FRAZEN v. DOWNTOWN DEVELOPMENT AUTHORITY OF ATLANTA
Filed June 29, 2020 · Docket S20A0328 · 309 Ga. 411
The Supreme Court of Georgia upheld a trial court's approval of up to $1.25 billion in revenue bonds to help finance The Gulch redevelopment project in downtown Atlanta, rejecting citizens' challenges to the process and the funding structure.
In plain language
Four Atlanta residents opposed a plan by the City of Atlanta and its Downtown Development Authority to issue revenue bonds to help a private developer redevelop a blighted downtown area known as The Gulch. The bonds would be repaid only from special infrastructure fees collected from businesses in the area, not from general tax money, and would be issued in stages as construction progressed. A Fulton County judge held multi-day hearings, let the residents intervene as parties, rejected their objections, and ruled the bond plan sound, feasible, and reasonable. The residents appealed, arguing the judge should have held a separate hearing on their objections, wrongly ruled some of their later objections untimely, failed to explain his reasoning adequately, and that the funding arrangement was illegal under the Georgia Constitution's enterprise zone provision. The Supreme Court of Georgia rejected every argument, holding the trial court's procedures and findings were proper and that the law allowed the City to use enterprise zone infrastructure fees to secure bonds benefiting a private developer's public-serving redevelopment project.
What the court decided
The court held that the trial court properly allowed the citizen intervenors to participate, correctly limited late-filed objections, made adequate factual findings, and correctly concluded the bond issuance and its infrastructure-fee security were sound, feasible, and reasonable, and that Georgia law authorizes using enterprise zone infrastructure fees to secure bonds for a private developer's redevelopment work.
Why it matters
The ruling clears the way for a major downtown Atlanta redevelopment financed through infrastructure fees rather than general taxes, and it confirms that Georgia cities can use enterprise zone tools to partner with private developers on large blighted-area projects statewide.
Outcome
Affirmed
How the court got there
- The court found that Georgia's bond validation statute (OCGA § 36-82-77) requires a hearing on objections but not a separate, standalone hearing, and since the residents got extensive multi-day hearings and never objected to proceeding without further argument, there was no procedural error.
- Applying Georgia's Civil Practice Act rules on amending pleadings (OCGA § 9-11-15), the court held the residents became parties at the first hearing when the judge orally allowed intervention, so their later attempt to add more objections required the trial court's permission, which the judge reasonably denied as untimely.
- The court held that under the fact-finding statute (OCGA § 9-11-52), the trial court's order explaining it relied on hearing evidence, including proof that bonds would issue only after work was completed, gave enough explanation for appellate review, unlike a prior case where the trial court's findings were bare conclusions with no explanation.
- Reviewing the intergovernmental agreement between the City and the Development Authority, the court held Georgia's Enterprise Zone Employment Act and Redevelopment Powers Law together authorize a city to collect infrastructure fees from qualifying businesses in a designated enterprise zone and pledge those fees to secure bonds that fund a private developer's construction work, even though the project is privately built.
- The court held that the Georgia Constitution's enterprise zone provision does not exclusively control the City's fee-collecting power, because a separate constitutional clause gives the legislature general authority to pass laws for the state's welfare, and nothing in the enterprise zone provision forbids fees.
- On the amount of bonds, the court held that because the bonds are 'draw-down' bonds issued only in stages tied to verified construction costs and projected fee revenue meeting a coverage test, the trial court could reasonably find the plan sound and feasible even though total projected fees were far less than the maximum bond ceiling.
From the opinion
“The job of the courts is not to question the advisability or estimate the popularity of the City's decisions regarding the development of The Gulch.”
Topics
- The Gulch redevelopment
- bond validation
- enterprise zone
- infrastructure fees
- Downtown Development Authority of Atlanta