108.02.04. Concept plans (preliminary plan approval).
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A. Purpose. The purpose of reviewing concept plans is to ensure compliance with the basic design concepts and improvement requirements of subdivisions and land developments prior to investing in preparing civil/site documents and to reduce the overall number of document revisions prior to approval.
B. Concept plans are recommended to be reviewed by the development review team (DRT) prior to submitting civil/site documents for any development that includes one or more of the following elements:
1) Dedication of a public street.
2) Installation of public infrastructure.
3) Subdivision constituting a larger common plan of development, including mixed use districts as defined in chapter 102 of this UDC.
4) Installation of a stormwater management facility.
5) Complex commercial projects.
C. Process. The following steps outline the required concept plan submittal, review and approval process:
1) Request preliminary review.
a. Applicant requests preliminary review and schedules a meeting with the DRT through the engineering department.
b. The DRT shall include representatives from city departments or divisions, including but not limited to engineering, planning and zoning, building, fire, police, stormwater management, as well as the Georgia Soil and Water Conservation Commission (GSWCC).
2) Plan submittal. Fourteen days prior to the preliminary review meeting, the applicant shall submit the following to the engineering department in order for the city to accept the plan:
a. Completed application form. Application forms are available at the engineering department and on the official City of Canton, Georgia website.
b. Concept plans at a scale of one inch equals 100 feet minimum, including:
i. A digital version of the concept plan.
ii. Eight paper copies of the concept plan, sized 24 inches by 36 inches or 30 inches by 42 inches.
c. Plan review fee payment based on type of plan.
d. All plans submitted must be complete. Failure to submit complete plans shall result in a delay of the reviewing process.
3) Plan specifications. Concept plans shall, at a minimum, include the following components, which are more fully described in section 108.03.00:
a. Basic information and location map.
b. Property boundaries and easements.
c. Zoning and land use.
d. Water resources, stream buffers and floodplain.
e. Topography.
f. Road/streets, ROW and utilities.
g. Buildings and structures.
h. Open space and amenity areas.
i. Off-street parking and loading.
j. Stormwater management. see also the stormwater system standards and requirements section in chapter 109, Design Standards: Streets and Stormwater Systems for stormwater concept plan and consultation meeting requirements.
4) Preliminary review meeting. The applicant shall attend the meeting and receive comments from the plan approval team to assist with the preparation of civil/site documents. Review criteria include the following:
a. Compliance with this UDC, including but not limited to densities, height restriction, lot size, setbacks, buffers, roadway access, overlay districts, uses, streets, open space requirements.
b. Compliance with all conditions of zoning, terms and conditions of development agreements, all conditions of variances or appeals.
c. Compliance with relevant provisions of the City of Canton Code of Ordinances.
d. Provisions made for water supply and sewage disposal that will meet federal, state and local regulations.
e. Whether proposed roads provide safe, convenient, and functional system for vehicular, pedestrian, and bicycle circulation and are otherwise consistent with the City of Canton Comprehensive Plan and the City of Canton Major Thoroughfare Plan.
f. Proposed development makes accommodations for areas unsuitable for development due to the likelihood of flooding or improper drainage, or due to rock formations, topography, utility easements or other characteristics that would render development of these areas harmful to the safety, health and general welfare of the general public and the citizens of the City of Canton.
D. Resubmittal. Concept plans and related comments will be kept on file for one year. After one year, applicants shall resubmit a concept plan prior to submitting construction documents.
History
(Ord. No. 2014-18, § 2, 8-21-2014)