Any development within any area of special flood hazard or area of future-conditions allowed under section 16-107 shall also meet the following conditions:

(1) Compensation for storage capacity shall occur between the average groundwater table elevation and the base flood elevation for the base flood, and between the average groundwater table elevation and the future-condition flood elevation for the futureconditions flood, and lie either within the boundaries of ownership of the property being developed and shall be within the immediate vicinity of the location of the

encroachment. Acceptable means of providing required compensation include lowering of natural ground elevations within the floodplain or lowering of adjoining land areas to create additional floodplain storage. In no case shall any required compensation be provided via bottom storage or by excavating below the elevation of the natural (pre-development) stream channel unless such excavation results from the widening or

relocation of the stream channel;

(2) Cut areas shall be stabilized and graded to a slope of no less than two percent;

(3) Effective transitions shall be provided such that flow velocities occurring on both upstream and downstream properties are not increased or decreased;

(4) Verification of no-rise conditions (0.01 foot or less), flood storage volumes, and flow characteristics shall be provided via a step-backwater analysis meeting the requirements of section 16-109;

(5) Public utilities and facilities, such as water, sanitary sewer, gas, and electrical systems, shall be located and constructed to minimize or eliminate infiltration or contamination from floodwaters; and

(6) Any significant physical changes to the base flood floodplain shall be submitted as a CLOMR or CLOMA, whichever is applicable. The CLOMR submittal shall be subject to approval by the city stormwater management office using FEMA community concurrence forms before forwarding the submittal package to FEMA for final approval. The responsibility for forwarding the CLOMR to FEMA and for obtaining the CLOMR approval shall be the responsibility of the applicant. Within six months of the

completion of development, the applicant shall submit as-built surveys for a LOMR.

History

The history line the source prints at the end of the section.

(Ord. of 11-4-2013, § 5-24.3(2))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:austell/zoning/16-108@2026-11-11-fd55cf0d0f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Austell Zoning Ordinance, Sec. 16-108. Conditions for development generally | Georgia Commons