Article 11 - STREAM BUFFERS AND OTHER ENVIRONMENTAL REGULATIONS

11.4. Stormwater Management

About this text

  • As posted on the city's website, retrieved 2026-11-11

A. Purpose and Intent The purpose of this section is to protect, maintain, and enhance the public health, safety, environment, and general welfare by establishing minimum requirements and

procedures to control the adverse effects of increased post-construction stormwater

runoff and nonpoint source pollution associated with new development and redevelopment. Proper management of postconstruction stormwater runoff will minimize damage to public and private property and infrastructure; safeguard the public health, safety, environment, and general welfare of the public; and protect water and aquatic resources. Additionally, the Town of Braselton is required to comply with several state and federal laws, regulations, and permits, and the requirements of the Metropolitan North Georgia Water Planning District’s regional water plan related to managing the water quantity, velocity, and quality of postconstruction stormwater runoff.

B. Adoption and Implementation of the GSMM, Conflicts and Inconsistencies

1. In implementing this section, the Town of Braselton uses and requires compliance

with all relevant design standards, calculations, formulas, methods, and other guidance from the Georgia Stormwater

Management Manual (GSMM) as well as all related appendices.

2. This section is not intended to modify or repeal any other section of this

Development Code, ordinance, rule, regulation, or other provision of law, including but not limited to any applicable stream buffers under state and local laws, and the Georgia Safe Dams Act and Rules

for Dam Safety. In the event of any conflict or inconsistency between any provision in the Town of Braselton MS4 permit and this section, the provision from the MS4 permit applies. In the event of any conflict or inconsistency between any provision of

this section and the GSMM, the provision from this section applies. In the event of any other conflict or inconsistency

between any provision of this section and any other ordinance, rule, regulation, or other provision of law, the provision that is more restrictive or imposes higher

protective standards for human health or the environment applies.

C. Applicability Criteria The requirements of this section apply to any of the following activities:

1. New development that creates or adds 5,000 square feet or more of new impervious surface area or that involves land disturbance activity of 1 acre of land or more.

2. Redevelopment (excluding routine maintenance and exterior remodeling) that creates, adds, or replaces 5,000 square

feet or more of new impervious surface area or that involves land disturbance activity of 1 acre or more.

3. New development and redevelopment if it is part of a subdivision or other common plan of development, and the sum of all

associated impervious surface area or land disturbance activities that are part of the subdivision or other common plan of

development meets or exceeds the thresholds in (1) and (2) above.

4. Any commercial or industrial new development or redevelopment, regardless of size, that is a hotspot.

5. Road, sidewalk, or multi-use trail projects that exceed the threshold in (1) or (2)

above.

D. Exemptions The requirements of this section do not apply to any of the following activities:

1. Land disturbance activity conducted by local, state, authority, or federal agencies solely to respond to an emergency need to protect life, limb, or property, or conduct emergency repairs.

2. Land disturbance activity that consists solely of cutting a trench for utility work and related pavement replacement.

3. Land disturbance activity conducted by local, state, authority, or federal agencies whose sole purpose is to implement

stormwater management or environmental restoration.

4. Repairs to any stormwater management system deemed necessary by the Town Engineer.

5. Agricultural practices as described O.C.G.A. 12-7-17(5) within areas zoned for these activities with the exception of

buildings or permanent structures that exceed the thresholds in Sec. 11.4C.1 or 11.4C.2.

6. Silvicultural land management activities as described O.C.G.A. 12-7-17(6) within areas zoned for these activities with the

exception of buildings or permanent structures that exceed the thresholds in Sec. 11.4C.1 or 11.4C.2.

7. Installations or modifications to existing structures solely to implement Americans with Disabilities Act (ADA) requirements, including but not limited to elevator shafts, handicapped access ramps and parking,

and enlarged entrances or exits.

8. Road, sidewalk, or multi-use trail projects being constructed by Town of Braselton to the extent the Town Engineer determines

that these stormwater management standards may be infeasible to apply, all or in part, for any portion of the project. For this exemption to apply, an infeasibility report must first be submitted to the Town Engineer with adequate documentation to

support the evaluation for the applicable portion(s) and any resulting infeasibility determination, if any, by the Town

Engineer.

E. Stormwater Management Standards The following stormwater management standards apply. Additional details for each standard can be found in the GSMM Section 2.2.2.2.

1. Design of Stormwater Management System: The design of the stormwater management system must be in accordance with the applicable sections of the GSMM as directed by the Town

Engineer. Any design that proposes a dam must comply with the Georgia Safe Dams

Act and Rules for Dam Safety as applicable.

2. Natural Resources Inventory: Site reconnaissance and surveying techniques must be used to complete a thorough assessment of existing natural resources, both terrestrial and aquatic, found on the site. Resources to be identified, mapped, and shown on the Stormwater

Management Plan, must include, at a minimum (as applicable):

a. Topography (minimum of 2-foot contours) and areas with slopes greater than 15%.

b. Natural drainage divides and patterns.

c. Natural drainage features such as swales, basins, and depressional areas.

d. Natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers, drinking water wellhead protection areas, and river corridors.

e. Predominant soils, including erodible soils and karst areas.

f. Existing predominant vegetation including trees, high quality habitat, and other existing vegetation.

3. Better site design practices for stormwater management: Stormwater management

plans must preserve the natural drainage and natural treatment systems and reduce the generation of additional stormwater

runoff and pollutants to the maximum extent practicable. Additional details can be found in the GSMM Section 2.3.

4. Stormwater runoff quality/reduction:

Stormwater runoff quality/reduction must be provided by using the following:

a. For development with a stormwater management plan submitted before November 16, 2020, the applicant may choose either (i) Runoff Reduction or (ii) Water Quality.

b. For development with a stormwater management plan submitted on or after November 16, 2020, the applicant must choose (i) Runoff Reduction and additional water quality are not required. To the extent that (i) Runoff Reduction has been determined

to be infeasible for all or a portion of the site using the Practicability Policy, then (ii) Water Quality applies for the

remaining runoff from a 1.2 inch rainfall event and must be treated to remove at least 80% of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM.

i. Runoff Reduction. The stormwater management system must be designed to retain the first 1.0 inch of rainfall on the site using runoff reduction methods, to the maximum extent practicable.

ii. Water Quality. The stormwater management system must be designed to remove at least 80% of the calculated average annual postdevelopment total suspended solids (TSS) load or equivalent as defined

in the GSMM for runoff from a 1.2 inch rainfall event.

Stormwater Credits for Nonstructural Measures. The use of one or more site design measures by the applicant may allow for a reduction in the water quality treatment volume required under this subsection. The applicant may, if approved by the Town Engineer, take credit for the use of stormwater better site design practices and reduce the water quality volume requirement. For each potential credit, there is a minimum set of criteria and requirements that identify the conditions or circumstances under which the credit may be applied. The site design practices that qualify for this credit and the criteria and procedures for applying and calculating the credits are included in the GSSM, Volume 2. Downspout disconnect credit may not be taken for lots less than 1 acre.

c. If a site is determined to be a hotspot, the Town may require the use of

specific or additional components for the stormwater management system to address pollutants of concern generated by that site.

5. Stream channel protection: Stream channel protection must be provided by using all of the following three approaches:

a. 24-hour extended detention storage of the 1-year, 24-hour return frequency

storm event.

b. Erosion prevention measures such as energy dissipation and velocity control.

c. Preservation of any applicable stream buffer.

6. Overbank flood protection: Downstream overbank flood protection must be

provided by controlling the postdevelopment peak discharge rate to the pre-development rate for the 25-year, 24- hour storm event.

7. Extreme flood protection: Extreme flood protection must be provided by controlling the 100-year, 24-hour storm event such

that flooding is not exacerbated.

8. Downstream analysis: Due to peak flow timing and runoff volume effects, some

structural components of the stormwater management system fail to reduce discharge peaks to pre-development levels downstream from the site. A downstream

peak flow analysis must be provided to the point in the watershed downstream of the site or the stormwater management

system where the area of the site comprises 10% of the total drainage area in accordance with Section 3.1.9 of the

GSMM. This is to help ensure that there are minimal downstream impacts from development on the site. The downstream analysis may result in the need to resize structural components of the stormwater

management system.

9. Stormwater management system inspection and maintenance: The components of the stormwater management system that will not be dedicated to and accepted by the Town, including all drainage facilities, best management practices, credited conservation spaces, and conveyance systems, must have an inspection and maintenance agreement to ensure that they continue to function as designed. All new development and redevelopment

sites must prepare a comprehensive inspection and maintenance agreement for the on-site stormwater management system. This plan must be written in accordance with the requirements of Sec.

11.4F.

F. Pre-Submittal Meeting, Concept Plan, and Stormwater Management Plan

Requirements

1. Before a land development permit application is submitted, an applicant may request a pre-submittal meeting with the Town. The pre-submittal meeting should

take place based on an early step in the development process such as before site

analysis and inventory (GSMM Section 2.4.2.4) or the stormwater concept plan (GSMM Section 2.4.2.5). The purpose of the pre-submittal meeting is to discuss opportunities, constraints, and ideas for the stormwater management system

before formal site design engineering. To the extent applicable, local and regional watershed plans, greenspace plans, trails and greenway plans, and other resource

protection plans should be consulted in the pre-submittal meeting. Applicants must request a pre-submittal meeting with the Town when applying for a

Determination of Infeasibility through the Practicability Policy.

2. The stormwater concept plan must be prepared using the minimum following steps:

a. Develop the site layout using better site design techniques, as applicable

(GSMM Section 2.3).

b. Calculate preliminary estimates of the unified stormwater sizing criteria

requirements for stormwater runoff quality/reduction, channel protection, overbank flood protection, and extreme flood protection (GSMM Section 2.2).

c. Perform screening and preliminary selection of appropriate best management practices and identification of potential siting locations (GSMM Section 4.1).

3. The stormwater concept plan must contain all of the following:

a. The common address and a legal description of the site.

b. A vicinity map.

c. Existing conditions and proposed site layout mapping and plans

(recommended scale of 1 inch = 50 feet), which illustrate at a minimum the following:

i. Existing and proposed topography (minimum of 2-foot contours).

ii. Perennial and intermittent streams.

iii. Mapping of predominant soils from USDA soil surveys.

iv. Boundaries of existing predominant vegetation and proposed limits of clearing and grading.

v. Location and boundaries of other natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers, and other setbacks such as drinking water well setbacks, septic setbacks, etc.

vi. Location of existing and proposed roads, buildings, parking areas, and other impervious surfaces.

vii. Existing and proposed utilities (water, sewer, gas, electric, etc.) and easements.

viii. Preliminary estimates of unified stormwater sizing criteria requirements.

ix. Preliminary selection and location, size, and limits of disturbance of proposed BMPs.

x. Location of existing and proposed conveyance systems such as grass channels, swales, and storm drains.

xi. Flow paths.

xii. Location of the boundaries of the base flood floodplain, futureconditions floodplain, and the floodway (as applicable) and

relationship of site to upstream and downstream properties and drainage.

xiii.Preliminary location and dimensions of proposed channel modifications, such as bridge or culvert crossings.

4. The stormwater management plan must contain the items listed below and be prepared under the direct supervisory control of either a registered Professional Engineer or a registered Landscape

Architect licensed in the state of Georgia.

Items (c), (d), (e), and (f) must be sealed and signed by a registered Professional

Engineer licensed in the state of Georgia.

The overall site plan must be stamped by a design professional licensed in the State of Georgia for such purpose. (GSMM Section

2.4.2.7)

a. Natural resources inventory

b. Stormwater concept plan

c. Existing conditions hydrologic analysis

d. Post-development hydrologic analysis

e. Stormwater management system

f. Downstream analysis

g. Erosion and sedimentation control plan

h. BMP Landscaping plan

i. Inspection and maintenance agreement

j. Evidence of acquisition of applicable local and non-local permits

k. Determination of infeasibility (if applicable)

5. For redevelopment and to the extent that existing stormwater management

structures are being used to meet stormwater management standards, the following must also be included in the stormwater management plan for existing stormwater management structures:

a. As-built drawings

b. Hydrology reports

c. Current inspection of existing stormwater management structures, with deficiencies noted

d. BMP Landscaping plans

G. Application Fee Each land development application must be accompanied by a fee determined by a

schedule of fees adopted by the Town Council from time to time. Payment must be made

before the issuance of any land disturbance permit or building permit for the development.

H. Application Procedures Land development applications are handled as part of the process to obtain a land

disturbance permit or building permit as applicable. Before any person begins

development on a site, the owner of the site must first obtain approval based on the

following procedure:

1. File a land development application with the Town with all of the following

supporting materials:

a. The stormwater management plan prepared in accordance with Sec.

11.4F.4.

b. A certification that the development will perform in accordance with the

stormwater management plan once approved.

c. A Preliminary Determination of Infeasibility, if applicable, prepared in accordance with the practicability

policy.

d. An acknowledgement that applicant has reviewed the Town of Braselton’s form of inspection and maintenance agreement, and that applicant agrees to sign and record the inspection and maintenance agreement before the final inspection.

2. The Town Engineer must inform the applicant whether the application and supporting materials are approved or disapproved.

3. If the application or supporting materials are disapproved, the Town Engineer must

notify the applicant in writing. The applicant may then revise any item not meeting the requirements of this section and resubmit for the Town Engineer to

again consider and either approve or disapprove.

4. If the application and supporting materials are approved, the Town of Braselton may

issue the associated land disturbance permit or building permit, provided that all other legal requirements for the issuance of such permits have been met. The

stormwater management plan included in approved applications becomes the approved stormwater management plan.

I. Compliance with the Approved Plan

1. All development must be consistent with the approved stormwater management

plan and all applicable land disturbance and building permits, and be conducted

only within the area specified in the approved stormwater management plan.

2. No changes may be made to an approved stormwater management plan without

review and advanced written approval by the Town Engineer.

J. Inspections During Construction Periodic inspections of the stormwater management system during construction must be conducted by Town staff or conducted and certified by a professional engineer who has been approved by the Town.

Inspections must use the approved stormwater management plan for establishing compliance. All inspections must be documented with written reports that

contain the following information:

1. The date and location of the inspection.

2. Whether the stormwater management system is in compliance with the approved stormwater management plan.

3. Variations from the approved stormwater management plan.

4. Any other variations or violations of the conditions of the approved stormwater

management plan.

K. Final Inspection, As-Built Drawings, Delivery of Inspection and Maintenance Agreement

Upon completion of the development, the applicant is responsible for all of the following:

1. Certifying that the stormwater management system is functioning properly and was constructed in conformance with the approved stormwater management plan and associated hydrologic analysis. The required certification must include a certification of volume, or other performance test applicable to the type of stormwater management system

component, to ensure each component is functioning as designed and built according to the design specifications in the approved stormwater management

plan. This certification and the required performance tests must be performed by a qualified person and submitted to the

Town with the request for a final inspection. The Town must perform a final inspection with applicant to confirm

applicant has fulfilled these responsibilities.

2. Submitting as-built drawings showing the final design specifications for all

components of the stormwater management system as certified by a professional engineer.

3. Certifying that the landscaping is established and installed in conformance with the BMP landscaping plan.

4. Delivering to the Town a signed inspection and maintenance agreement that has

been recorded by the owner in the property record for all parcel(s) that make up the site.

L. Violations and Enforcement Any violation of the approved stormwater management plan during construction, failure to submit as-built drawings, failure to submit a final BMP landscaping plan, or failure of the final inspection will constitute and be

addressed as violations of, or failures to comply with, the underlying land disturbance permit or the underlying building. To address a violation of this section, the Town has all the powers and remedies that are available to it for other violations of building and land disturbance permits, including without

limitation the right to issue notices and orders to ensure compliance, stop work orders, and penalties as set forth in this Development Code.

M. Maintenance of Systems Predating Current

GSMM

Any stormwater management systems approved and built based on requirements predating the current GSMM and that are not otherwise subject to an inspection and

maintenance agreement must be maintained by the owner so that they perform as they were originally designed.

N. Inspection and Maintenance Agreements

1. The owner must execute an inspection and maintenance agreement with the Town

obligating the owner to inspect, clean, maintain, and repair the stormwater management system, including vegetation in the final BMP landscaping plan. The form of the inspection and maintenance agreement must be the form provided by the Town. After the inspection and maintenance agreement has been signed by the owner and the Town, the owner must promptly record the agreement at the owner’s cost in the property record for all parcel(s) that make up the site.

2. The inspection and maintenance agreement must identify by name or official title the person(s) serving as the point of contact for carrying out the

owner’s obligations under the agreement.

The owner must update the point of contact from time to time as needed and upon request by the Town. Upon any sale or transfer of the site, the new owner must notify the Town of Braselton in writing

within 30 days of the name or official title of new person(s) serving as the point of contact for the new owner. Any failure of an owner to keep the point of contact up to date will, following 30 days’ notice,

constitute a failure to maintain the stormwater management system.

3. The inspection and maintenance agreement must run with the land and bind all future successors-in-title of the site. If there is a future sale or transfer of only a portion of the site, then:

a. The parties to such sale or transfer may enter into and record an assignment

agreement designating the owner responsible for each portion of the site and associated obligations under the

inspection and maintenance agreement. The parties must record and provide written notice and a copy of such assignment agreement to the Town.

b. In the absence of a recorded assignment agreement, all owners of the site are jointly and severally liable for all obligations under the inspection and maintenance agreement

regardless of what portion of the site they own.

O. Right of Entry for Maintenance Inspections The terms of the inspection and maintenance agreement must provide right of entry for the Town for maintenance inspections and other specified purposes. If a site was developed before the requirement to have an inspection and maintenance agreement or an inspection and maintenance agreement was for any reason not entered into, recorded, or has otherwise been invalidated or deemed insufficient, then the Town has the right to enter and make inspections pursuant to Sec. 13.6B.

1. Any temporary or permanent obstruction that inhibits access to the property or

facility to be inspected and/or sampled must be promptly removed by the owner or operator at the written or oral request of the Town and must not be replaced. The

costs of clearing access must be covered by the owner or operator.

2. Vehicular access to every stormwater facility must be provided directly from an abutting street, or by access easement

between the facility and the nearest street.

This easement must be cleared of any trees and shrubs, must be unpaved and no less than 20 feet wide, and must have a

maximum grade of 12%.

3. If the Town or its agent, has been refused access to any part of the premises from

which stormwater is discharged, and the Town is able to demonstrate probable cause to believe that there may be a violation of this section; or that there is a need to inspect and/or sample as part of a routine inspection and sampling program

designed to verify compliance with this section or any order issued under the provisions of this section; or to protect the overall public health, safety, environment, and welfare of the community; then the

Town may seek a search warrant from any court of competent jurisdiction.

4. In the event that a discharge constitutes an immediate danger to public health or

public safety, the Town or its agent, is authorized to enter the subject property without giving prior notice and to take any and all measures necessary to abate the

violation and/or restore the property. The Town is authorized to seek costs of the

abatement from the owner or operator.

P. Owner’s Failure to Maintain the System The terms of the inspection and maintenance agreement must establish what constitutes a failure to maintain a stormwater management system and the enforcement options available to the Town. If a site was developed before the requirement to have an inspection and

maintenance agreement, or an inspection and maintenance agreement was for any reason not entered into, recorded, or has otherwise been invalidated or deemed insufficient, then:

1. An owner’s failure to maintain the stormwater management system so that it performs as it was originally designed constitutes and must be addressed as a violation of, or failure to comply with, owner’s property maintenance obligations consistent with this Development Code.

2. To address a failure to maintain the stormwater management system, the Town has all the powers and remedies that are available to it for other violations of an owner’s property maintenance obligations, including without limitation prosecution, penalties, abatement, and emergency

measures.

Q. Other Design and Construction Standards

1. Any required retention and/or detention areas must be incorporated into the

common areas of the residential development

2. Fences a minimum of 4 feet in height with a minimum 8 foot wide gate are required

on all detention ponds where:

a. The sides of the pond have a slope greater than 3 horizontal to 1 vertical, or

b. The depth of water in the pond is greater than 3 feet at one hour after the duration of any storm event up to the

50-year event.

3. Drainage easement requirements. The minimum easement width for an open ditch where a pipe is feeding into the ditch is determined as follows:

Pipe Size Feeding Into Ditch Min. Drainage Ditch Easement Width 15 to 30 inches 20 feet 36 to 66 inches 30 feet 72 inches and greater 40 feet

a. Where a subdivision is traversed by a watercourse, drainage way or stream,

there must be a drainage and access easement conforming substantially with the lines of the watercourse, and enough additional width to be adequate for drainage and maintenance, taking into account possible future development of higher land in the same drainage area, in accordance with the table above, or bank plus 20 feet. The drainage way must be piped when the Town Engineer finds that it is a hazard or that a continual maintenance problem might exist.

b. If the drainage way is piped, the easement width is calculated as the pipe diameter plus two feet plus two times the depth, rounded up to the nearest five-foot interval, but may be no less than 20 feet wide.

4. Stormwater inlets must be designed and located so as not to exceed a maximum

gutter spread width of half the travel lane based on flow data calculations for the 10- year storm event.

5. Pipe size is determined by utilizing the Rational Method or the Soil Conservation Service Method (TR-55) to compute peak

runoff. A 25-year storm event will be used to determine all pipe sizes. Hydraulic grade line may not exceed 90% of the diameter

of the pipe. All culverts under roadways must be sized based on a 50-year storm

event.

6. Manning's equation must be used to evaluate hydraulic capacity and velocity of flow within the storm drainage system.

Required storm pipes must be designed to maintain a water flow velocity greater than or equal to 3 feet per second. The hydraulic analysis of culverts must be based on

Federal Highway Administration engineering practice and take into account the inlet geometry, slope, size, roughness, and approach or tailwater conditions.

Stormwater inlets must be designed in accordance with Federal Highway Administration engineering practice and constructed in compliance with GDOT construction standards and conform with GDOT Standard 1033, 1034, and 1019.

Drainage calculation and design data are required for all stormwater conveyance

systems and structures. All drainage structures must be constructed of reinforced precast concrete, four feet diameter or larger. All 1033D and 1034D drainage structures must require a reinforced precast "Round to Square" adapter for additional throat support. All junction boxes must include precast

adapters and heavy duty traffic rated ring and covers. All manholes must include

approved steps, spaced 12 inches on center vertically, aligned with manhole cover to allow safe access by maintenance personnel. All structures must have paved inverts.

7. Pipe penetration of structures may not exceed 50% of inside wall perimeter .

8. All drainage ditches that are between building lots must be piped to the rear

property line.

9. The minimum cross drain diameter must be 15 inches.

10. Minimum pipe cover must be 24 inches.

11. In all instances, depth requirements must meet or exceed manufacturer's

guidelines.

12. Materials and installation.

a. Pipes.

i. Pipe material must be determined based on type of installation, as set forth in the table below. All pipes must be new and unused.

ii. The gauge or class of pipe used must be determined by acceptable methods using H-20 highway loading, and must meet GDOT specifications. The Town Engineer must inspect the pipe before installation to assure that it is free of cracks or damage. All damaged, used, or "second" quality pipe must be refused and immediately removed from the job site.

b. Joints and installation.

i. Reinforced concrete pipe joints must be properly constructed to prevent exfiltration.

ii. The use of O-rings or sealants may be required, depending on pipe design.

iii. All storm sewer piping must be constructed in a linear approach with no vertical or horizontal variance from the approved design.

iv. High density polyethylene (HDPE) and corrugated metal pipe (CMP) must be joined by manufacturer's recommended pipe banding materials. All trench lines must be thoroughly compacted prior to pipe installation. HDPE pipe will require special bedding and installation in strict accordance with manufacturer's specifications and as directed by the Town Engineer.

c. Selection Guidelines for Storm Sewer Piping Corrugated Steel AASHTO

M-36 Corrugated Aluminum

AASHTO M-196

Plastic

AASHTO M294

Reinforced Concrete Box Culvert Type of Pipe Installation Reinforced Concrete Pipe (RCP) Aluminized Type II CMP Bituminous Coated CMP Aluminum Alloy

CMP

Corrugated

HDPE

Smooth Lined Per GDOT Standards Longitudinal Grade < 10% Yes Yes Yes Yes Yes a – Longitudinal Grade Over 10% No Yes Yes Yes Yes a – Cross Drain < 250 ADT Yes No No No No – Cross Drain < 250 ADT Yes No No No No – Cross Drain Flowing Stream Application Yes No No No No – Cross Drain Flowing Stream Application b No No No No Yes Conditional Uses:

a Corrugated high density polyethylene pipe smooth lined type "S" must be manufactured and installed in strict compliance with the manufacturer's recommendation. Special backfill and bedding are required per the direction of the Town Engineer.

Prior approval of the Town Engineer is required.

b Reinforced concrete box culverts are required under excessive flow and/or fill depth conditions. Approved pipe materials may be utilized in some instances based on the Town Engineer’s assessment of existing conditions and future maintenance requirements.

c The addition of a type "A" full bituminous coating with paved invert is required for this application. (AASHTO M-190) d Requires approval of Town Engineer based on assessment of existing conditions and future maintenance requirements.

13. Only reinforced concrete pipe may be used within street right-of-way on arterial roads. Reinforced concrete pipe must be

used on all cross drains crossing under the roadway for major and minor collectors.

Concrete pipe may not be used on grades exceeding 10%. Metal pipe may be used within the rights-of-way of local streets and for driveway culverts. Metal pipe must

either be corrugated steel (AASHTO M-36) with aluminized Type II or bituminous

coating or corrugated aluminum alloy pipe

(AASHTO M-196).

14. Unless otherwise specifically set forth in this article, all of the materials, methods of construction, and workmanship for the

work covered in reference to stormwater drainage construction must conform to the latest standard specific specifications of the Georgia Department of Transportation.

15. Pipe installation must conform to GDOT Standard Specifications for construction of roads and bridges. Before any traffic over a storm drain is allowed, the developer

must provide an adequate depth and width of compacted backfill to protect the

structure from damage or displacement.

The developer must remove any debris or silt that constricts the flow through a pipe as necessary to maintain drainage. All pipe structures must be cleaned before the

work is accepted. Any damage or displacement that may occur due to traffic or erosion must be repaired or corrected at the developer's expense.

a. Trench construction for storm drainage pipe must be in accordance with State

Highway Standard 1030D (or most current) or as directed by the Town Engineer.

b. Storm drainage pipe must be bedded in Type 57 gravel where wet conditions

are encountered.

c. Backfilling of trenches must be accomplished immediately after the pipe is laid. The fill around the pipe must be placed in layers not to exceed 6 inches with each layer being thoroughly compacted. All material must have an in-place density of 98% modified proctor to a depth of 6 inches below the finished grade, and 95% modified proctor at depth greater than 6 inches below the finished grade.

Compaction requirements must be attained by the use of mechanical methods. Each layer of backfill must be placed loosely and thoroughly compacted in place.

d. All backfill must be non-plastic in nature, free from roots, vegetative matter, waste, construction material or other objectionable material. Backfill material must be capable of being compacted by mechanical means and must have no tendency to flow or behave in a plastic manner under the tamping blows.

e. Material deemed by the Town Engineer as unsuitable for backfill purposes must be removed and replaced with selected backfill material.

f. Water is not permitted to rise in trenches that are not backfilled after the pipe has been placed.

16. Field changes. Minor changes to approved construction plans because of field conditions must be documented as revisions to the approved development plans and correctly shown on the as-built drawings. Discrepancies between the asbuilt drawings and the approved development plans may result in delays in approving final plans or certificates of occupancy until the discrepancies are

resolved.

17. End walls. All culverts must have end walls or flared end sections constructed in accordance with GDOT Specifications and

the GDOT Manual on Drainage Design for Highways. All flared end sections under or adjacent to roadways with a posted speed in excess of 25 mph must be safety end

sections per GDOT standards.

18. Catch basins and storm sewer structures.

a. All catch basins and storm sewer structures must be designed and constructed in compliance with GDOT Specifications and conform with GDOT Standard 1033D, 1034D, or 1019.

b. The use of a Standard 1019 is excluded from turnarounds and the low point of

sag vertical curves draining more than 300 feet of gutter. Drainage calculations and design data are required for the use of a Standard 1019.

c. All drainage structures must be constructed of reinforced precast concrete, 4 foot diameter or larger.

d. All 1033D and 1034D drainage structures require a reinforced precast "Round to Square" adapter for additional throat support.

e. All junction boxes must include precast adapters and heavy duty traffic rated

ring and covers. All junction boxes must include approved steps, spaced 12

inches on center vertically, to allow safe access by maintenance personnel.

f. All storm sewer structures must be reinforced precast or poured in place reinforced concrete. Masonry structures are not allowed unless authorized in writing by the Town Engineer.

g. No length of pipe may exceed 200 feet without intermediate structures.

h. In certain instances where rolled curb is utilized, the Town Engineer may require

the use of 1033F and 1034F catch basins.

i. All structures must have poured inverts to minimize accumulation of water and

sediment in the structure.

j. All structure covers must be cast to read “Storm Sewer, Dump No Waste - Drains to Stream.”

R. Easements.

1. Drainage easements must be provided where a development is traversed by or contains a natural or manmade water course, impoundment, detention pond, floodplain, natural stream or channel. It must conform substantially to the limits of such natural drainage feature, but may be not less than 20 feet in width.

2. For manmade channels or drainage pipes, drainage easement widths are calculated

as the pipe diameter plus two feet plus two times the depth, rounded up to the nearest five-foot interval, but may be no less than 20 feet wide. Easement lines at stream

crossings must encompass the full extent of the culvert including maintenance area and any area required for access.

3. The owner of property containing a drainage easement may not allow or cause to be deposited any material which causes a physical obstruction, including, but not limited to: structures; landscaping; fences;

yard waste such as grass clippings, tree trimmings, and leaves; impervious cover;

or any other material that may block the flow of water or otherwise disrupt proper function of the stormwater management

system unless approved by the Town Engineer. All drainage easements must be kept clear of obstructions along the entire length of the easement whether it be a

buried pipe, ditch, or other facility contained within the easement. The property owner must remove any such materials existing prior to, or installed after, the effective date of this ordinance.

4. Easements for storm pipes, swales, ponds and other stormwater management

facilities must be located within open or common space owned and maintained by

a property owners’ association.

5. Drainage easements for improved ditches, pipe construction, and detention facilities must be cleared, opened, and stabilized

with erosion control measures at the time of development to control surface water

runoff.

6. Drainage easements outside of the street right-of-way must be clearly defined on the final subdivision plat. The property owner is required to keep the easement free of obstruction in such a way as to assure the maximum designed flow at all times. The

property owner may not alter any drainage improvements without prior written

approval from the Town Engineer.

7. Overlapping easements. Easements for water, sanitary sewers, and drainage purposes may be combined, with the approval of the Town Engineer, but must provide at least 7½ feet of pipe separation unless required otherwise by this code.

8. Easements for water, sewer, reuse or stormwater outside of the right of way must be platted in open space owned and maintained by a property owners’ association and may not be part of any residential lot.

S. Definitions The following definitions apply to this section.

Other terms used but not defined in this section should be interpreted based on how those terms are defined and used in the GSMM and the Town of Braselton MS4 permit.

Best management practice (BMP): Structural devices used to store or treat stormwater runoff and non-structural programs or practices which are designed to prevent or reduce the pollution of the waters of the State of Georgia.

BMP landscaping plan: A design for vegetation and landscaping that is critical to the

performance and function of stormwater best management practices (BMP), including how the BMP will be stabilized and established with vegetation. It includes a layout of plants and plant names (local and scientific).

Channel: A natural or artificial watercourse with a definite bed and banks that conveys continuously or periodically flowing water.

Detention: The temporary storage of stormwater runoff in a stormwater detention facility for the purpose of controlling the peak discharge.

Detention facility: A structure designed for the storage and gradual release of stormwater runoff at controlled rates.

Extreme flood protection: Measures taken to prevent adverse impacts from large storm events with a return frequency of 100 years or more.

Flooding: A volume of surface water that exceeds the banks or walls of a BMP or channel and overflows onto adjacent land.

GSMM: The latest edition of the Georgia Stormwater Management Manual, Volume 2:

Technical Handbook, and its Appendices.

Hotspot: A land use or activity that has the potential to produce higher than normal levels of pollutants in stormwater runoff. Hotspots may include gas stations, vehicle service, industrial uses, material storage sites, waste transfer facilities, and commercial parking lots with highintensity use.

Inspection and maintenance agreement: A written agreement providing for the long-term inspection, operation, and maintenance of a stormwater management system and its

components on a site.

New development: Land disturbance activities, structural development (construction, installation or expansion of a building or other structure), and/or creation of impervious surfaces on a previously undeveloped site.

Overbank flood protection: Measures taken to prevent an increase in the frequency and magnitude of out-of-bank flooding (flow events that exceed the capacity of the channel and enter the floodplain).

Post-construction stormwater management:

Stormwater best management practices used on a permanent basis to control and treat runoff once construction has been completed.

Post-development: The conditions anticipated to exist on site immediately after completion of the proposed development.

Practicability policy: The latest edition of the Metropolitan North Georgia Water Planning District’s Policy on Practicability Analysis for Runoff Reduction.

Pre-development: The conditions that exist on a site immediately before the implementation of the proposed development. Where phased

development or plan approval occurs (preliminary grading, roads and utilities, etc.), the existing conditions at the time before the first item being approved or permitted establish predevelopment conditions.

Pre-development hydrology: For new development, the runoff curve number determined using natural conditions hydrologic analysis based on the natural, undisturbed condition of the site immediately before implementation of the proposed development.

For redevelopment, the existing conditions hydrograph may take into account the existing development when defining the runoff curve number and calculating existing runoff, unless the existing development causes a negative impact on downstream property.

Previously developed site: A site that has been altered by paving, construction, and/or land disturbance activity.

Redevelopment: Structural development (construction, installation, or expansion of a building or other structure), creation or addition of impervious surfaces, replacement of

impervious surfaces not as part of routine maintenance, and land disturbance activities associated with structural or impervious development on a previously developed site.

Redevelopment does not include such activities as exterior remodeling.

Routine maintenance: Activities to keep an impervious surface as near as possible to its constructed condition. This includes ordinary maintenance activities, resurfacing paved areas, and exterior building changes or improvements which do not materially increase or concentrate stormwater runoff, or cause additional nonpoint source pollution.

Site: An area of land where development is planned, which may include all or portions of one or more parcels of land. For subdivisions and other common plans of development, the site includes all areas of land covered under an applicable land development permit.

Stormwater management system: The entire set of non-structural site design features and structural BMPs for collection, conveyance, storage, infiltration, treatment, and disposal of stormwater runoff in a manner designed to prevent increased flood damage, streambank channel erosion, habitat degradation and water quality degradation, and to enhance and promote the public health, safety and general welfare.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/11.4@2026-11-11-9c9a037896

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 11.4. Stormwater Management | Georgia Commons