36-91-24. Liquidated damages and other incentive provisions for project completion.
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
El texto siguiente es la ley tal como la imprime el estado, en inglés.
Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.
History
Code 1981, § 36-91-24, enacted by Ga. L. 2013, p. 628, § 6/SB 179.
Code Commission notes
Pursuant to Code Section 28-9-5, in 2013, Code Section 36-91-23, as enacted by Ga. L. 2013, p. 628, § 6/SB 179, was redesignated as Code Section 36-91-24.
Leer la página oficial (el PDF del estado, abierto en la página de la que se leyó este texto).
Actualizado hasta: Including Acts of the 2025 Session of the General Assembly of Georgia.
Texto leído de t36-ch60-92-(v27a)-2025-pdf.pdf, Volumen V27A, edición 2025, página 638; acción de fusión: bound only; SHA-256 del archivo 5150ee8c60f7.