(a) Residential buildings.
(1) New construction. New construction of principal residential structures shall not be allowed within the limits of the future-conditions floodplain unless all requirements of Sections 10-15—10-17 have been met. If all the requirements of Sections 10-15—10-17 have been met, all new construction shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate the structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Section 10-19(e)(1).
(2) Substantial improvements. Substantial improvement of any principal residential structure shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Section 10-19(e)(1).
(b) Non-residential buildings.
(1) New construction. New construction of principal non-residential structures shall not be allowed within the limits of the future-conditions floodplain unless all requirements of Sections 10-15— 10-17 have been met. If all the requirements of Sections 10-15—10-17 have been met, all new construction shall have the lowest floor, including basement, elevated no lower than one foot above the base flood elevation, or at least as high as the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate the structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Section 10-19(e)(1). New construction that has met all the requirements of Sections 10-15—10-17 may be floodproofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be watertight to one foot above the base flood elevation, or at least as high as the future-conditions flood elevation, whichever is higher, with walls substantially impermeable to the passage of water and structural components have the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A licensed professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the City Manager, or his or her designee using the FEMA Floodproofing Certificate along with design and operation/maintenance plan.
(2) Substantial improvements. Substantial improvement of any principal, non-residential structure located in A1-30, AE, or AH zones, may be authorized by the City Manager, or his or her designee to be elevated or floodproofed. Substantial improvements shall have the lowest floor, including basement, elevated no lower than one foot above the base flood elevation or at least as high as the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate the structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Section 10-19(e)(1). Substantial improvements may be floodproofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be watertight to one foot above the base flood elevation, or at least as high as the future-conditions flood elevation, whichever is higher, with wall substantially impermeable to the passage of water and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A licensed professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the City Manager, or his or her designee using the FEMA Floodproofing Certificate along with the design and operation/maintenance plan.
(c) Accessory structures and facilities.
Accessory structures and facilities (i.e. barns, sheds, gazebos, detached garages, recreational facilities, and other similar non-habitable structures and facilities) which meet the requirements of Sections 10- 15—10-17 and are permitted to be located within the limits of the future-conditions floodplain shall be constructed of flood-resistant materials and designed to provide adequate flood openings in accordance with Section 10-19(e)(1) and be anchored to prevent flotation, collapse, and lateral movement of the structure.
(d) Standards for manufactured homes.
(1) New manufactured homes shall be allowed to be placed within the limits of the future-conditions floodplain unless all requirements of Sections 10-15—10-17 have been met. If all requirements of Sections 10-15—10-17 have been met, all new construction and substantial improvement shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation or one foot above the future-conditions flood elevation, whichever is higher. Should solid foundation perimeter walls be used to elevate the structure, openings sufficient to automatically equalize the hydrostatic flood forces on exterior walls shall be provided in accordance with standards of Section 10-19(e)(1).
(2) Manufactured homes placed and/or substantially improved in an existing manufactured home park or subdivision shall be elevated so that either:
a. The lowest floor of the manufactured home is elevated no lower than three feet above the level of the base flood elevation, or one foot above the future-conditions flood elevation, whichever is higher; or
b. The manufactured home chassis is elevated and supported by reinforced piers (or other foundation elements of at least an equivalent strength) of no less than 36 inches in height above grade.
All manufactured homes must be securely anchored to an adequately anchored foundation system to resist flotation, collapse, and lateral movement in accordance with standards of Section 10-19(g).
Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.