110.02.04. Construction methods.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Excavation general.

1) It is the responsibility of the general contractor, any subcontractor, their employees, and inspectors of job sites to observe all safety regulations. Deficiencies in safety measures noted should be immediately reported to the contractor's superintendent, so that immediate corrective measures can be taken by the contractor. It is, however, the contractor's responsibility to conform to all safety regulations and practices as pertain to his construction site. The contractor shall contact the U.S. Department of Labor, Occupational Safety and Health Administration (OSHA), Region IV, Atlanta, Georgia for any assistance needed to complying with the appropriate regulations.

2) All unsuitable excavated material must be properly disposed of in a manner acceptable to the city and in a manner that will not adversely affect the environment. It shall be expressly understood that these standards are for the installation of all underground water mains and appurtenances. All work shall conform to the applicable provisions of the AWWA Specifications except as otherwise specified herein.

B. Erosion and sedimentation control.

1) All erosion and sedimentation control methods shall be in compliance with the local, state, and federal regulations, the Manual for Erosion Control in Georgia and the EPD requirements regarding the NPDES storm water monitoring permits (see the soil erosion, sedimentation and pollution control section of chapter 107 of this UDC).

2) The contractor shall designate one individual to be responsible for the implementation and maintenance of erosion and sedimentation controls on a 24-hour, everyday basis. The contractor shall furnish the city the individual's name, address, and 24-hour telephone number. This information shall be updated as is necessary.

C. Clearing and grubbing.

1) Areas for water system construction shall be cleared and grubbed.

2) All trees, shrubs, stumps, brush, paving and other waste material must be removed from the site. No trees or stumps shall be pushed beyond the right-of-way or buried nor shall any timber beyond the right-of-way damaged.

3) On water line extensions to the development, the road right-of-way shall be cleared to the width necessary for trenching and pipe laying operations. All stumps and roots within the trench dimensions shall be grubbed to such depths and widths as will enable the trenching to be done.

4) The contractor shall remove only such trees on or along the work as the city engineer and community development director permits, and shall carefully protect all other trees adjacent to the work. The contractor shall not permit excavating machinery or trucks to scrape the bark or tear the limbs from the trees, nor connect ropes or guy cables to them.

D. Trench excavation.

1) It is the responsibility of those installing water mains and related appurtenances to conform to OSHA regulations during trench excavation. OSHA publications are available to assist the contractor in having a safe construction site). Publications from OSHA can be obtained by contacting OSHA Publications Distribution, Washington, D.C. The city assumes no liability or responsibility for unsafe trench conditions.

2) Trenches shall have a minimum width of 12 inches plus the diameter of the outside of the bell of the water main and the depth thereof shall be such that the water mains shall be installed so that the top of the pipe is a minimum of four feet below final grade, four feet below the edge of the pavement, or four feet below the ditch paralleling the road, whichever is deepest. Permission must be granted by the city to vary from this requirement. Maximum trench width at the top of the pipe shall not be more than the outside diameter of the bell plus two feet. The sides of the trench above the pipe shall be sloped or benched as necessary to maintain stability. Minimum pipe cover shall be as shown on the approved plans.

3) Pipe trenches shall be straight and true to grade and in the location shown on the plans. Trenches shall be dug so that the pipe can be laid to the alignment and depth required, and the trench shall be of such width and shall be braced and drained so that the workmen may work therein safely and efficiently.

Chocking under the pipe will not be permitted. All joints shall be as specified herein. Excavation must be made under the bell of each pipe so that the entire length of the pipe will lie uniformly on the bottom of the trench and the pipe weight shall not rest on the bells.

4) Trenches shall be free of water during the work. Whenever water is present in the trench, it shall be removed in a manner satisfactory to the city and enough backfill shall be placed on the pipe to prevent floating. Any pipe that has floated shall be removed from the trench and re-laid later during dry conditions. Pipe shall not be laid in wet trench conditions that preclude proper bedding, or on frozen trench bottom, or when, in the opinion of the city, the trench conditions or the weather are unsuitable for proper installation.

a. The contractor shall do all necessary pumping or bailing, build all drains and do all other work necessary at his own expense to keep the trenches clear of water during the progress of the work.

b. Structures will not be built or pipe will not be laid in water, and water shall not be allowed to flow over or rise upon any concrete, masonry or pipe until the same has been inspected and the concrete or joint material has thoroughly set.

c. All water pumped, bailed or otherwise removed from the trench or other excavation shall be conveyed in a proper manner to a suitable place of discharge where it will not cause injury to the public health or to public or private property or to work completed or in progress, or to the surface of the streets or cause any interference with the use of same by the public.

5) All changes in grade shall be made gradually. At points of interference with storm sewers and cross drains on DOT right-of-way, the pipe will be run under the conflicting utility unless the water main can be installed above the storm sewer while maintaining both the required one foot separation and the required cover specified in section 109.05.04.D.2 above. Where the water main crosses beneath a storm sewer, there shall be a minimum of 12-inch clearance between the main and the storm sewer.

6) In laying pipe across water courses, the top of the water main or casing shall be a minimum of four feet below the creek or river bed. Four feet of cover shall be maintained over water mains crossing ditches or depressions of any kind. Railroad crossings shall be installed according to American Railway Engineering Association requirements.

7) Where necessary, the line shall be lowered at valves so that the top of the valve stem is approximately three feet below the finished grade. The trench shall be deepened to provide a gradual approach to all low points of the line.

8) Excavation will not be made under highways, streets, alleys or private property until satisfactory arrangements have been made with the city, county, state or owners of the property to be crossed.

a. All excavated material shall be placed so as to not interfere with public travel on the streets and highways along which the lines are laid.

b. All work shall be performed to cause the least possible inconvenience to the public.

c. Adequate temporary bridges or crossings shall be constructed and maintained where required to permit uninterrupted vehicular and pedestrian traffic.

d. No more than 100 feet of trench shall be opened on any line in advance of pipe laying. The city engineer shall have the right to limit the amount of trench open at any one time to less than 100 feet if he believes the reduced limits are necessary.

9) All excavations shall be adequately guarded with barricades and lights in compliance with all OSHA, City of Canton, and Georgia Department of Transportation requirements so as to protect the public and workers from hazard.

10) When possible, all crossings of paved highways or driveways shall be made by boring or jacking the pipe under the pavement and shall be done in such manner as not to damage the pavement or sub-grade, unless the casing or pipe is in solid rock, in which case the crossing shall be made by the open cut method, wet bore or by tunneling.

a. Wherever streets, roads, or driveways are cut, they shall be immediately backfilled and compacted after the pipe is laid and shall be maintained in first-class condition as passable at all times until repaved. Backfilling, compaction, dressing and clean-up shall be kept as close to the line laying crew as is practical, and negligence in this feature of the work will not be tolerated.

b. Streets, sidewalks, parkways, and other public and private property disturbed in the course of the work shall be restored to as near as original condition as possible or better in a manner satisfactory to the city.

11) In excavation and backfilling and laying pipe, care must be taken not to remove or injure any water, sewer, gas or other pipes, conduits or other structures without an order from the designer. When an obstruction is encountered, the contractor shall notify the designer who will have the owners of the obstruction adjust same or make necessary changes in grade and/or alignment to avoid such obstruction. Any house connection, drains or other structures damaged by the contractor shall be repaired immediately.

12) All excavation shall be placed on one side of the trench, unless permission is given by the city to place it on both sides. Excavation materials shall be so placed as not to endanger the work and so that free access may be had at all times to all parts of the trench and to all fire hydrants or water valve boxes, etc.

13) Excavations adjacent to existing or proposed buildings and structures, or in paved streets or alleys shall be adequately protected by the use of trench boxes, sheathing, shoring and bracing to support the sides of the excavation and to prevent cave-ins of the excavation, or the undermining or subsequent settlement of adjacent structures or pavements. Underpinning of adjacent structures shall be done when necessary to maintain structures in safe condition.

14) Construction occurring around active sewer systems shall be done in such a way so as to prevent the passage of wastewater onto the ground. Absolutely no wastewater shall be allowed to spill onto the ground.

E. Rock excavation.

1) Wherever rock is encountered in the excavation, it shall be removed by suitable means. Drilling and blasting operations shall be conducted with due regard for the safety of persons and property in the vicinity and in strict conformity with requirements of all ordinances, laws and regulations relative to the handling, storing and use of explosives.

2) The developer is fully responsible for filing for and acquiring any blasting permits which may be required by those agencies with such jurisdiction. Before blasting, the contractor shall cover the excavation with heavy timbers and mats in such a manner as to prevent damage to persons or the adjacent property.

Rock excavation near existing pipelines or other structures shall be conducted with the utmost care to avoid damage. The contractor shall be wholly responsible for any damage resulting from blasting, and any injury or damage to structures or property shall be promptly repaired by the contractor to the satisfaction of the city and property owner.

3) Rock in trenches shall be excavated over the horizontal limits of excavation and to depths as follows in table 110-3:

Table 110-3 Rock Excavation Requirements Size of Pipeline (inches) Depth of Excavation Below Pipe (inches) 4" and less 4" 4" to 6" 6" 8" to 18" 8" 18" to 30" 10" Over 30" 12"

4) The space below grade for pipe lines shall then be backfilled with subgrade stabilizer or other approved bedding material and compacted.

5) In rock excavation, the backfill from the bottom of the trench to one foot above the top of the pipe shall be finely pulverized soil, free from rocks and stones. The rest of the backfill shall not contain over 50 percent broken stone, and the maximum sized stone placed in the trench shall not exceed two inches in diameter. Excess rock and fragments of rock larger than two inches in diameter shall be loaded and hauled to disposal. If it is necessary, in order to comply with these specifications, selected backfill shall be borrowed and hauled to the trenches in rock excavation. Sides of the trench shall be trimmed of projecting rock that will interfere with backfilling operations. Rock excavation by blasting shall be at least 75 feet in advance of pipe laying.

F. Subgrade and bedding.

1) The bottom of the trench shall be accurately cut to grade so that the pipe will have a longitudinal bearing on undisturbed soil for the full length of the pipe, except for such distances that are necessary for bell holes.

2) If the soil at the bottom of the trench is in such condition that it cannot be properly shaped or graded, due to the hardness of the soil and in all cases where rock or shale is encountered at sub-grade, the trench shall be refilled with suitable backfill material to the required sub-grade elevation, thoroughly tamped with mechanical tampers and shaped to fit the outside of the pipe as specified in the preceding paragraph. Wherever water is encountered in conjunction with the additional sub-grade excavation, the backfill shall consist of sub-grade stabilizer stone.

3) In the event that a trench is excavated below grade, the contractor shall refill the trench to the proper grade with suitable, thoroughly compacted material.

a. Allowable soils shall be dry course-grained soils ranging from well-graded gravel-sand mixtures with little or no fines to clayey sands and sand-clay mixtures with appreciable amounts of fines.

b. All soil materials shall have 100 percent passing a one and one-half-inch sieve and a maximum of 55 percent passing a no. 200 sieve. The maximum volume change allowable shall be 15 percent.

c. Allowable soils shall be class I and class II as defined in section 810 of the Georgia Department of Transportation Specifications for the Construction of Roads and Bridges.

4) All gravel or crushed stone used for class "C" bedding shall have a gradation equal to or smaller than #57 stone in order to limit the void area, and all the material must pass a one and one-half-inch sieve.

Where sand or other acceptable soil is used, it shall be spread over the trench bottom, compacted to at least 90 percent maximum density and shaped before placing the pipe; after the pipe is placed, additional material shall be compacted under the haunches and for the full trench width as described above.

G. Installation of water main.

1) Pipe and accessories shall at all times be handled with care to avoid damage. Proper and suitable tools and equipment for the safe and convenient handling and laying of pipe shall be used. Whether moved by hand, skidways or hoists, material shall not be dropped or bumped. Great care shall be taken to prevent the pipe from being damaged, particularly the cement lining on the interior of ductile iron pipe.

Each joint of pipe shall be unloaded opposite or near the place where it is to be laid in the trench.All pipe shall be carefully examined for cracks and other defects. All such material that is defective in manufacture, has been damaged in transit, after delivery or in installation, shall be removed from the job site and replaced with new material.

2) All pipe shall be laid straight, true to line and grade. Bell and coupling holes shall be dug in the trench and the pipe shall have a continuous bearing with the trench bottom between bell or coupling holes. No shimming or blocking up of the pipe shall be allowed. When the work is not going on, all pipe openings shall be securely closed by the insertion of the proper size plug and caulking so that dirt and debris will not be washed into the pipe in case of rain. The inside of the pipe shall be clean and free of trash and dirt, and if necessary a swab or brush shall be used to clean the pipe before lowering it into the trench.

All pipe and fittings shall be kept clean until completion of the work.

3) Water mains shall be joined by "push-on" joints using elastomeric gaskets to affect the pressure seal.

The spigot end of the pipe and the inside of the bell shall be thoroughly cleaned and the gasket inspected to see that it is properly placed. Lubricant shall be applied to the spigot end of the pipe and it shall be inserted into the bell of the adjoining pipe to the stop mark on the pipe, and the assembly shall be made as recommended by the pipe manufacturer. Lubricant used must be non-toxic and supplied or approved for use by the pipe manufacturer.

4) Restrained joints shall be provided where specified on the approved plans and shall be of the type specified in section 110.02.03.B above. Assembly shall be in accordance with the manufacturer's recommendations. While the typical bedding required for water mains is type 3, all restrained pipe and bends shall have type 4 bedding.

5) Water shall not be allowed to run or stand in the trench before the trench has been backfilled. The contractor at no time shall open up more trench than his available pumping facilities are able to dewater.

6) Where allowed by the city, PVC water mains shall be installed in accordance with the requirements of ASTM D 2774, latest revision. Where PVC pipe is installed, electric conductive wire shall be placed in the trench one foot above the pipe.

7) Ductile iron water mains shall be wrapped in black polyethylene tubing where required by the city.

Polyethylene tubing shall be installed in accordance with AWWA C105, Method A, latest revision.

8) At changes in direction of the main and at other points shown on the plans or directed by the city, the line shall be adequately blocked with concrete or restrained in some other manner approved by the city.

The city engineer shall be notified by the contractor before blocking is placed. Prior to blocking any joint or fitting with concrete, that joint or fitting shall be wrapped with polyethylene film in such a manner that the concrete will not stick directly to the pipe but that the load bearing capacity of the blocking will not be affected.

9) For water mains, the contractor shall place a vertical piece of two-inch diameter PVC pipe on top of the pipe at all bends, fittings, valves, elevation transitions and every 50 feet along the length of the water main for the purpose of enabling the surveyor to determine the water main elevation for "as-builts." The contractor will then be responsible for removing the vertical PVC sections after the as-built locations have been verified by the city. The PVC shall be capped by approved method to prevent trash from entering the PVC prior to the depth being measured.

H. Backfilling trenches.

1) Backfill material shall consist of fine, loose earth containing sufficient but not excessive moisture content for thorough compaction.

a. Material that is too dry for adequate compaction shall receive a prior admix of sufficient water to secure adequate moisture content.

b. Material having excessive water content shall not be placed at any time.

c. Backfill material shall be free of large clods, stones, vegetable matter, debris, and other objectionable material.

d. All unsuitable excavated material and excess material must be properly disposed of in a manner that will not adversely affect the environment.

e. After the pipe has been laid, backfilling shall be done in two distinct operations.

i. In general, all backfill beneath, around and to a depth of 12 inches above the top of the pipe shall be placed by hand in four-inch layers for the full width of the trench and thoroughly compacted by hand with vibratory equipment.

ii. The remainder of the backfill shall be placed in six-inch layers and compacted to the top of the trench, either by pneumatic hand tamps, hydro-tamps, or other approved methods.

iii. Care shall be taken so that the pipe is not laterally displaced during backfilling operations.

iv. The backfill lifts shall be placed by an approved method in accordance with that hereinafter specified.

v. Backfill materials shall be the excavated materials without bricks, stone, or corrosive materials.

2) Backfill under permanent concrete or bituminous pavement or floors and as elsewhere specified or indicated on the plans shall be approved bank-run sand or compacted graded aggregate free from large stones and containing not more than ten percent by weight of loam or clay. This backfill shall be compacted to 95 percent as determined by the standard proctor test from pipe bedding to one foot above the pipe, and the remainder of the trench up to the concrete trench cap shall be compacted to 100 percent as determined by the standard proctor test. Mechanical vibrating equipment shall be used to achieve the required compaction.

3) Backfill under gravel or crushed stone surfaced roadways and surface treated type bituminous roadways shall be the approved suitable excavated material placed as described above for the full depth and width of the trench. Backfill shall be free from large stones and contain no more than ten percent by weight of loam or clay. This backfill shall be compacted to 95 percent as determined by the standard proctor test from pipe bedding to one foot above the pipe, and the remainder of the trench shall be compacted to 100 percent as determined by the standard proctor test. Mechanical vibrating equipment shall be used to achieve the required compaction.

4) Backfill in unpaved areas shall be compacted with mechanical vibrating equipment to 98 percent as determined by the standard proctor test. Backfill material from pipe bedding to ground surface by shall be excavated earth free from large stones and other debris.

5) Where sheeting is used in connection with the work, it shall not be withdrawn before the trench is sufficiently filled to prevent damage to banks, road surfaces, adjacent pipes, adjacent structures or property. When the removal of sheeting endangers adjoining improvements, it will be left in place.

6) All costs of compaction testing shall be the responsibility of the developer.

I. Thrust restraint for pressure lines.

1) Reaction blocking.

a. Underground piping installed around curves and at all unsupported changes of direction, all tees, wyes, crosses, plugs and other like fittings shall be solidly and properly blocked with high early strength concrete against solid earth to take the reaction of the main pressure and to prevent lateral movement of the pipe or fittings when under pressure.

i. Concrete for reaction blocking shall be class A concrete and shall have a minimum compressive strength of 3,000 psi at 28 days.

ii. The contractor shall allow the concrete to set up for a minimum of four hours before backfilling. The blocking, unless otherwise shown, shall be so placed that the pipe and fitting joints will be accessible for repair.

b. Reaction blocking shall be constructed in conformance with the standard detail drawings in chapter 112 of this UDC. Prior to blocking any joint or fitting with concrete, that joint or fitting shall be wrapped with polyethylene film is such a manner that the concrete will not stick directly to the fitting, but that the load bearing capacity of the blocking will not be affected.

c. The sizing of the thrust block bearing area given in the detailed drawings is based on a soil strength of 2,000 PSF and a water pressure of 250 PSI. The design professional preparing the water main design shall verify the soil conditions before the thrust block design is implemented.

2) Retainer glands. Mechanical joint fittings and valves on ductile iron pipe shall be installed with retainer glands where specified herein.

3) Rodding/straps.

a. Where blocking cannot be poured against undisturbed earth, the contractor shall pour concrete deadmen with threaded rods and/or metal straps coming out of the deadmen and connecting to the valve/fitting for restraint.

b. The rods and metal straps shall be coated with an approved bitumastic coating prior to backfilling.

c. Vertical bends shall be restrained with threaded rods and concrete deadmen as shown in the standard detail drawings in chapter 112 of this UDC.

4) Restrained joints.

a. Where approved by the city, another option to using concrete blocking in restricted areas is the use of restrained joints.

b. Restrained joints shall be provided where specified on the approved plans and shall be of the type specified in section 110.02.03.B above.

c. Assembly shall be in accordance with the manufacturer's recommendations.

d. While the typical bedding required for water mains is type 3, all restrained pipe and bends shall have type 4 bedding.

J. Setting fire hydrants.

1) Fire hydrants shall be placed at the locations shown on the plans.

a. Gate valves for fire hydrants shall be connected directly to the main by means of a "locked hydrant tee." All other connections between the main and the fire hydrant shall be mechanical joint with ductile iron retainer glands.

b. Fittings shall be restrained by a "locked hydrant adapter" whenever the fire hydrant is located close enough to the main to allow its use.

c. Not less than four cubic feet of No. 5 or No. 57 stone shall be placed around the base of the hydrants, as shown in the standard detail drawings in chapter 112.

d. Before placing the hydrants, care shall be taken to see that all foreign material is removed from within the body.

e. The stuffing boxes shall be tightened and the hydrant valve opened and closed to see that all parts are in first class working condition.

f. All hydrant openings shall be kept capped, except when hydrant is being worked on.

2) When a fire hydrant has been constructed but is not yet in service, the contractor shall provide and attach to the fire hydrant a flag or collar indicating that the fire hydrant is not in service. Said flags or collars shall remain on the fire hydrant until it is put into service. Whenever an existing fire hydrant is taken out of service, whether temporarily or permanently, it shall be equipped with a flag or collar indicating that it is not in service. The contractor shall provide and install flags or collars as required and shall notify the fire department whenever the operating status of any fire hydrant changes.

3) Fire hydrants shall only be operated with a specifically designed fire hydrant wrench. If the contractor observes any other contractor or person operating a fire hydrant with an unapproved fire hydrant wrench, he shall report that fact to the city immediately.

4) It is the contractor's responsibility to insure that all new facilities are maintained in new condition until final completion of the project and acceptance by the city. Fire hydrants with damaged operating nuts shall not be accepted.

K. Setting valves and fittings.

1) Valves and fittings shall be placed where shown on the plans.

a. Valves shall be set plumb, and shall have cast iron valve boxes.

b. The valve boxes shall be placed directly over the valve and set plumb, the top of the box being brought to the surface of the ground.

c. After the boxes are in place, earth shall be filled in the trench and thoroughly tamped around the box.

d. After all settlement has taken place, a concrete collar shall be constructed for each valve box.

2) Fittings shall be properly braced to insure that they will not be blown off or broken loose under the greatest possible working pressure.

a. All fittings shall be mechanical joint unless specified otherwise.

b. In situations where there is insufficient undisturbed earth to act as a bearing surface or where otherwise directed by the city, fittings shall be restrained by the use of threaded rods or other method acceptable to the city.

c. Line valves shall be supported and restrained by concrete blocking and threaded rods as shown in the detailed drawings.

3) Valve stem extensions shall be installed where the valve operating nut is more than three feet below the finished grade. The valve stem extension shall be of sufficient length to place its operating nut at a depth between two and three feet below finished grade.

L. Marking location of valves and the end of the main.

1) Each main line water valve shall be marked by cutting a letter "V" in the curb. The "V" shall be turned to point toward the valve. The letter height shall be six inches.

2) Concrete valve markers shall be set for main line water valves with an even number of feet between the center line of the valve and the center line of the aluminum disc in the top of the marker, and the distance in feet between the valve and marker shall be stamped in the marker at the time of setting.

3) A concrete valve marker shall be placed directly over the end of any water main stubbed out for future use or any dead end main. The letters "EOL" shall be cast into the top of the marker or stamped into the aluminum disc in the top of the marker.

M. Placing of steel casing pipe.

1) Casing pipe shall be installed at the locations required by the city. Unless directed otherwise, the installation procedure shall be the dry bore method. The hole is to be mechanically bored and cased through the soil by a cutting head on a continuous auger mounted inside the casing pipe. The installation of the casing and boring of the hole shall be done simultaneously by jacking. Lengths of casing are to be full circumference butt-welded to the preceding section installed. Excavation material will be removed and placed at the top of the working pit.

2) Jacks for forcing the casing pipe through the roadbed shall have a jacking head constructed in such a manner as to apply uniform pressure around the ring of the pipe. The casing to be jacked shall be set on guides, braced together, to properly support the section of the pipe and direct it to the proper line and grade. In general, roadbed material shall be excavated just ahead of the pipe, the excavated material removed through the pipe, and the pipe then forced through the roadbed into the excavated space.

3) Where pipe is required to be installed under railroads, highways, streets or other facilities by jacking or boring methods, construction shall be done in a manner that will not interfere with the operation of the facility, and shall not weaken the roadbed or structure.

4) The use of water or other fluids in connection with the boring operation will be permitted only to the extent necessary to lubricate cuttings. Jetting will not be permitted.

5) The diameter of the excavation shall conform to the outside diameter and circumference of the casing pipe as closely as practicable. Any voids which develop during the installation operation shall be pressure grouted.

6) The casing shall be jacked from the low or downstream end. At each end of the casing pipe the void between the carrier pipe and casing shall be sealed with brick and mortar. Any pipe damaged in jacking operations shall be removed, and replaced by the contractor at their expense.

7) After the steel casing pipe has been installed, the DIP carrier pipe shall be installed in the casing pipe.

Care shall be exercised at all times to protect the coating and lining of this pipe and to maintain tight, full-seated joints in the carrier pipe. Where the carrier pipe is 24 inches in diameter or less, joint gaskets shall be "Field-Lok" gaskets or approved equal inside of the casing.

N. Connection to the existing city water system.

1) All persons desiring a tap must make application at the city at least seven working days prior to the date the tap is to be made.

2) The contractor shall furnish the following information when making application:

a. Approved plan for the project.

b. Copy of street or highway permit if available.

c. Meter size or detector check applications if for apartments, shopping centers, or residential developments.

d. Billing address and purchase order if required.

e. Plan and profile of meter installation larger than two inches.

3) The city will schedule the tap to conform to their work schedule and notify the contractor so that he can complete his preparation.

4) The contractor shall furnish the following at site:

a. Tapping sleeve and valve installed on the line and ready for tapping.

b. Proper traffic control devices and person(s) to direct traffic if required.

c. Backhoe or lift capable of handling the tapping machine.

d. Minimum of three people to assist with the work.

5) The contractor will be billed for the tap plus an hourly rate for the city's operator, his helper, truck, and any other equipment used if made by city forces.

O. Water line tap made by private contractor on city line.

1) The city shall be notified one week prior to date tap is to be made.

2) City personnel shall supervise the tap and associated work by private contractor.

3) All taps shall be made on wet line.

4) All taps to be made with saddles or tapping sleeves.

P. Interruption of water supply during construction.

1) Interruptions of water service will not be allowed without the permission and supervision of city personnel.

2) Residents and building occupants shall be informed of the date, time of cutoff and the duration of stoppage. Failure to do so will make the contractor liable for any damages reported to the City of Canton Engineering Department.

a. Four days' notice shall be prepared and given to the affected customers and must be coordinated with the city.

b. When it is necessary to schedule a water outage for any construction, signs must be posted at least four days in advance to notify the public.

c. In some cases, the water outage may need to be scheduled for nights or weekends to lessen the inconvenience to businesses or schools.

d. See standard detail No. W724 "Water Line Maintenance Sign" in chapter 112 for sign requirements. These signs are to be provided and installed by the developer.

Q. Railroad crossings.

1) All railroad crossings shall conform to the requirements of the American Railway Engineering Association Manual for Railway Engineering.

2) The contractor shall secure permission from the railroads to schedule the work so as not to interfere with the operation of the railroads. The contractor shall be held responsible for any delays or damages occurring to the railroads.

3) The contractor will furnish the railroad with such additional insurance as may be required, cost of same to be borne by the contractor, together with the costs for flagmen, watchmen, temporary work of any nature, safety devices and any other items that may be imposed by the railroad.

R. Highway crossings.

1) The contractor shall be responsible for coordinating and scheduling all construction work in the Georgia State Highway right-of-way with the Georgia Department of Transportation.

2) Work along and across Georgia State Highway right-of-way shall conform to Georgia DOT Standard Specifications for Construction of Roads and Bridges. The developer is required to obtain all necessary permits.

3) Traffic control within the Georgia State Highway right-of-way shall comply with section 107.09 of the State of Georgia DOT Standard Construction Specifications, or Sections 104.05 and 107.07 of the U.S.

Manual on Uniform Traffic Control Devices for Streets and Highways, latest editions.

S. Stream crossings. Crossing streams shall be done in compliance with the federal, state and local laws and permit requirements. The methods described below are subject to change due to more recent regulations implemented by the varying government agencies. The developer is liable for knowing and complying with the most stringent regulations in force at the time of construction.

1) The suggested method of crossing a river, stream, creek, impoundments, or wet weather ditch is with a bore under the creek or river with a minimum of four feet of cover between the lowest point in the stream and the top of outside diameter of the casing. Casings and ductile iron pipe are required for all stream crossings and shall extend a minimum of 20 feet beyond the vegetative buffer (city or state buffer, whichever is wider) on each side. An open cut of the stream is allowable if no endangered species are affected and if the developer obtains permission from the various governing agencies. If the stream is open cut, concrete collars or encasement must be provided at all joints for ductile iron pipe with less than four feet of cover.

2) Design engineer is responsible for checking and designing against floatation.

3) The stream bed and sides at the crossing site shall be protected from erosion in accordance with the latest edition of the Manual for Erosion and Sediment Control in Georgia.

4) Where streams are allowed to be open cut, the construction in stream beds shall follow the following guidelines:

a. Construction in and around stream beds must adhere to the current regulations of the Georgia EPD, the Corps of Engineers, the City of Canton and the U.S. Department of Fish and Wildlife.

The design engineer and contractor are responsible for knowing and complying with these regulations. Any item published within these specifications that is in conflict with stream bed protection regulations is hereby deemed invalid, unless the specification herein is considered more stringent by the reviewing agency.

b. Fording of live streams with construction equipment will not be permitted, unless specifically approved in writing. Unless otherwise approved in writing, mechanized equipment shall not be operated in live streams except as may be required to construct temporary diversion structures, and temporary or permanent structures.

c. Erosion control measures shall be installed prior to performing any stream crossings. All work should be performed when stream flows are at their lowest, and all work should be performed as quickly and safely as possible. As soon as conditions permit, the stream bed shall be cleared of all falsework, debris, and other obstructions placed therein or caused by the construction operations.

d. Erosion control measures can include, but is not limited to, the following items:

i. Silt fencing, two rows of type C.

ii. Erosion control checkdams.

iii. Channel diversion through temporary storm drain pipe.

iv. Rock filter dams.

v. River stone in the creek bed.

vi. Geotextiles for stream bank restoration.

vii. Special vegetative installations.

e. The construction and installation of the various structures listed above are detailed in the Manual for Erosion and Sedimentation Control in Georgia or the Georgia Department of Transportation Standards and Construction Details, both of which are available for purchase by the contractor.All measures must be approved by the NRCS and the EPD.

T. Replacement of pavement.

1) General.

a. Contractor shall fully restore and replace all pavement, curbs, gutters, sidewalks and other surface structures removed or disturbed, to a condition that is equal to or better than the original condition in a manner satisfactory to the city.

b. Contractors which are utilizing the roadway shoulders for construction are required to stabilize the earth shoulders every three days as a maximum time period. They are required to stabilize the shoulder before leaving the work area on any particular day if rain is forecast within the next 24 hours.

2) Pavement cuts.

a. All paved roads will be bored and cased. A bore must be attempted before consideration will be given to cutting the street.

b. Existing roadways shall not be open cut unless permission is granted by the City of Canton Engineering Department, Cherokee County Engineering Department, or Georgia DOT Submittal of an authorization letter from the City of Canton Engineering Department, Cherokee County Engineering Department, or Georgia D.O.T is required.

c. One lane of traffic shall be maintained open at all times. Construction work shall be limited to time between 9:00 a.m. and 4:00 p.m.

d. The contractor shall furnish traffic control devices and certified personnel to direct traffic, if required.

e. The above requirements may be altered with the written approval of the City of Canton Engineering Department in extenuating circumstances.

f. Assuming that a road bore has been attempted and failed, or that the developer has received permission to open cut a road, pavement replacement shall meet the current specifications as required by the City of Canton, Cherokee County or Georgia DOT.

g. The contractor shall adhere to the Georgia DOT Specifications for the Installation of Safety Barricades, section 107.09 during construction in the roadway or shoulder.

h. Where possible, all pipe under existing paved driveways will be either free bored or installed in casing.

U. Location and protection of existing underground utilities.

1) It is the responsibility of the contractor to locate and protect all underground utilities and structures. No utility or structure is to be moved or disturbed without the approval of the utility company or the owner of the structure. Any damage caused by waterline installation to any utility or structure shall be immediately reported to the city engineer and repaired at the contractor's expense.

V. Clean-up.

1) The contractor shall remove all unused material, excess rock and earth, and all other debris from the construction site as closely behind the work as practical. If the contractor fails to maintain clean-up responsibilities as directed by the city's representative, the city may choose to use their own forces to do so, followed by an invoice to the developer for the city's work.

2) All trenches shall be backfilled and tamped before the end of each work day.

3) Prior to requesting the "completion of water main construction" inspection, the contractor shall do the following:

a. Remove and dispose of in an acceptable manner all shipping timbers, shipping bands, spacers, excess materials, broken material, crates, boxes and any other material brought to the job site.

b. Repair or replace any work, trees, lawns, shrubs, fences, flower beds, drainage culverts or other property damaged during the water line construction. All items damaged beyond repair shall be replaced with "in-kind" or better material that existed prior to construction.

c. Insure that all valves have been located and are fully open. Adjust all valve boxes to grade and pour concrete collars around all valve boxes outside paved areas.

d. Insure that fire hydrants are set to grade and that connections are open.

e. All easement areas shall be cleared of trees, stumps and other debris and left in a condition such that the easement can be maintained.

f. All shoulders, ditches, culverts, and other areas impacted by the water main construction shall be at the proper grades and smooth in appearance.

W. Grassing.

1) A uniform stand of grass or mulch for erosion protection is required over all road shoulders and water main easements prior to the city's acceptance of the water main. Grass shall be as defined and planted in conformity with the temporary and permanent disturbed area stabilization of the Manual for Erosion and Sediment Control in Georgia, most current edition.

2) Grass seed shall be selected based on the type of seed suitable to the area and season of year. Refer to the Manual for Erosion and Sediment Control in Georgia for grass growing schedule, selection of grass seed, fertilizers, lime, inoculants, mulching, etc.

3) The contractor shall provide water for irrigation from the nearest available metered source. The soil must be thoroughly wet to a depth that will insure germination of the seed. Water must be applied at a rate not causing runoff or erosion.

4) Growth and coverage on areas grassed shall be considered in reasonably close conformity with the intent of this requirement when a viable stand of grass covers at least 98 percent of the total area with no bare spots exceeding one square foot and the ground surface is fully stabilized against erosion. The contractor shall repeat all work, including plowing, fertilizing, watering, and seeding as necessary to produce a satisfactory stand.

5) The contractor or developer shall do all maintenance work necessary to keep all planted areas in satisfactory condition until the work is finally accepted. This shall include mowing, repairing washes that occur, reseeding, and water as required to produce a healthy and growing stand of grass. Mowing will be required to remove tall and obnoxious weeds before they go to seed.

X. Standard detailed drawings. Installation of fire hydrants, water valves, valve boxes, meters, long side services, water lines, etc. shall be made in accordance with the standard detailed drawings in chapter 112 of this UDC.

Y. Barricades.

1) The contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient red lights, danger signals and necessary precautions for the protection of the work and the safety of the public.

2) Streets closed to traffic shall be protected by effective barricades on which shall be placed acceptable warning signs.

3) Barricades shall extend completely across the street which is to be closed, and shall be illuminated at night by lights not farther than five feet apart, and lights shall be kept burning from sunset to sunrise.

Z. Fences.

1) The contractor shall temporarily remove fences on or crossing the right-of-way for such periods of time only as are necessary to perform clearing, grubbing, trenching, pipe laying and backfilling operations.

2) Gaps made in fences shall be closed in a substantial manner at night and during any suspension of work.

3) Upon completion of the pipe line, fences shall be restored to as good condition as before disturbed.

AA. Rip-rap.

1) Where required, stone rip-rap shall be dumped and hand placed to form a compact layer.

2) Stone rip-rap shall be placed to a thickness of not less than eight inches and not more than 18 inches, to the length and width shown on the plan or as directed by the city engineer.

3) A geotextile liner shall be installed between the soil and the stone.

History

The history line the source prints at the end of the section.

(Ord. No. 2014-18, § 2, 8-21-2014)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:canton/zoning/110.02.04@2026-11-11-b251d1c5ea