Each development plan must carry the following certificates printed or stamped on the plat.

A. Signed approval from the applicable County Environmental Health Department (if septic tanks are allowed by the County).

B. Certificate of Project Approval, to read as follows:

CERTIFICATE OF PROJECT APPROVAL

All applicable requirements of the Town of Braselton Development Code relative to the project approval having been fulfilled,

approval is hereby granted by the Town Public Works Director, subject to further compliance with all provisions of the Development Code.

______________________________________ Town Public Works Director (or designee) Date__________________

This Certificate of Project Approval expires 12 months from the date of approval if a

development permit has not been issued or a development permit has been issued but

development activity has not commenced.

C. Signature of Owner and Developer of the Development.

D. Signature of the Planning Director with the following notation:

CERTIFICATE OF PLANNING APPROVAL

All applicable Planning and Zoning requirements of the Town of Braselton Development Code relative to the project approval have been fulfilled, approval is hereby granted by the Planning Director.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/8.8@2026-11-11-da0d142305

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 8.8. Evidence of Project Approval | Georgia Commons