Title 36. LOCAL GOVERNMENT · Chapter 91. PUBLIC WORKS BIDDING · Article 2. CONTRACTING AND BIDDING REQUIREMENTS
36-91-24. Liquidated damages and other incentive provisions for project completion.
Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.
Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.
History
Code 1981, § 36-91-24, enacted by Ga. L. 2013, p. 628, § 6/SB 179.
Code Commission notes
Pursuant to Code Section 28-9-5, in 2013, Code Section 36-91-23, as enacted by Ga. L. 2013, p. 628, § 6/SB 179, was redesignated as Code Section 36-91-24.
Read the official page (the state's PDF, opened at the page this text was read from).
Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.
Text read from t36-ch60-92-(v27a)-2025-pdf.pdf, Volume V27A, 2025 edition, page 638; merge action: bound only; file SHA-256 5150ee8c60f7.