MASSEY v. DUKE BUILDERS, INC
Filed September 28, 2020 · Docket S20G0018 · 849 S.E.2d 186
The Supreme Court of Georgia ruled that a contractor's materialmen's lien against a homeowner's property cannot include profits the contractor expected to earn on unfinished work, but that including such profits only voids the improper portion, not the entire lien.
In plain language
John and Stephanie Massey hired Duke Builders to rebuild their house after a fire. After disputes led Duke Builders to stop work, the company filed a lien against the property for over $197,000, which included both money owed for finished work and profit it expected to earn on work it never finished. The Masseys sued and asked the trial court to strike the lien because it included these anticipated profits; the trial court agreed and voided the entire lien. Duke Builders appealed, and the Court of Appeals of Georgia agreed that anticipated profits could not be part of the lien, but said the whole lien should not be thrown out just because part of it was improper. The Supreme Court of Georgia took the case to settle both points and agreed with the Court of Appeals on each: a lien cannot include profits not yet earned, but an otherwise valid lien survives even if part of the claimed amount was improper.
What the court decided
A materialmen's lien under Georgia law may include only amounts actually due for work already completed, not profits a contractor anticipated earning on future work; and when a lien improperly includes such nonlienable amounts, only the excess is void while the valid portion of the lien remains enforceable.
Why it matters
The ruling gives Georgia contractors, property owners, and courts a clear rule: liens can only cover money actually owed for completed work, but a contractor's mistake in overstating a lien will not automatically wipe out its right to be paid for legitimate work already performed.
Outcome
Affirmed
How the court got there
- The court examined Georgia's lien statutes (OCGA §§ 44-14-361 and 44-14-361.1), which let contractors file a lien for the 'amount due and owing' under a contract, and found this phrase limits the lien to money already earned for completed work, not profit expected from work not yet done.
- The court noted that OCGA § 44-14-361.1(e) reinforces this limit by capping total liens at the contract price of 'improvements made or services performed,' using past-tense language that excludes future, unearned profits.
- Applying older Georgia precedent (Pace v. Shields-Geise Lumber Co. and Hillburn v. O'Barr), the court held that when a lien claim exceeds what the claimant is legally entitled to, only the excess amount is void, not the entire lien, so long as the valid and invalid parts can be separated.
- The court found this severability rule, already applied by the Court of Appeals to materialmen's liens with improper amounts, applies with equal force whether the overage comes from claiming too much property or claiming too high a dollar amount.
- The court disapproved a conflicting Court of Appeals case that had voided an entire excessive lien, since that case did not address the separability question or account for the established line of cases allowing partial liens to survive.
- The court noted that Georgia law already lets a contractor amend a lien 'at any time' to reduce the amount claimed, supporting the Court of Appeals' suggestion that the trial court could direct Duke Builders to amend its lien to remove the improper profit amount on remand.
From the opinion
“If one’s claim exceed his right, the excess of the claim is void, but not the whole claim. A valid part may be included in that which is not sound as a whole, and the valid part may be legally asserted, while the invalid part fails.”
Topics
- materialmen's lien
- construction contract dispute
- anticipated profits
- lien validity
- homebuilding lawsuit