Canton · Zoning Ordinance
Part III - DEVELOPMENT CODE / Chapter 111 - DESIGN STANDARDS: SEWER SYSTEM TABLE OF CONTENTS
111.03.04. Wet wells.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A. Wet wells shall be a minimum diameter of six feet. Rectangular wet wells shall be allowed upon approval of the city. Sizing of wet wells shall be as follows:
1) For lift station pumping, Vmin = Tmin × Q/4, where:
a. Vmin = The minimum effective wet well volume in gallons. This effective volume is the volume between the "pumps on" and the "pumps off" elevations. The "pumps on" elevation shall be a minimum of two feet below the invert of the inflow pipe.
b. Tmin = The minimum cycle time in minutes. All lift stations shall be sized based on six starts per hour or Tmin = ten minutes. Although most pumps are rated at much higher starts per hour, the size is set at six starts per hour due to the limited number of starts per hour allowed by the electrical hardware. Ideal cycle time is achieved when the pump capacity (Q) is two times the inflow.
c. Q = Pump capacity in GPM.
B. The wet well subgrade must have a minimum 95 percent Std. proctor and a 24-inch minimum thickness of #57 stone base.
C. All wastewater lift stations shall be designed so that the base elbow to the submersible pumps be mounted on a grout shelf approximately one foot above the base slab or to the pump manufacturer's recommendations. The base elbow shall be anchored to the base slab with four and three-quarters-inch stainless steel bolts — 5,000 pound pull-out each. Bolts shall be threaded into concrete a minimum of 8 inches.
Anchor inserts shall be cast into the invert. Carbon steel bolts shall not be accepted.
D. All miscellaneous metals inside the wet well shall be stainless steel. Typical wet well pipe supports shall be constructed of stainless steel with stainless steel mounting hardware. Bracket shall be a minimum of three-inch by three-inch by five-sixteenths-inch. Pipe strap shall be minimum three-inch by five-sixteenths-inch with minimum ½-inch stainless steel bolts. Base of support shall be constructed of five-sixteenths-inch stainless steel plate mounted with three-quarters-inch stainless steel bolts.
E. A vent for the wet well shall be supplied constructed of ductile iron pipe. The vent shall be a minimum of six-inch diameter floor pipe, FL. x P.E., shall be cast in place and shall extend six inches up from the top of the wet well. A one foot long D.I.P. FL. x FL. spool shall be connected to the floor pipe and two six-inch diameter 90 degree bends shall be mounted to the spool to complete the vent pipe. A stainless steel bird screen shall be attached to the open end of the bend.
F. For wet wells larger in area than a ten-foot diameter well, squirrel cage type ventilator fans shall be supplied and shall have enough capacity to provide a minimum of six air changes per hour. The fan shall include mounting curb, bird screen and explosion-proof motor. Acceptable manufacturers are Penn, Acme and Twin City Blowers or alternate acceptable to the city.
G. A lift station wet well access ladder shall be provided. The ladder is to be constructed of materials not likely to be affected by the corrosive atmosphere of the wet well. The ladder is to be permanently mounted in the wet well to provide access for maintenance. Cast-in concrete steps will not be acceptable as an access ladder.
The ladder steps shall be roughened to deter foot slippage. Minimum ladder width shall be 18 inches. Ladder shall be equipped with "safety-climb" and must be easily accessible.
H. Odor control equipment is required on all new sewer lift stations. Proposed odor control equipment is subject to review and approval by the city on a case by case basis.
History
(Ord. No. 2014-18, § 2, 8-21-2014)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.