Whenever it is necessary or desirable to locate a public utility line outside of a street right-of-way, the line must be located in an easement

dedicated to the Town (or other appropriate public entity) for such purpose.

A. Utility easements for electric and telephone service lines, sewage lines, water lines, or other similar utilities located along rear lot lines or side lot lines or passing through a lot must be at least 20 feet wide, and may be required to be wider depending on the depth of cut to maintain a 1:1 open cut slope. When warranted, temporary construction

easements widths may be required by the town. Pressurized water, sewer, or reuse lines proposed between residential buildings must be platted in common area no less than 30 feet wide and not on any part of an individual residential lot.

B. Easements for sanitary sewers may be required by the Town Engineer for future extension of lines, whether or not the

subdivision or development is currently proposed to be served by public sewer.

C. No structure may be built on a utility easement.

D. Utility easements for private utilities should be avoided except in cases where no other

satisfactory arrangements can be provided for the installation of private utilities.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/8.13@2026-11-11-f7c1c73344

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 8.13. Utility Easements | Georgia Commons