A. Persons seeking to undertake development activity may not commence or proceed until development plans are approved and a

development permit is issued by the Planning Director after all other departmental and agency approvals.

B. The development plan must generally conform to the preliminary plat, if any, and may constitute only that portion of the

approved preliminary plat which the developer proposes to construct at one time as a single unit, provided that the portion conforms to the requirements of this article and all

requirements of this Development Code. If no preliminary plat was approved on the

property, the development plan must include the entire property being developed within the same zoning district.

C. The development plans for a project must conform in all respects with the requirements of this Development Code, and must contain each of the plans in this Section as

appropriate to the project, including but not limited to:

1. Information provided in preliminary plat

2. Erosion and sedimentation control plan meeting the requirements of Sec. 11.4E

and Sec. 11.4F.

3. Grading plan, including all of the following:

a. Contour intervals

b. Maximum slope

c. Outline of areas required to remain undisturbed

d. Building pad grading

e. Embankment slopes

f. Grades of proposed roads and improved ditches

4. Stormwater management plan, including all of the following:

a. Location and size of all proposed drainage structures including detention ponds, catch basins, grates, headwalls, pipes, and any extension thereof, as well as energy dissipators, improved channels, and all proposed drainage easements to be located outside street right-of-way lines.

b. Profiles of all storm drainage pipes and the slope of receiving channels. The

hydraulic grade line must be shown on all profiles of pipes for the required design flow. On storm drainage profiles, a pipe chart must be shown which

includes pipe numbers, pipe sizes, pipe materials, pipe slopes, pipe length, contributing drainage area, design flow, design storm frequency, runoff

coefficient, velocity, and hydraulic grade lines of the design storm event.

c. Profiles of all open channels and ditches including Manning’s normal depth and velocity of the design storm.

On storm drainage profiles, an open channel chart must be shown including open channel numbers, conveyance size, lining material, length, channel slope, contributing drainage area, design storm frequency, runoff coefficient, and velocity.

d. Hydrologic and hydraulic calculations used in determining size of drainage

conveyance systems, including map of all contributing drainage basins and acreages.

5. Street improvement plan

6. Buffer and screening plan

7. Water and sewer plan

8. Floodplain management plan (if applicable)

9. Tree preservation and planting plan

10. Street lighting plan

D. Street improvement plan (must be prepared under the supervision of a professional

engineer and bear their stamp):

1. Center line profiles and typical street sections of all proposed streets are

required. Profiles must be drawn on standard plan and profile sheet with plan section showing street layout, pavement

and right-of-way width, curvature, and required drainage facilities. Typical street sections must be provided for street

widenings.

2. Where sanitary sewer or storm water sewers are to be installed within a street, the grade, size, location and bedding class of pipe, and the location and invert

elevation of manholes must be indicated on the road profile.

3. Center line profiles covering streets that are extensions of existing streets must

include elevations at 50-foot intervals for such distance as may be adequate to

provide continuity consistent with the standards required by this Development Code for street improvements, but no less than 200 feet.

4. All plan elevations must be coordinated and sited into U.S. Coast and Geodetic

Survey or Georgia Department of Transportation benchmarks where feasible or into reference monuments established by the Federal Emergency Management Agency.

5. A street striping plan, showing striping in accordance with the Manual on Uniform

Traffic Control Devices, latest edition as published by the Federal Highway

Administration, must be prepared for any street newly constructed or widened to 4 or more lanes.

E. Utility Plans

1. Sewage disposal plan: If connection to a public system is proposed, sewage

disposal plans are to include:

a. Sanitary sewerage plans, including profiles of all mains and outfalls, lift station and force main details, typical

manhole construction details, and other information as may be required by the Town Engineer.

b. For projects approved by the Town Council to be served by on-site sewage disposal systems, location of septic tank, extent of drain field and attendant structures, location and results of

percolation tests or soil data test locations, and other information must be shown as required by the applicable County Department of Environmental Health.

2. Domestic water supply plan: For projects to be served by public water, the domestic

water supply plan must depict all water system improvements, water mains, fire hydrants, valves and other appurtenances, and other information as may be required by the Town Engineer.

a. Domestic water supply and/or distribution systems must be designed and built in accordance with the latest edition of Town’s Water and Wastewater Standards as well as the Rules for Safe Drinking Water: Chapter 391-3-5, Revised June 1989 or latest edition, Georgia Environmental Protection Division.

b. Public water service must be provided to every lot in every subdivision and to every development for both domestic

use and fire protection if public water is available or under bid or contract to be available within 1,000 feet of the

development.

3. Fire hydrants are required in all developments served by a public water system. Hydrant spacing must follow the specifications of the Town or the applicable water service provider. Hydrant placement must be approved by the

applicable County Fire Department. A hydrant must be located every 500 feet or at every intersection, whichever is closer.

4. Sanitary sewer and domestic water capacity must be demonstrated to the satisfaction of the Public Works Director in accordance with established codes prior to the issuance of land disturbance and

building permits. The developer is responsible for providing and paying for necessary water and sewer extensions

including the addition of necessary capacity required to serve the development.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/8.7@2026-11-11-6e9e79ce45

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 8.7. Development Plan Requirements | Georgia Commons