110.02.05. Water line inspection, testing and acceptance.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
  • Read by OCR from a scanned page: a character, a name, or a number may be misread.

A. Inspection.

1) Inspection will be done and scheduled as received by the City of Canton Engineering Department.

2) The city engineer shall be notified when specific inspections are required so that the inspection time can be scheduled.

3) The contractor shall present the following when requesting a final project inspection:

a. The size and length of all lines installed including services.

b. A completed project information form (see figure 2).

c. As-built plans and electronic data prepared in accordance with the requirements set forth in subsection E below ("as-built" record drawings).

4) Under no circumstances shall any buildings and plumbing fixtures be connected to the main until the main is inspected and approved by the city.

5) Upon request, the contractor shall furnish the city engineer with appropriate copies of the manufacturer's certification that the materials to be used meet the materials requirements of these specifications. The city inspector may reject any materials not meeting specifications or any faulty or damaged materials. Any materials so rejected just be removed from the project immediately and must be prominently marked so that they can be spotted on this or any other project.

6) Authorized representatives of the City of Canton, which may include appropriate county, state or federal agencies, shall have access to the site for inspection at any time.

7) The city engineer shall be notified by 8:30 a.m. of each workday when work is scheduled unless authorized otherwise.

8) The city engineer may at any time direct that he/she be allowed to see any pipe work, bedding, fire hydrant, tee, valve or other appurtenance. If the city engineer so directs, all pipe work shall be left open until the city engineer views the work. The trench may be backfilled with the approval of the city engineer if the work is not inspected by the close of the working day. Valves, fire hydrants, tees, thrust blocking or lot services shall not be backfilled without the approval of the city engineer.

9) The contractor shall complete the project and shall have cleaned up the job site prior to requesting a final project inspection. The city engineer may terminate the inspection and direct further work at any time he feels that the project is not substantially complete and ready for inspection. The contractor shall furnish adequate personnel to check for open valves and give assistance needed by the city engineer.

10) The representative of the City of Canton Engineering Department will normally visually inspect all water lines and appurtenances for conformance to the specifications and will check the measurements shown on the "as-builts" for accuracy. The representative will perform pressure and leakage tests to insure all lines are watertight. The representative shall also supervise a disinfection test.

a. Any of the following tests may also be required at the discretion of the city engineer:

i. Fire hydrant/hammer test (see section 110.02.03.C).

ii. Trench compaction tests.

b. Any defects found by these tests must be corrected before construction of the project may proceed.

11) A punch list shall be issued for corrective work if needed. However, the city engineer shall not perform the contractor's work by finding all of his problems before the project is reasonably complete.

B. Compaction testing.

1) All trenches shall be subject to compaction testing after backfilling and shall meet the compaction requirements set forth in section 110.02.04.H.

2) All trenches failing to meet compaction requirements shall be excavated and re-compacted and retested. This process shall continue until a passing test is achieved.

3) All costs of compaction testing shall be the responsibility of the developer.

C. Fire hydrant and valve testing.

1) All fire hydrants shall be tested per section 110.02.03 and flushed to check the operation of the hydrant.

2) All valves shall be located and their operation checked. All valves shall be left fully open.

D. Water system testing.

1) General.

a. All lines designed to operate under pressure shall be successfully tested. Tests of installed piping shall consist of a pressure and leakage test and a disinfection test.

b. All piping to be tested must satisfactorily comply with these tests before being eligible for acceptance. In general, tests shall be conducted in accordance with AWWA C600 and C651 except as otherwise herein specified.

2) Pressure and leakage testing.

a. After all piping has been placed, each section between line valves shall be tested by the developer's contractor in the presence of the city engineer or his designated representative and tests shall be continued until all leaks have been made tight to the satisfaction of the city. The contractor shall furnish all necessary meters, pumps, gauges, bulkheads, and other materials and appliances necessary to conduct the test as herein required. Every precaution must be taken to valve-off or otherwise protect control equipment in or attached to the pipe line to prevent damage thereto.

b. Before applying the specified test pressure, all air shall be expelled from the pipe. If hydrants, blow-offs or air release valves are not available at the high places, the contractor shall make the necessary taps at points of highest elevation before the test is made and insert plugs before the test has been completed.

c. Prior to the pressure test, pipe laid in trenches shall be backfilled adequately to secure the pipe during the test. Any observed leakage shall require corrective measures to pipe lines and/or joints to the satisfaction of the city engineer.

d. The city will furnish the necessary water for testing and disinfection of the lines; however, any water lost through breakage of lines or unnecessary or excessive flushing of lines will be charged to the contractor at the current residential rate.

e. All lines shall be tested to a pressure of one and one-half times the working pressure at the lowest point of the system to be tested. Test duration shall be two hours. However, test pressure shall not exceed pipe, valve and/or thrust-restraint design pressures. The city engineer or his representative may require a 24-hour test if he so desires. Test pressure shall not vary by more than plus five psi for the duration of the test which may require periodic pumping (in which case the added water will be counted as part of the leakage). Lines shall be tested in sections between the valves. The rate of leakage shall not exceed 13.5 gallons per 24 hours per inch diameter per mile of water main. (See table 110-4.)

Table 110-4 Leakage Tabulation Size of Pipe (inches) Gallons/Hour/100 Feet Gallons/Day/100 Feet 16" .171 4.091 12" .128 3.068 10" .107 2.557 8" .085 2.046 6" .064 1.534

f. Any section of the line not meeting the above test shall have the leaks found and corrected at once and re-tested until the leakage falls within the limits specified above. Leakage testing must be witnessed and approved by the city.

3) Disinfection.After leakage testing and all necessary repairs have been made, the contractor shall flush and disinfect all potable water mains and equipment installed in strict accordance with AWWA Standard for Disinfecting Water Mains, C651, latest revision.

a. The method of disinfection shall be the continuous — feed method as per AWWA C651, latest revision, section 4.4.3. Care shall be taken in filling the mains so that entrained air is drawn from the pipes at all high points so as to permit intimate contact of the disinfection agent with the entire inside surface of the pipe and appurtenances. The potable water shall be chlorinated so that after a 24 hour holding period in the main, there will be a free chlorine residual of not less than ten mg/L at all points in the system when tested with a standard orthotolindine solution.

b. The form of chlorine shall be a one percent solution made from either sodium hypochlorite or calcium hypochlorite which shall be measured and pumped into the pipeline. Water must be flowing during the feeding operation and the injection point must be located so that the flow of water will disperse the chlorine throughout the pipeline. AWWA C651 requires the injection point be located at a point not more than 10 feet from the point of connection to the existing water supply. The chlorine should be fed at a constant rate such that the water will have not less than 25 mg/L free chlorine. Table 110-5 gives the amount of chlorine required for each 100 feet of pipe of various diameters to produce a 25 mg/L concentration.

Table 110-5 Chlorination Tabulation Pipe Diameter (in.)

100% Chlorine (lb.)

1% Chlorine Solution (gal.)

6" 0.030 0.36 8" 0.054 0.65 10" 0.085 1.02 12" 0.120 1.44 16" 0.217 2.60

c. After 24 hours, the line shall be flushed until the chlorine content is not more than two parts per million. When this step is completed, the developer will notify the city engineer so as to schedule the taking of the water sample for the bacteria test. If the samples show evidence of contamination upon testing, the above procedure of disinfection shall be repeated until approved samples are obtained. No connections shall be made to the existing system until all of the samples have been tested and approved by the city engineer. The developer may be required to add additional taps for bleeding purposes at the ends of water mains or wherever necessary for taking samples.

d. The contractor shall dechlorinate the highly-chlorinated water being flushed from the water main to open areas where the discharge will not damage the roadbed or adjacent property.

e. The chlorine residual of water being disposed may be neutralized by treating the water with one of the chemicals listed in table 110-6:

Table 110-6 Chemical Required* Residual Chlorine Concentration mg/L Sulfur Dioxide (SO2 ) Sodium Bisulfite (NaHSO3 ) Sodium Sulfite (Na2SO3 ) Sodium Thiosulfate (Na2S2O3 .5H2O) lb. (kg) lb. (kg) lb. (kg) lb. (kg) 1 0.8 0.36 1.2 0.54 1.4 0.64 1.2 0.54 2 1.7 0.77 2.5 1.13 2.9 1.32 2.4 1.09 10 8.3 3.76 12.5 5.67 14.6 6.62 12.0 5.44 50 41.7 18.91 62.6 (8.39 73.0 33.1 60.0 27.22

* Amounts of chemicals required to neutralize various residual chlorine concentrations in 100,000 gal (378.5 m3

) of water.

E. "As-built" record drawings. At the completion of the water line installation and when requesting the final project inspection, the city engineer shall receive from the contractor three sets of printed "as-built" plans and electronic data prepared in accordance with the following requirements:

1) Attached to the "as-builts" shall be a completed project information form (figure 2), which includes the name of the project, the project location, the developer's name and telephone number, the contractor's name and telephone number, the street names, the water main size for each street, the length of the water main for each street, the pipe material used on each street, the cost of the water facilities for each street, and the work start date and work completion date for each street.

2) Three sets of "as-built" plans shall be submitted to the city engineer.

a. The plans shall show all water information "as-built" in the field and any field changes made to the approved plans.

b. In the event "as-builts" cannot be made available at the completion of the line, the city engineer may authorize the continuation of the construction; however, the final inspection cannot be conducted and the conditional approval letter cannot be written until "as-builts" are received.

c. In the event that the designer does not perform the field staking, the contractor must furnish certification from a licensed engineer or surveyor attesting to the accuracy of all as-built information presented. This certification and the certification of the engineer/land surveyor preparing the "as-builts" must be shown on the drawings.

d. "As-built" drawings shall include a site plan, plan and profile sheets, and any supplementary drawings and shop drawings. Stationing of the water main alignment and the various water system appurtenances shall be required on the "as-builts" as well as the construction drawings along with the point I.D.

e. The "as-built" drawings shall meet the same requirements as the plans for review.

f. The printed version of the as-built water plan shall show the correct location and point I.D. of water mains at all transitions (vertical and horizontal) at 50-foot intervals along city, county, state or federal road ways), fire hydrants, fittings, tap location(s), valves, meters, and lot services.

3) "As-built" plans shall be submitted on 22-inch by 34-inch drawing sheets and shall be submitted concurrently in an "AutoCAD" drawing electronic format.

a. The monumentation and the calculations used to reference and determine the coordinate system for locations shall be supplied at the same time that "as-built" plans are submitted.

b. As-built information for utility locations shall be shown on plans and submitted in ASCII text electronic format for each point.

4) Horizontal locations shall be referenced to Georgia State Plane Coordinates (west zone feet). Vertical locations shall be shown referenced to mean sea level. Reference all horizontal locations to the NAD83/94 (latest adjustment) datum and reference all vertical locations to the NAVD88 datum. All orthometric locations shall be referenced to Geoid 99/03. All points shall be verifiable by the City of Canton Engineering Department control network. All horizontal and vertical locations shall have no translation, rotation or angle adjustment. All points are subject to verification by the City of Canton Engineering Department.

5) The information submitted electronically for water mains, including correct locations of the water main, point I.D. of water mains at all transitions (vertical and horizontal) at 50-foot intervals along city, county, state or federal roadways), fire hydrants, valves, fittings, main line taps, master meters, and fire line meters, shall include:

a. Point I.D. (see City of Canton Engineering Department staff).

b. Northing.

c. Easting.

d. Ground elevation.

e. Top of pipe, valve or hydrant elevation.

f. Point description (pipe, fitting or valve type and size).

6) The following are specific guidelines for the preparation of the printed version of the "as-built" drawings:

a. Water "as-built" shall be a separate plan.

b. No contour lines.

c. Location of service, meter and backflow preventer shall be shown.

d. Road names shall be on plans.

e. The center of all fire hydrants shall be located horizontally and vertically as described above.

f. All lots shall be numbered.

g. Printed "as-builts" shall be clear and legible.

h. Roads shall be shown on all plans.

i. "As-built" shall be in large clear print on plans.

j. Drawings sheet shall be no larger than 22 inches by 34 inches.

k. Scale shall be no larger than one inch equals 20 feet, no smaller than one inch equals 100 feet for cross-country lines and one inch equals 50 feet for congested areas.

l. When a phase of a subdivision is completed, a location sketch of the entire subdivision with said phase outlined shall appear on the plans. m. Ground water and solid rock encountered during construction shall be noted on "as-builts."

n. Water point I.D.'s (valve I.D., water main points, etc . . . ) shall be on plans, electronic data and ASCII or EXCEL data file. All point I.D.'s shall correspond.

7) As-built water plans for commercial, multi-family, school and industrial sites shall show the following at a minimum scale of one inch equals 100 feet:

a. Location, size and elevation of all existing and proposed water, sanitary sewer, and fire lines and of any easements required.

b. Location and size of all fire mains and location of all fire hydrants.

c. Location, size and number of dwelling units and buildings.

8) The "as-builts" must be printed from the AutoCAD files supplied to the City of Canton Engineering Department concurrently with the "As-Builts." These plans shall have been corrected to show all field changes made to the approved drawings. Hand marked copies prepared by the contractor will not be accepted for "as-builts."

9) As-built drawings shall include the site plan, construction plan sheets, and any supplementary drawings and shop drawings. Plan of fire meters or detector meters should be shown if applicable. "As-builts" is to be stamped in large clear print on plans.

10) The City of Canton shall have the right to withhold water meters until the "as-builts" have been submitted as required.

11) Final plat and/or final plans will not be approved or signed by the City of Canton until "as-builts," easement drawing and easement agreements have been completed and submitted to the City of Canton Engineering Department.

F. Acceptance. Please refer to figure 1 for the procedures related to the final approval and acceptance of water and sanitary sewer facilities:

Figure 1 City of Canton Maintenance Bond/Letter of Credit Administrative Policy & Procedures General

• All new developments must submit to the City a maintenance bond or letter of credit prior to approval of the final plat for residential developments or the acceptance of the as-built drawings for all other developments.

• Once the water and sewer infrastructure is in place and approved, the developer must submit a maintenance bond or letter of credit in a form acceptable to City of Canton Engineering Department staff, prior to the city's approval of the final plat or as-built plans.

• The maintenance bond or letter of credit amount will be generally determined by the linear feet of water and linear feet of sewer infrastructure within the development.

• Maintenance bonds or letters of credit shall be for a period of 12 months from the receipt of Final Plat approval for residential developments or acceptance of as-built drawings for all other developments.

Approval of Infrastructure for Final Plat Recording

1) Upon the completion of the water and/or sewer construction, the developer shall contact the City of Canton Engineering Department requesting a final inspection of infrastructure.

2) If the City Engineer finds, upon inspection, that all infrastructures meet the requirements of the City of Canton Unified Development Code (UDC), he/she shall provide written notice of acceptance to the developer.

3) If the City Engineer finds, upon inspection, that infrastructures do not meet the requirements of the City of Canton UDC, the City Engineer shall provide the developer with written notice detailing the reasons for rejections of the infrastructure.

4) Once the City Engineer finds that all infrastructures meet the requirements of the City of Canton (UDC), the City Engineer shall require the developer to post maintenance bond or letter of credit.

5) Once a maintenance bond or letter of credit has been posted, the City Engineer will approve the final plat for residential developments or accept the as-built drawings for all other developments.

6) Final plat will not be signed or as-built drawings will not be accepted until a satisfactory maintenance bond or letter of credit has been posted.

No Exceptions.

Maintenance Bond/Letter of Credit Amount

1) The maintenance bond or letter of credit amount will be determined generally by the linear footage of water line and/or the linear footage of sewer line within the development.

2) Per foot amount will be determined by the City Engineer taking into account the current economic climate as well as the cost of materials, labor and fuel.

3) The minimum maintenance bond and/or letter of credit amount required for a development shall be $5,000 for water and $5,000 for sewer.

Approval of Water and Sewer System for City Acceptance

1) The 18-month maintenance period will allow the City Engineer to assure compliance with the City of Canton UDC development specifications. The developer shall be required to contact the City Engineer in writing at the end of the 9-month period to initiate the City's punch list.

2) The City Engineer shall prepare a single punch list to the developer affording a 60-day period in which to make all necessary repairs. The developer shall be required to contact the City Engineer in writing at the end of the 60-day period after all punch list items have been completed. The City Engineer shall have 30 days to make its final review for approval and shall notify the developer in writing of the results of this inspection. An extension of the bond may be granted at the discretion of the City Engineer. The developer shall pay for any additional inspections required by the developer's failure to complete punch list items prior to final approval.

3) If any punch list items are not completed by the developer within the specified period of time or extensions the maintenance bond or letter of credit shall be utilized to pay for the full cost of the repairs. Should the amount of the maintenance bond or letter of credit be inadequate to pay for the full cost of the repairs, the City of Canton shall have the authority to collect the remaining amount from the developer.

Official Acceptance/Release of Bond or Letter of Credit

1) At the time that the work is inspected and found free from defects, the City Engineer shall provide the developer with written "Final Approval" for the acceptance of the water and sewer infrastructure.

2) Upon the issuance of final approval, the City of Canton shall release the maintenance bond or letter of credit.

Lift Station Maintenance Bond

1) All new subdivisions or commercial developments that include wastewater lift station(s) will be required to post a maintenance bond or letter of credit for each lift station.

2) The amount of the maintenance bond or letter of credit will be in amount as determined by the City Engineer.

3) The maintenance bond or letter of credit will be for an 18-month period from the date of acceptance a limited warranty deed for the fee simple ownership of the real property upon which the pump station is constructed.

4) The maintenance bond or letter of credit will be released following the expiration of the 18- month maintenance period and upon final inspection and final approval of the lift station.

5) The developer shall provide a detailed construction cost report to the City of Canton Engineering Department upon completion of construction of any lift station prior to the acceptance of as-built drawings.

Figure 2 City of Canton Project Information Form Water System Facilities Project Name:

Location:

Developer: Phone No: (__) - Contractor: Phone No: (___) - Street or Segment Name:

Water Main Size: Length: Material: No. of Manholes:

Start Date: / / Completion Date: / / Street or Segment Name:

Water Main Size: Length: Material: No. of Manholes:

Start Date: / / Completion Date: / / Street or Segment Name:

Water Main Size: Length: Material: No. of Manholes:

Start Date: / / Completion Date: / / (Ord. No. 2014-18, § 2, 8-21-2014)

110.03.00 Cross-connection control program.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:canton/zoning/110.02.05@2026-11-11-487f45d758

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Canton Zoning Ordinance, 110.02.05. Water line inspection, testing and acceptance | Georgia Commons