Georgia Commons

Official Code of Georgia Annotated

Title 36. LOCAL GOVERNMENT · Chapter 91. PUBLIC WORKS BIDDING · Article 2. CONTRACTING AND BIDDING REQUIREMENTS

36-91-24. Liquidated damages and other incentive provisions for project completion.

Active

Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.

  1. Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.

The notes below are printed with the section but are not enacted law (O.C.G.A. § 1-1-1(c)). They are shown apart from the text.

History

Code 1981, § 36-91-24, enacted by Ga. L. 2013, p. 628, § 6/SB 179.

Code Commission notes

Pursuant to Code Section 28-9-5, in 2013, Code Section 36-91-23, as enacted by Ga. L. 2013, p. 628, § 6/SB 179, was redesignated as Code Section 36-91-24.

Read the official page (the state's PDF, opened at the page this text was read from).

Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.

Text read from t36-ch60-92-(v27a)-2025-pdf.pdf, Volume V27A, 2025 edition, page 638; merge action: bound only; file SHA-256 5150ee8c60f7.

Ask about this section

The answer is drawn from this section and, when they fit, the other sections of its chapter. It quotes the text and names the section for each claim. Not legal advice.

Answers come from this document. Not legal advice.