108.02.05. Civil/site documents.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Purpose. Civil/site documents are intended to document the detailed design and construction required for an individual building or subdivision.

B. Process. The remaining section outlines the submittal, review and approval process. The steps, as outlined in subsections C through I, are required to be followed in the order and manner described.

C. Plan submittal. Applicant shall submit a completed application package to the engineering department.

A code number will be assigned to assist in tracking plans during process. All plans submitted must be complete.

Failure to submit complete plans shall result in a delay of the reviewing process. The application package shall include:

1) Completed application form. Application forms are available at the engineering department and on the official City of Canton, Georgia website.

2) Civil/site documents. Final plats at a scale of one inch equals 100 feet minimum shall be submitted to the engineering department.

a. A digital version of the documents is required.

b. Eight complete sets (paper copies), sized 24 inches by 36 inches or 30 inches by 42 inches, are required. No other sizes will be accepted.

3) Plan review fee payment based on the current review fee schedule depending on the type of proposed development.

4) The centerline of the development entrance shall be located by nail and cap at the centerline or edge of pavement of the roadway that the development will access. Said nail and cap location shall be indicated on the submitted construction plans along with the date that the nail and cap were placed.

5) A copy of the NPDES notice of intent (NOI) ensuring compliance with that state permit and a copy of either the certification indicating the developers' completion of a NPDES class thereby permitting him/her to monitor his/her own site or a copy of a contract from a professional engineer currently registered on the State of Georgia stating that he/she been hired to monitor the development.

6) A copy of a certificate indicating the completion of one of the following:

a. The University of Georgia Erosion Control Course.

b. NPDES certification.

c. The Georgia Department of Transportation Work Site Erosion Control Supervisor Course.

7) A letter of approval from the Cherokee County Environmental Health Department must be submitted with the construction plans to address developments containing septic tank systems. On-site waste water systems shall not be approved where sewer is considered available to a project.

8) A copy of the developer's contract or a letter of commitment from a professional geo-technical engineer currently registered in the State of Georgia.

9) If a clearing and grubbing only permit is being requested, the applicant shall submit the erosion and sedimentation control plan as well as the tree save plan.

10) The applicant is responsible for submitting all structural drawings and/or architectural building plans to the building department prior to any building permits being issued.

D. Plan specifications. Civil/site documents shall, at a minimum, include the following components, which are more fully described in section 108.03.00:

1) Basic information and location map.

2) Property boundaries and easements.

3) Zoning and land use.

4) Water resources, stream buffers and floodplain.

5) Topography.

6) Road/streets, ROW and utilities.

7) Stormwater management plan.

8) Buildings and structures.

9) Open space and amenity areas.

10) Off-street parking and loading.

11) Erosion, sedimentation and pollution control plan.

12) Landscape and tree preservation plan.

E. Completeness check. After the engineering department reviews the application package for completeness, the applicant will be contacted to schedule a technical review meeting.

F. Plan routing and initial review.

1) The city engineer enters the application into the tracking system, which assigns a code number to assist in tracking plans during the approval process.

2) Development review members are notified that civil/site documents are distributed for review, the date of the technical review meeting and deadline for their comments. The City of Canton requires a minimum two-week review period.

3) The DRT shall include representatives from the following departments and agencies based on the scope of the proposal:

a. Stormwater management.

b. Canton Planning and Zoning Division.

c. Canton Building Division.

d. Canton Engineering Department.

e. Canton Utilities Department.

f. Fire safety services manager.

g. Canton Oversight Committee.

h. USDA Natural Resource Conservation Services (GASWCC).

4) Plan approval team members enter their review comments into the tracking system.

5) Applicant may review comments from the online "track it" system as they are completed by individual team members. Applicant may note any comments that require clarification or further explanation.

G. DRT meeting.Applicant shall attend the technical review meeting with the DRT to discuss and clarify comments prior to revising the civil/site documents.

H. Plan revisions after technical review.

1) Applicant shall submit revised civil/site documents to the engineering department.

2) City staff logs in revisions and notifies DRT that they are available for review.

3) DRT reviews revisions.

a. If the revisions completely address comments, team members approve application.

b. If comments are not addressed, applicant will receive comments through the online "track it" system. The applicant may contact individual departments for clarification.

Any changes to the plans must be resubmitted to the engineering department for re-re-routing to the DRT.

c. Team members indicate their approval in the tracking system.

I. Plan approval.

1) When revisions completely address comments, the applicant will be notified by the engineering department that all departments and agencies have approved the construction plans and final copies must be submitted for stamping.

2) The applicant shall submit final copies. Final copies are stamped for LDP issuance. The approved set of plans does not constitute a land disturbance permit.

3) The city engineer shall provide the applicant with an approval letter containing information about the LDP process and fees (see section 108.04.01).

4) If land disturbance permit is not obtained within 6 months of plan approval, plan will be withdrawn. The city engineer can approve one six-month extension if requested prior to original expiration date.

History

The history line the source prints at the end of the section.

(Ord. No. 2014-18, § 2, 8-21-2014; Ord. No. 2022-0317-01, 3-17-2022)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:canton/zoning/108.02.05@2026-11-11-e3320630f8

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Canton Zoning Ordinance, 108.02.05. Civil/site documents | Georgia Commons