to State House Bill 137, in December 2025, changing the bidding limits from $100k to $250k. The federal portion of the Procurement Policy still needs to be updated that produced a federal micro/small/formal limit update. This will be an agenda item at the August Council meeting.

ORGANIZATIONAL CHART UPDATES AND DISCUSSION

As previously mentioned, these items were discussed at the end of the meeting. Mr. Bailey, Mr. Middlebrooks, and Ms. Thompson left the room at 1:41 pm.

A. Project Management Updates

Mr. Propes stated that he would like to see management updated and rectified. The changes will occur over the next several months.

B. Additional Police Presence

There was a robust discussion regarding the need for additional police presence. Mentioned was this desire from downtown shop owners, DDA members, as well as various Council members. A letter from DDA, addressed to Chief Watts was read, and a tentative check list of to do items was discussed, for moving forward with the request.

C. Homelessness Issue The topic was discussed as this is a rising issue with no clear, easy solution.

VI. DISTRICT DISCUSSION

Councilmember Tyler Gregory: reported issues at the end of 5" Street, vines between 3“ Street and Barrett Street

need to be cut, trash on Walker Drive, and there is still a smell from the Biodiesel establishment that needs to be addressed.

Councilmember David Dickinson: agreed that the smell is not confined, and if it is not cleaned up, next steps need to occur.

Councilmember Ross Bradley: Nothing to report.

Councilmember Julie Sams: reported that e-bikes are becoming an issue because individuals drive on sidewalks, fly through stop signs, and do not wear helmets.

Councilmember Lee Malcom: Nothing to report.

Councilmember Adriane Brown: reported that the neighborhood at Ash Street needs repaving; an HOA is being established at Monroe Estates and a meet and greet is scheduled for next month; the traffic at Chestnut is better on the weekends, but the grass needs to be cut where turning out.

Councilmember Greg Thompson: asked about Ammons Bridge Road work and commented that cars drive so fast.

Mayor John Howard: praised the COM and Council for all of the projects that have been completed and still in process. He apologized for the fireworks location change and mentioned the COM was told they would be the

same as previous years.

VII. ADJOURNMENT -— 3:11

Motion by Sams, Seconded by Thompson Passed unanimously

LWE%L Peeve rll