Coffee County · Zoning Ordinance
Appendix D - LAND DEVELOPMENT CODE / Chapter 10 - ADMINISTRATIVE PROVISIONS
10-12. Submittal Requirements for Infrastructure and Utility Plans.
About this text
- As published by Municode, current through 2024-10-07
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
a. Infrastructure and Utility plans. The plans for the required public improvements shall be prepared for approval by the Zoning Administrator prior to the construction and only after approval of the preliminary plat. Such improvement plans shall show the proposed locations, sizes, types, grades and general design features of each improvement and shall be based on reliable field data.
(1) The improvement construction drawing shall be submitted on white background prints. The sheet size shall be a minimum 11 inches by 17 inches unless another size is approved by the Zoning Administrator. The drawing shall be include the following information:
i. Construction plans. The developer shall provide the plan and profile of each proposed street indicating the existing ground surface elevation and proposed street centerline grade. Design shall be in accordance with good engineering practices.
ii. Street-typical sections. A typical section of each proposed street shall be submitted, showing the width of the street and the width of rights-of-way.
iii. Water supply, sanitation systems, utility systems and storm water drainage. The plan and profile of proposed sanitation, storm drainage or other drainage systems, with grade and sizes indicated are required. Floodplain areas shall be indicated on the plan. Stormwater drainage shall be consistent with applicable ordinances of the governing authority and other applicable governmental agencies. Water and sewer systems shall be approved by the County Engineer and all relevant state agencies.
iv. Utility service agreement. A developer's agreement for utilities service shall be required before final improvement plan approval is granted.
v. As-built drawings. The designing surveyor or engineer shall submit to the Administrator two sets of white background prints of certified as-built drawings prior to recording of the final plat.
b. Plans for infrastructure, utilities, and other improvements shall be submitted, after an approved preliminary plat has been obtained, demonstrating compliance with the requirements of chapter 7 and other engineering and construction standards of Coffee County.
c. Following approval of the Preliminary Plat, the developer shall request approval of the improvement plans by the County Engineer. Said developer can begin installation of the minimum improvements, including grading, paving, installation of utilities, etc., upon approval of the improvement plans. In all cases, sedimentation control devices, retention, detention or sedimentation ponds shall be first in order of construction.
d. Improvements required and/or regulated by these regulations shall be constructed in accordance with approved engineering plans and specifications, the standards, requirements and regulations set forth in these regulations, and other applicable ordinances of the County.
e. Construction of improvements required or regulated by these regulations shall not commence until the County Engineer has approved in writing engineering plans and specifications for said improvements.
f. If, in the course of construction, the developer wishes to modify the size, type, quality, quantity and/or location of any or all of the improvements required or regulated by these regulations, the developer's engineer/surveyor shall submit a written change request to the County Engineer for review and written approval prior to proceeding with installation of the modified improvement.
g. Tests required by these regulations shall be performed solely by independent testing laboratories, the developer's engineer/surveyor or qualified personnel employed by the developer's engineer/ surveyor, and shall be performed at the developer's expense. The developer's engineer/surveyor shall direct that the results of required tests be mailed or delivered to the County Engineer immediately on completion. All test results must be clearly indicated as to the project and the exact location of the sample and that no test results be withheld from the County Engineer.
h. Acceptance. Upon written notification of completion of Minimum Improvements, the County Engineer shall within 30 days after such notice accept or reject, in writing, the completed improvements stating the deficiencies, if any.
(1) The required minimum improvements shall not be accepted unless they conform to these regulations and officially adopted County specifications.
(2) Upon completion of construction of improvements required and/or regulated by this chapter, the developer's engineer/surveyor shall deliver all required test data not previously forwarded to the County Engineer to the County Engineer.
(3) The County Engineer is authorized to reject any construction which fails to conform to the approved plans and specifications and this chapter.
(4) The County shall bill the developer the County's cost for any subsequent inspections necessitated by the developer's failure to construct improvements in accordance with approved plans and specifications and this chapter. Said costs shall be based on a schedule of fees established as two and one-half times the inspector's hourly rate.