(a) Runoff computations. A hydrology report must be submitted with engineering construction plans detailing pre- and post-development impact of runoff. The report shall cover all of the major storm events (two through 100). The developer must provide adequate stormwater management facilities to infiltrate, retain, or detain stormwater runoff. Post-development runoff or discharge shall be limited to the original estimated pre-development runoff for a 25-year storm event. The developer must make every effort to prevent damages to those properties down-gradient, which would be adversely effected by any additional stormwater runoff. Only stormwater management facilities located in a residential subdivision will be considered to be deeded to the city.
(b) Pipe culverts.
(1) The minimum allowable cross-drain pipe size shall be 15 inches in diameter.
(2) Bituminous coated corrugated metal pipe or concrete pipe shall be used for all storm drainage. When bituminous coating is specified, the invert shall be fully paved. Coupling bands shall be fully coated. Smooth lined polyethylene pipe (HDPE), which conforms to AASHTO M294-97, Type S in 12-inch to 48-inch and AASHTO MP7-97 in 54-inch and 60-inch, may be installed in dead load areas. HDPE used for crossdrainage shall strictly conform to installation procedures. Any other pipe material shall be submitted for pre-approval with installation.
(3) The minimum pipe velocity shall be five feet per second when the pipe is flowing two-thirds full.
(4) Storm drain lines of 30 inches in diameter and smaller shall be laid with uniform slopes and alignments between drainage structures spaced no more than 400 feet apart. A pre-cast or built-in-place junction box, conforming to state department of transportation standard 9031-U, or a catch basin is required at each change in direction.
(5) Pipe gauge shall be based on loading conditions and height of fill as per state department of transportation standard 1030-D, table No. 1. Minimum cover shall be 18 inches excluding pavement.
(c) Headwalls. Headwalls shall be provided at inlet and outlet points of all drainage systems.
Spillway aprons and energy dissipaters shall be provided integral with effluent headwalls when design velocities exceed ten feet per second when flowing at two-thirds full. A variance is required when energy dissipation area is over 20 lineal feet. All headwalls shall conform to state department of transportation standard 1125.
(d) Catch basins. Combination curb and gutter catch basins shall be provided at the upstream end of the curb radius at intersecting streets, and at intermediate points as required for adequate drainage. Particular care shall be taken to maintain proper street crown to insure effective performance of inlets. At low points, provide catch basins on both sides of the street with a minimum of one combination curb and gutter inlet for each three cfs of predicted inlet flow, plus 20 percent assumed spillover from all upgrade inlets. Provide grates having openings perpendicular to the direction of traffic flow so as to avoid creating a hazard to bicycle traffic.
All single side catch basins shall conform to state department of transportation standards 1033-D and 1033-D pre-cast. All double-sided catch basins shall conform to state department of transportation standards 1034-D and 1034-D pre-cast.
(e) Area drains and grates. Area drains and grates may be utilized in areas other than dedicated streets.
(f) Improved drainage channels. Existing drainage channels may be improved where excessive erosion of banks has occurred. Channel banks may be covered with erosion control matting to establish grass. Channels shall not be lined with riprap. Only hand clearing shall be permitted within 25 feet of a flowing stream, and/or creek; otherwise any encroachment requires a buffer variance from the governing authority issuing land-disturbing activities.
(g) Installation. Pipe installation shall conform to state department of transportation standard 1030-D or as specified herein. Pipe shall have at least 30 inches of cover before wheel loading and at least 48 inches of cover before using heavy-duty tamping equipment such as a hydrohammer. Installation for smooth lined HDPE shall conform to ASTM D2321, DOT spec 1030P revised 10-21-1998 as well as manufacturers' recommendations.
(1) Concrete pipe. The pipe shall be placed in a prepared trench with the socket end pointing upstream. The pipe may be joined by mortar joints, bituminous plastic cement joints, rubber-type gasket joints, or O-ring gasket joints. In mortar and bituminous plastic cement joints the open space shall be filled with the joint material, and the inside of each joint wiped smooth. Mortar joints shall be made in the same manner except that the open space shall be thoroughly wetted before filling with joint material. After the initial set, the mortar on the outside shall be protected from the air and sun with thoroughly wet earth or burlap cover. Rubber-type and O-ring gasket joints shall be installed according to manufacturer's recommendations.
(2) Corrugated metal pipe. Pipe sections shall be laid in a prepared trench with outside laps of circumferential joints pointing upstream and with longitudinal joints at the sides.
Coupling bands, fastened by two or more bolts, shall join the sections. The space between adjoining sections shall be not more than two inches. All damaged spots in the coating that expose base metal shall be recoated with asphalt before the trench is backfilled.
(h) Stormwater management facilities.
(1) The developers shall choose at their discretion the applicable facility to balance preand post-development runoff. Once established, the facility should not be of the nature to demand routine maintenance. Acceptable approaches include permanent detention ponds, ponds with available storage for storm surge, and manmade wetlands. Ponds with storage for storm surge shall be equipped with a concrete spillway. Other alternatives may be discussed, yet permanent detention ponds are favored. Only stormwater management facilities located in a residential subdivision will be considered to be deeded to the city.
(2) Permanent detention pond design shall conform to the guidelines of the latest edition of the Manual for Erosion and Sediment Control in Georgia. The ponds shall be completely enclosed by a fence with 12-foot double leaf gate. The fence shall be a minimum of seven feet in height, and consisting of two-inch mesh × nine-gauge × 72-inch aluminum coated steel fabric; conforming to the latest revision of ASTM A 491, a seven-gauge aluminum coated steel barbed wire with four-point aluminum barbs spaces five inches apart mounted on barbed wire support arms along the top of the fence fabric; galvanized line posts, 2.5 inches O.D. (3.65 pounds per foot); galvanized corner posts, three inches O.D. (5.79 pounds per foot); galvanized gate posts, four inches O.D. (9.11 pounds per foot); galvanized top rails, 15
/8 inches O.D. (2.27 pounds per foot) with extra-long pressed steel sleeves. Corner and gate posts shall have necessary struts and tie bracing. Gates shall be equipped with heavy-duty latches, keepers and heavy-duty hardened bronze padlocks with duplicate master keys. Posts shall be set at not more than ten-foot centers, a full three feet deep in concrete poured to the full size of the excavated postholes. After setting the post, the postholes shall be filled with grout to an elevation of two inches above the finished ground. Gate frames shall be galvanized, two O.D. (2.75 pounds per foot) with welded corners and necessary braces and trusses.
(3) "No Trespassing, City of Bremen Stormwater Detention Pond" signs shall be placed at the entrance gate and along the outside of the fence every 50 feet. The detention pond shall be accessed by a 12-foot gravel drive. The developer shall submit a landscaping plan, which will be part of the mandated buffer zone, incorporating evergreens to screen the facility from adjacent property. As part of the landscaping plan, water absorbing vegetation may be shown within the dike to further enhance the water uptake and aesthetics.