Skip to content
Georgia Commons
Menu

Bogart · Zoning Ordinance

Article 10 - Project Design and Construction Standards / Division II - PROJECT CONSTRUCTION

Sec. 1018.02. Development phase inspections.

About this text

  • As posted on the city's website, retrieved 2026-11-14

Requests for inspections shall be made by the owner or contractor to the Planning, City Engineer/ Public Works, or Water Resources Department in accordance with the listing of inspection responsibilities established by the City of Bogart. Such requests shall be made at least 24 hours prior to when the inspection is needed. Inspections shall be made and passed prior to continuation of further activity or proceeding into new phases. Inspections are required Sec. 1018 Overview—project construction.

of each of the following phases, as applicable to the actual work to be performed under the development permit:

a. Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, inspection of erosion and sedimentation control measures and protective devices for undisturbed areas. Inspection of erosion and sedimentation control measures will be conducted on a continuing basis.

b. Upon completion of street grading, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.

c. Upon installation of storm drainage pipe, detention, or other storm water facilities.

d. Street curbing and gutter (if provided). Inspection shall be requested after the forms or string line have been set. Street width and vertical and horizontal alignment may be spot-checked.

e. Sub-grade of streets. The sub-grade may be roll tested in accordance with Sec.

1008.05.k.

f. Street base. The base may be string-lined for depth and crown. The street base will be tested for depth and compaction in accordance with Sec. 1021.05.e, and may be rolltested in accordance with Sec. 1008.05.k, at the discretion of the City Engineer/ Public Works Director.

g. Paving. A Road & Bridge Inspector may be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored, the asphalt will be tested for depth and compaction in accordance with Sec. 1021.05.e, and may be roll-tested in accordance with Sec. 1008.05.k, at the discretion of the City Engineer/ Public Works Director.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bogart/zoning/1018.02@2026-11-14-60f83b2e27

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bogart Zoning Ordinance, Sec. 1018.02. Development phase inspections | Georgia Commons