Commerce · Zoning Ordinance
Commerce Zoning Ordinance
This document is shown whole, as one text: its source does not cut it into sections.
About this text
- As posted on the city's website, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Part 3 of 6. This text is long, so its page prints it in parts, in the source's order. A link to one of its paragraphs leads to the part that holds it.
(c) Need for loading and unloading spaces. Space for the loading and unloading of equipment, supplies, and products is needed to serve properties engaging in such loading and unloading operations. If not required, adequate and proper loading spaces in acceptable locations tend not to be provided.
(d) Environment. Poor design of parking lots can lead to damage to the environment and may require the community to subsidize the interests of a private property owner at the expense of the community’s environment. It is reasonable to require good design of parking lots. Possible negative effects of parking and loading areas include changes to microclimate, isolation of pedestrians, increased stormwater runoff, and reduced stormwater infiltration into the ground.
(e) Stormwater management. Parking lot surfaces such as asphalt and concrete contribute to the degradation of local water quality. Parking lots can be more compatible environmentally if protection measures are incorporated into design standards and regulations. Porous pavement and grass pavers reduce runoff by allowing it to pass through the paved surface and infiltrate back into the soil and groundwater. Utilizing porous pavements and grass pavers also reduces or eliminates land dedicated to surface storm water management facilities. Porous pavement designs and grass pavers are appropriate in some instances. Other types of stormwater management facilities are environmentally compatible, such as vegetative swales and bioretention. It is therefore appropriate to provide for alternative pavement materials, such as porous asphalt, turf block, gravel, and cobbles which have higher degrees of water quality effectiveness than conventional asphalt and pervious concrete.
(f) Pedestrian mobility. Areas of paving are necessary to accommodate automobiles, but they can be unfriendly to pedestrians without specific regulations requiring that designers accommodate pedestrians. Large, open parking areas are conducive to high speeds and random maneuvers which can endanger pedestrians. Wide driveway aisles and access roads also increase speeds and discourage pedestrian travel. Street and parking lot design can balance the needs to accommodate automobile-centered standards with approaches that take into account the needs of pedestrians. It is in the public interest to establish onsite circulation patterns conducive to safe pedestrian as well as vehicular and truck access.
(g) Overbuilding of parking lots. Off-street parking requirements, as conventionally implemented, have resulted in excess, unnecessary parking around commercial development because it remains unused for most of the year. Parking lot construction is a considerable factor in the cost of development. Reducing parking areas reduces development costs. Therefore, reductions in the size of paved parking and flexibility in the types of pavement and parking designs are beneficial to all concerned. It is in the public interest to establish maximum off-street parking limitations.
(h) Connectivity. Abutting properties which do not provide interconnecting access to one another make it difficult, dangerous, and inefficient if not impossible, for motorists to travel between those properties. Between compatible uses, provisions requiring interparcel access meet substantial public purposes of convenience and safety. It is therefore in the public interest to promote and require inter-parcel access to facilitate movement of customers from business to business without generating additional turning movements on the public street, thus increasing public safety.
(i) Public improvements. It is in the public interest to establish design and improvement specifications for the development of driveways and the connection of parking lots to public streets.
Sec. 6-102. Definitions.
AASHTO: The American Association of State Highway and Transportation Officials.
Access: A way or means of approach to provide physical entrance to a property.
Arterial, principal: A term used in the functional classification of roads. These roads, which include interstates and rural freeways: serve “substantial” statewide or interstate trips, as defined by high mileage or volume; connect most urban areas of 25,000 or more and virtually all urban areas of 50,000 or more; and provide an integrated network without stub connections except where geography dictates otherwise. Arterials are the longest roads with the highest speed limits.
Arterial, minor: A term used in the functional classification of roads. With the principal arterial system, these roads form a rural network that links other cities, larger towns, and other traffic generators, such as major resort areas, capable of attracting travel over long distances; link all developed areas of the state; and serve corridors with trip lengths and travel density greater than those predominantly served by rural collector or local systems. Minor arterials, therefore, constitute routes whose design should be expected to provide for relatively high overall travel speeds, with minimum interference to the through-movement.
Collector, major: A term used in the functional classification of roads. These roads, with minor collectors, primarily serve the city rather than state traffic. Consequently, more moderate speeds are typical. They serve any places not on an arterial route, and other traffic generators of equivalent intra-county importance, such as consolidated schools, shipping points, county parks, and important mining and agricultural areas; link the latter places with nearby larger towns or cities, or arterials and freeways; and serve the more important intra-county travel corridors.
Collectors are shorter roads with slower travel speeds than arterial roads.
Collector, minor: A term used in the functional classification of roads. Serving county-wide or city-wide traffic, these roads should evenly collect traffic from local roads and bring all developed areas within a reasonable distance of a collector road; provide service to the remaining smaller communities; and link the locally important traffic generators with the hinterlands.
Curb cut: Any interruption or break in the line of a street curb for the purpose of connecting a driveway to a street, or otherwise to provide vehicular access to abutting property.
Deceleration lane: A speed-change lane, including tapered areas, for the purpose of enabling a vehicle that is making an exit turn from a roadway to slow to a safe turning speed after it has left the mainstream of faster-moving traffic. Also called a “decel lane”; it denotes a right turn lane or a left turn lane into a development.
Driveway: A constructed vehicular access serving one or more properties and connecting to a public or private street.
Driveway, residential: Any private passageway to any property used for dwelling purposes.
However, if a driveway provides access for more than four dwelling units, it shall be considered a commercial driveway.
Driveway width: The narrowest width of a driveway measured perpendicular to centerline of the driveway, from edge of pavement to edge of pavement or edge of curb to edge of curb.
Functional classification of roads: A system for the classification of roads used by the Federal Highway Administration, the Georgia Department of Transportation and the county and city. The system is based on several factors, including: the amount of traffic currently on the road plus if any new major traffic generators (e.g., new schools, new subdivisions, new community level commercial centers, or new major employers) are being built in the near future along that roadway; the length of the roadway in comparison with the functional classification of other roads in the same area.
Gated community: Residential areas that restrict access to normally public roads and spaces.
Gates can include guard houses, electronic arms operated by card, codes, or remote control devices. Visitors must stop to be verified for entry.
Handicapped parking space: A space for parking a standard sized passenger vehicle, laid out and designated by signage in accordance with the requirements of the federal Americans with Disabilities Act.
Highway: A term applied to streets and roads that are under the jurisdiction of the Georgia Department of Transportation or federal highway agency. Highways are major arteries of the circulation network, carry significant volumes of traffic for both long and short trips, and are designed with access to abutting properties with some degree of control and safe standards of design.
Horizontal alignment: Horizontal geometrics of a roadway.
Horizontal curve: A curve by means of which a road can change direction to the right or left.
Inter-parcel access: A roadway or series of connecting roads within a property providing access to interior lot frontage or other properties, not connected to a public road or state route.
Intersection: The general area where two or more roads join or cross, including the roadway and roadside facilities for traffic movements within the area.
Parking aisle: The traveled way, which is not the public right-of-way, by which cars enter and depart parking spaces and maneuver within a designated parking lot.
Parking lot: Any public or private area at grade used for the express purpose of temporarily parking automobiles and other vehicles otherwise in operation for personal or business use.
Parking space: A space identified and set aside for the temporary parking of an automobile or other motor vehicle. The typically acceptable parking space has a dimension of 9 feet in width by 20 feet in length, although this Article permits reductions in parking space widths in certain circumstances.
Source: Stover, Vergil G., and Frank J. Koepke. 2002.
Transportation and Land Development (2nd Ed.).
Washington, DC: Institute of Transportation Engineers.
Figure 9-13, p. 9-24.
Pavement markings: Devices or paint placed on the roadway to mark pavement for vehicular and pedestrian traffic control.
Pavement width: The width of a given lane, road, or other road pavement width, measured from back-of-curb to back-of-curb or to the edge of pavement where no curbs are required or exist.
Profile: A longitudinal section of a roadway, drainage course, etc.
Public improvement: The construction, enlargement, extension or other construction of a facility intended for dedication to the city or to a facility already owned by the city, including but not limited to a street, curb and gutter, sidewalk, cross drain, catch basin, other roadway appurtenance, domestic water supply system main, fire hydrant, valve or other water system appurtenance, or sanitary sewerage main or outfall, lift station, force main, manhole or other appurtenance. Utility supply lines to a building are not considered public improvements.
Reservation: The designation by plat or deed of a certain area reserved for possible future public purposes. A reservation does not transfer title of the reserved area to the public unless the Commerce City Council accepts the area for public purposes.
Right-of-way: Land reserved for and immediately available for public use as a street or other purpose.
Right-of-way, private: That area, distinguished from an access easement or public right-of-way, dedicated to property owners of the subdivision involved or to other individuals, and which affords permanent access to abutting property or properties. A private right-of-way is distinguishable from a public road right-of-way in that maintenance and ownership of the road and accessory improvements is by private individuals or a private association rather than the county, state, or another governmental entity.
Right-of-way, public: That area, distinguished from an easement or private road right-of-way, which is owned in fee-simple title or via prescription by the City of Commerce, the Jackson County Board of Commissioners, State of Georgia, or other government, for the present or future use of roads, roads and highways, together with its drainage facilities and other supporting uses and structures.
Right-of-way miter: A right-of-way line at a street or highway intersection, which is parallel to neither road but forms a triangle with extensions of the right-of-way lines of the adjacent sides of the intersecting roads. The purpose of a right-of-way miter is to provide improved visibility for vehicles approaching the intersection by enabling the elimination of visual obstructions or to provide room for a traffic signal support pole or guy wire.
Road: A state highway, a county road, a road adopted as a county-owned right of way approved for county maintenance, a street owned and/or maintained by a municipality, or where permitted, a private road. Roads afford the principal means of access to abutting property or properties and are required to meet specifications contained in this UDC. The term includes “street” but does not include “access easement.”
Road, private: An improved road, distinguished from a public road in that the right-of-way which affords a principal means of access to abutting property or properties is privately owned and maintained. Private roads are required to meet specifications contained in this UDC.
Road, public: A state highway, county road, a road adopted as a county-owned right of way approved for county maintenance, or a street owned and/or maintained by a municipality. New public roads are required to meet specifications contained in this UDC.
Roadway: The portion of a highway or road, including shoulders, for vehicle use.
Roadway drainage structure: A device such as a bridge, culvert, or ditch, composed of a virtually non-erodible material such as concrete, steel, plastic, or other such material that conveys water under a roadway by intercepting the flow on one side of a traveled way consisting of one or more defined lanes, with or without shoulder areas, and carrying water to a release point on the other side.
Sidewalk: A hard-surfaced pedestrian access area adjacent to or within the right-of-way of a street.
Sight distance: The length of roadway ahead visible to a driver.
Street: A dedicated and accepted public right-of-way, or a private street approved by the Commerce City Council, which affords the principal means of access for motor vehicles to abutting properties.
Traveled way: The portion of a roadway for the movement of vehicles, exclusive of shoulders and auxiliary lanes.
Sec. 6-103. Compliance required.
(a) Before any land disturbance permit, development permit or building permit is issued for a given development or building, the access (including driveways), parking lot layout and area, and if applicable loading area, must be found by the Zoning Administrator to be in compliance with all applicable requirements of this Article. No such permit shall be issued if the access and improvements fail to comply with the requirements of this Article.
(b) The Building Official shall not issue a building permit and shall not allow occupancy or use of a building until advised by the Zoning Administrator that access, parking, and loading as applicable meet the requirements of this Article.
(c) No lot shall be subdivided unless it complies with the requirements of this Article.
(d) When located in the Highway Corridor Overlay District established in Article 4 of this UDC, additional requirements apply.
Sec. 6-201. Access to entire parcel.
(a) The entire parcel, rather than simply a particular project, shall be considered in formulating and approving access plans. To this end, the Zoning Administrator may require a development project or subdivision on only part of a lot (unsubdivided parcel) to design and provide access through the remainder of the parcel not proposed for land development at the time or reserve such future access by easement or right of way.
(b) Where land proposed to be subdivided or developed includes only part of the tract owned or intended for subdivision or development by the subdivider or land developer, a tentative plan of a future road system for the portion not slated for immediate subdivision or land development consideration shall be required by the zoning administrator. When such tentative plan is required, it shall be prepared and submitted by the subdivider or land developer no later than the time of submission of lot subdivision or development plan approval, whichever occurs first.
Sec. 6-202. Access required.
(a) A publicly approved street meeting the requirements of this Article shall serve every development and every lot within a subdivision, unless otherwise specifically provided in this Article.
(b) Every development and every major subdivision shall have access to the public right-ofway via a standard city street.
Sec. 6-203. Access control on state routes.
(a) Access onto a state road shall meet the Georgia Department of Transportation Regulations for Driveway and Encroachment Control, Revision 4.0, dated March 15, 2016, as may be amended from time to time. For driveways accessing U.S. or State highways, the requirements of the Georgia Department of Transportation shall apply whenever more restrictive than the standards in this UDC.
(b) A copy of the Georgia Department of Transportation permit, if required, shall be submitted to the Zoning Administrator before plans for land development are approved or permits can be issued for building. Proposed subdivisions along state routes also require prior review and recommendation by the Georgia Department of Transportation. No project proposals will be reviewed by the City of Commerce Planning Commission until the Georgia Department of Transportation review is completed and approved.
Sec. 6-204. Access easements.
(a) For any lot of record which existed prior to adoption of this UDC but which does not have frontage on a public street or private street meeting the requirements of this UDC, access may be obtained to and from that lot of record solely via any access easement which was lawfully established for access to such lot prior to the adoption of this UDC.
(b) A new access easement shall not be authorized as the sole means of access to a lot.
Sec. 6-205. Common access easements for shared driveways.
Shared driveways between two parcels along the common property line of the two parcels may be required by the Zoning Administrator at the time of lot subdivision.
Sec. 6-206. Substandard access.
In the event that any development or major subdivision, other than minor subdivisions and infill lot development, has access to a substandard road (i.e., a dirt, gravel or surface treated pavement road), the following project access improvements shall be required.
(a) The street shall be upgraded by the developer or subdivider to a standard city street from the project entrance to the nearest standard paved road along the route of access.
(b) The roadway section shall meet the requirements for the functional classification of street as determined by the Zoning Administrator based on the functional classification assigned by the city or county transportation plan or other official standards and guidelines as may be appropriate.
(c) The developer or subdivider shall design the road and provide the labor, equipment and materials required for roadway improvements and necessary drainage improvements.
(d) The right-of-way required for these off-site improvements shall be acquired by the developer or subdivider at no expense to the city. If the developer or subdivider cannot acquire adequate right-of-way, the city attorney shall initiate acquisition proceedings at the expense of the developer after authorization by the City Council.
(e) If the city desires the roadway to be improved to a standard greater than the functional classification of street as determined by the zoning administrator, the city shall provide or pay the cost of the additional right-of-way, materials, and labor.
Sec. 6-207. Improvement of existing street adjoining subdivision or land development.
At the time of any non-single-family residential development or major subdivision, existing roads that adjoin the development or subdivision shall be improved to meet the minimum standards of this UDC along the entire length of the development’s road frontage. Such standards include standard right of way width, standard pavement width, curbs, gutters, and sidewalk for the street’s functional classification as determined by the zoning administrator.
Sec. 6-208. Inter-parcel access.
(a) Developments abutting an arterial or collector street shall provide vehicular access to abutting commercial or multi-family residential development, whether existing or planned (i.e., according to either the zoning map and/or the future land use map, as determined by the zoning administrator), so as to provide a vehicular connection among all adjacent parcels also abutting an arterial or collector street.
Source: Florida Department of Transportation. 2008.
Driveway Information Guide.
(b) This requirement may necessitate driveway aprons, stub-outs, or other design features to provide for cross-connection access to abutting properties as determined by the zoning administrator. If inter-parcel access is required, the property owner shall grant an access easement to facilitate the movement of motor vehicles from site to site.
(c) Where possible, the location of vehicular connections across a property line shall be mutually determined and constructed by both property owners. Connection of parking areas for vehicular access may be provided in the front portion of the site. In cases where it is not possible to provide the connection in front, it may be provided in the rear portion of the site. In the case of coordination problems or any factors preventing construction of an inter-parcel connection, the Zoning Administrator will determine the location of the inter-parcel connection to be constructed by property owners.
Sec. 6-209. Inter-parcel pedestrian access.
New multi-family residential, institutional, commercial development that abuts a planned, new or existing multi-family residential property, institutional property, or commercial property shall provide a sidewalk connecting the two uses, unless the Zoning Administrator determines that it is unnecessary to provide inter-parcel pedestrian access due to the unlikelihood of patrons walking among two or more existing or proposed uses on abutting or nearby sites. This provision shall require such developments to construct the required sidewalk to the property line so that it may be continued by the adjacent development for future connectivity.
(a) Internal to each building site, non-single-family residential developments shall provide safe routes of pedestrian access between points of departure and destinations. Such provisions for pedestrian access shall be shown on plans, including site plans for development permits, and building permits.
(b) When multiple buildings are proposed, they shall be linked with on-site pedestrian walkways.
(c) All walkways internal to the site shall be a minimum of 5 feet wide.
(d) The internal sidewalk system shall connect to the public sidewalk system along streets and highways, where it exists or is planned.
Sec. 6-210. Traffic control signage.
All land developments shall be provided with traffic control signs (e.g., speed limits, direction of travel, etc.) if necessary, that meet or exceed The Manual on Uniform Traffic Control Devices for Streets and Highways published by the Federal Highway Administration of the U.S. Department of Transportation, as may be amended from time to time, subject to the approval of the zoning administrator.
Sec. 6-211. Roadway curve protection.
(a) This section shall apply to new subdivisions which abut an arterial road with a designated speed limit of greater than 30 miles per hour at the point of a simple circular curve, compound curve, reverse curve, transition curve, or a vertical curve including both sag and crest curves.
(b) Guardrails shall be installed if the development is on an arterial road and in an applicable curve. The Zoning Administrator may require an additional buffer on the lots in an applicable curve of up to 25 feet in width if the existing right of way of the arterial road is less than 60 feet.
(c) Uniform fencing and/or walls shall be installed along the entire property line abutting the arterial road.
Sec. 6-301. Standards generally.
Public streets contained wholly within a subdivision or land development shall be improved to the full standards contained in this Article.
Sec. 6-302. Functional classification.
The functional classification of a given street in the city shall be as designated in the Jackson County Comprehensive Transportation Plan, as may be amended from time to time. Where the county transportation plan does not classify a certain street in the city, it shall be the responsibility of the Zoning Administrator to determine the functional classification based on the definitions in this Article.
Sec. 6-303. Street right of way.
(a) All State or U.S. numbered highways shall meet all design requirements of and be approved by the Georgia Department of Transportation.
(b) All other roads shall meet the minimum street right-of-way requirements of Table 6-3-1.
Table 6-3-1 Minimum Required Street Right-of-Way (Excludes State and U.S. Numbered Highways) Street Classification Minimum Required Right-of-Way Width Arterial 120 feet Major collector 100 feet Minor collector 80 feet Local commercial or industrial street 60 feet Local residential street with swale ditches 60 feet Local residential street with curb and gutter 50 feet Local residential street with on-street parking 66 feet
(c) Additional right of way may be required to accommodate turning lanes or other improvements.
(d) In residential subdivisions or land developments, streets that serve 100 dwelling units or more shall be improved to or exceed “minor collector” street standards, while those serving fewer than 100 dwelling units shall be improved to or exceed “local” street standards.
(e) Subdivisions or developments that adjoin an existing street that does not meet the rightof-way width required by this development code for said street as classified, shall dedicate up to one-half of the right-of-way needed to meet the minimum right-of-way width required for the street along the entire property frontage. If any part of a subdivision or land development fronts on both sides of an existing street, all of the rightof-way needed for the existing street to meet the right-of-way standards of this development code for the street shall be dedicated along the entire property frontage.
Sec. 6-304. Planned streets.
When a future street or road, proposed in the comprehensive plan or comprehensive transportation plan, adjoins or traverses a subdivision or development project, the future right-ofway shall be platted as part of the subdivision or development project. No development will be allowed within the platted future right-of-way except for drives and landscaping, and the platted future right-of-way is to be treated as a lot line for the provision of all setback lines as required by this Article.
Sec. 6-305. Continuation of existing streets.
When a new street is proposed within a development or subdivision, the development or subdivision shall provide for the continuation or projection of any existing street adjoining the development or subdivision at the same or greater right-of-way and pavement width. Where, in the opinion of the zoning administrator, it is necessary to provide for street access to adjoining property, proposed streets shall be extended by dedication of right-of-way to the boundary of such property through the development.
Sec. 6-306. Dead-end streets and cul-de-sacs.
(a) Cul-de-sac required. Streets that dead-end shall terminate in a cul-de-sac meeting the requirements of this Article or as approved by the zoning administrator. A dead-end street other than a cul-de-sac shall not be allowed except as a temporary stage of construction of a street that will be extended in a later stage of construction.
(b) Minimum length. A cul-de-sac street shall have a minimum length of at least 125 feet.
(c) Maximum length. The maximum length of a cul-de-sac street shall be 600 feet, unless necessitated by topographic or other conditions and approved by the zoning administrator.
(d) Residential street. Cul-de-sacs in residential subdivisions shall terminate in a circular turnaround having a minimum right-of-way of at least 116 feet in diameter (58-foot radius) and a paved turnaround with a minimum outside diameter of 96 feet (48-foot radius). (see figures below)
Centered Eyebrow Teardrop
(e) Commercial and industrial street. Cul-de-sacs in commercial and industrial subdivisions shall terminate in a circular turnaround having a minimum right-of-way of at least 120 feet in diameter (60-foot radius), and a paved turnaround with a minimum outside diameter of 100 feet (50-foot radius).
(f) Temporary cul-de-sac. Streets that are planned to continue at some future date shall provide a temporary cul-de-sac as required by the zoning administrator. The minimum radius for a temporary cul-de-sac shall be 48 feet. Temporary turnarounds shall consist of 3 inches of graded aggregate base and 1 inch of asphalt. A temporary cul-de-sac shall be made permanent within 12 months if the next phase is not permitted.
Sec. 6-307. Alleys.
(a) Alleys may be required at the rear of all lots used for multi-family, commercial or industrial developments. Alleys may be provided to facilitate rear-access to garages on each lot at the discretion of the subdivider/developer with approval of the zoning administrator.
(b) If alleys are provided, they must be paved. The minimum easement shall be 20 feet in width; the travel way shall be a minimum of 16 feet with 2-foot shoulders on each side (see figure):
Alley Section
(c) If alleys are provided, they must be private and shall not be publicly dedicated.
(d) Dead-end alleys shall be avoided were possible; but if unavoidable, they shall be provided with a turn-around having a radius of at least 40 feet, or a “T-head” turn-around approved by the zoning administrator.
Sec. 6-308. Street alignment and offsets/jogs.
(a) Streets shall be aligned to join with planned or existing streets.
(b) No new street that intersects a State or U.S. numbered highway shall be approved unless there is maintained a separation of at least 800 feet from any other street.
(c) The Georgia Department of Transportation may require a greater separation between streets intersecting a State or U.S. numbered highway.
(d) Other, local, adjoining street intersections shall be spaced at least 250 feet apart measured from edge of right-of-way to edge of opposing right-of-way.
Sec. 6-309. Street intersection angles.
All streets shall intersect at no less than 75 degrees, and as near a right angle as possible.
The angle of intersection is to be measured at the intersection of the street centerlines.
Such intersecting streets shall provide an uninterrupted line of sight from the center point of the intersection for not less than the minimum sight distance required in accordance with this UDC.
Sec. 6-310. Street intersection curb radii.
Turning radii for street intersections shall be provided as follows, based on the highest street classification involved in the intersection as listed below. Where the angle of street intersection is less than 90 degrees, a longer radius may be required.
(a) Arterial: 50-foot radius.
(b) Major collector: 35-foot radius.
(c) Minor collector: 25-foot radius.
(d) Local street: 25-foot radius.
Sec. 6-311. Street grades.
(a) Minimum grades. All streets shall have a minimum grade of 0.5 percent.
(b) Maximum grades and minimum design speeds. Maximum grades and minimum design speeds for proposed streets by street type shall be as required in Table 6-3-2.
Design exceptions must be justified and approved by the zoning administrator.
Table 6-3-2 Maximum Grades and Minimum Design Speeds Street Type Maximum Grade Minimum Design Speed Arterial street 6% 55 mph Major collector street 6% 45 mph Minor collector Street 8% 35 mph Local street 12% 25 mph Alleys 12% 15 mph Sec. 6-312. Horizontal alignment of streets.
Where a deflection angle of more than 5 degrees in the alignment of a street occurs, the radius of curvature of the center line of said street shall be not less than as shown on Table 6-3-3.
Table 6-3-3 Horizontal Alignment of Streets Street Classification Minimum Radius of Curvature of Center Line Arterial street 800 feet Major collector street 350 feet Minor collector street 200 feet Local street 100 feet Curved streets shall have a minimum tangent of 100 feet at intersections as measured from the centerline of cross streets. A tangent of at least 200 feet in length shall be introduced between reverse curves on collector streets, and 100 feet on local streets.
Sec. 6-313. Minimum sight distance.
(a) Sight distance requirements at intersections and driveways shall be as required in Table 6- 3-4. The design speed for sight distance requirements at entrance intersections shall be the existing posted speed limit. Distances shall be measured from a point on the centerline of the entering road or driveway 10 feet back from the edge of the nearest traffic way in the abutting street and extending in both directions along the abutting street. Minimum sight distances shall be measured from the driver’s eyes, which are assumed to be 3.75 feet in height above the pavement surface, to an object 6 inches high on the pavement in the center of every on-coming travel lane. The sight distance shall be clear along its entire minimum length and unimpaired by intervening changes in street grade, horizontal alignment, or obstructions. Examples of obstructions are vegetation, ground cover, signs, existing topography, etc.
Table 6-3-4 Minimum Sight Distance Requirements Design Speed (miles per hour) Distance in Feet (Each Way) 25 125* 30 125* 35 150 40 185 45 230 50 475 55 350 60 450 65 550
* 125’ street spacing for internal residential streets only. Any external non-residential street spacing shall be a minimum of 150’
(b) Minimum sight distance requirements of this section may be designed in accordance with AASHTO’s Geometric Design of Highways and Streets if such standards conflict with the requirements of this Section.
Sec. 6-314. Pavement width and paving specifications.
Roadways shall be constructed and paved with top courses meeting the following standards. The minimum pavement width, measured from edge of pavement to edge of pavement, (or from the inner edge of curb where curbing exists) shall be as required for the street type in Table 6-3-5.
Table 6-3-5 Street Base and Pavement Width Street Classification Width of Pavement Base Binder Topping Arterial, Principal 72 feet Per GDOT Per GDOT Per GDOT Arterial, Major 72 feet Per GDOT Per GDOT Per GDOT Arterial, Minor 48 feet Per GDOT Per GDOT Per GDOT Collector, Major 48 feet 10 inches GAB 3 inches B 2 inches E Collector, Minor 36 feet 6 inches GAB 3 inches B 1½ inches E Local Commercial or Industrial Street 26 feet 10 inches GAB 4 inches B 2 inches E Local Residential Street 22 feet 6 inches GAB 2 inches B 1½ inches E Local Residential Street – On Street Parking (Major Subdivisions) 32 feet 6 inches GAB 2 inches B 1½ inches E GDOT = Georgia Department of Transportation GAB = graded aggregate base.
Note: width of pavement excludes curb and gutter.
Sec. 6-315. Street base.
(a) Graded aggregate base course. The base course shall consist of mineral aggregate and may be a combination of natural deposit or a blend of the materials specified. All materials are subject to approval of the zoning administrator. If a blend of materials is used, it shall be blended through a base plant that meets the latest specifications of the Georgia Department of Transportation Specification 815.
(b) Thickness of material. Street base material shall conform to the thickness as required for the street type (see Table 6-3-5).
(c) Extension. For streets without curbs, the base shall extend at least 1 foot beyond the edge of payment.
(d) Replacement of unsuitable material. Wherever unsuitable material is found in the subgrade, the unsuitable material shall be replaced with graded aggregate stone.
Sec. 6-316. Pavement topping.
(a) Prime. After the base has been placed, mixed, compacted, shaped, inspected and accepted, it shall be primed with suitable asphaltic materials as specified in Department of Transportation Specification 412.
(b) Roadway binder. After the prime has been inspected and accepted, the roadway or street shall be surfaced with Type “B” binder as required for the street type (see Table 6-3-5).
(c) Tack coat. Tack coat shall be applied on a prepared road surface according to the requirements of Georgia Department of Transportation Specification 413.
(d) Final topping. Final topping shall consist of a course of Type “E” asphaltic cement as required for the street type as required (see Table 6-3-5).
Sec. 6-317. Testing requirements for street base and paving.
(a) Tests shall be conducted of street base and paving as per Table 6-3-6.
Table 6-3-6 Testing Requirements and Standards Type of Test to be Performed Minimum Number of Tests Testing Standards Sub-grade Compaction Each 500 linear feet of roadway 95% Max Density
ASTM-1557
Field Tests
ASTM D-1556
F-2922 and D-2167 Base Compaction Each 500 linear feet of roadway 100% Max Density
ASTM-1557
Field Tests
ASTM D-1556
F-2922 and D-2167 Asphalt Density Each 1,000 linear feet of roadway 92% Laboratory Density Asphalt Thickness Each 500 linear feet of roadway Deficient in thickness not more than ¼”
When testing is required, it is the responsibility of the developer to ensure that all required tests are made and reported to the Zoning Administrator for review and approval. The cost of all testing and quality control shall be performed at the expense of the developer by qualified testing laboratories. The developer is also required to repair any defects or damages caused by testing such that the roadway still meets the required standard following repair.
Sec. 6-318. Curb and gutter -- required.
Curb and gutter are required along:
(a) All new commercial and industrial streets;
(b) Existing city streets that abut a subdivision where curb and gutter are required, or abut a multi-family or nonresidential development; and
(c) Deceleration lanes and travel lane widenings on existing city streets.
Sec. 6-319. Curb and gutter -- detail.
(a) Curbs along collectors, local commercial or industrial streets, and residential streets shall be Portland cement concrete, 6-inch x 24-inch x 10-inch vertical type only, with a minimum strength of 3,000 psi at 28 days.
(b) All curbing shall be backfilled. The curb and gutter shall be constructed so as to present a smooth, even line both horizontally and vertically. There shall be no areas of ponding.
Sec. 6-320. Slopes and shoulder improvements.
(a) On streets with curb and gutter, the shoulders shall slope ¼ inch to the foot toward the roadway for at least 7 feet from back of curb, and no more than ½ inch to the foot for the remainder of the right-of way width.
(b) On streets with swale ditch drainage, the shoulders shall slope ¾ inch to the foot away from the roadway for at least 5 feet to the drainage channel. The maximum slope for the drainage channel shall be 2 feet of run for each 1 one foot of fall, with a minimum 2-footwide channel at the bottom of the swale.
(c) Immediately after grading and filling and re-spreading of topsoil, all areas of disturbed soil shall be fertilized and seeded (or in steep areas sodded or otherwise appropriately treated) with suitable vegetative cover to retard erosion.
(d) When all construction is completed, all slopes and shoulders shall be cleared of all rubbish and shall have a stand of grass to prevent undue erosion, either by sprigging or seeding.
Sec. 6-321. Deceleration and turning lanes.
(a) Generally. Access improvements such as deceleration lanes, dedicated left-turning lanes, center turn lanes, merge lanes, signalization, etc., required as deemed necessary for safe traffic operations by the Zoning Administrator shall be installed at all entrance roads into a development or major subdivision. The Zoning Administrator shall use the Georgia Department of Transportation Regulations for Driveway and Encroachment Control, Revision 4.0, dated March 15, 2016, Section 4.9, “Auxiliary Turn Lanes,” as may be amended from time to time, as a basis for determining whether deceleration lanes and other lanes are required; unless otherwise determined appropriate by the zoning administrator, if the DOT driveway regulations would require an improvement if the road were a state route, the Zoning Administrator shall require the same such improvements.
In addition, a deceleration lane shall be required at each street entrance to a multi-family development of 25 or more units, any residential subdivision of 25 lots or more, and any commercial or industrial subdivision.
(b) Length. Generally, deceleration lanes and turn lanes shall be a minimum length of 150 feet, with an additional 50-foot taper length, and a pavement width of 12 feet (exclusive of curb and gutter). Deceleration lanes and tapers may be required to be of greater length, based on the design speed of the road.
(c) Right of way. If needed, additional right-of-way to accommodate the deceleration lane or turn lane and a 10-foot shoulder shall be dedicated by the developer to the city.
(d) Drainage. Associated drainage improvements as deemed necessary by the city by the construction of the deceleration or turn lane shall also be required. The developer will pay the cost of any cross-drain pipe relocations and catch basins that must be constructed along an existing city street as a result of installing a required deceleration or turning lane.
(e) Utilities. Utilities shall be relocated at the developer’s expense outside of a deceleration or turning lane. Waterlines can remain beneath the additional lanes.
Sec. 6-322. Street names and street name signs.
(a) Street names are subject to the approval of the Jackson County E-911 Coordinator (GIS Department) and the zoning administrator.
(b) Proposed public or private streets, which are extensions of, or in alignment with, existing or other proposed streets shall have the same name.
(c) Street names shall not duplicate or be phonetically similar to existing street names.
(d) Street name signs of a type approved by the city are to be placed at all intersections.
Unless otherwise adopted by the zoning administrator, street signs shall be constructed of aluminum sheets with reflective backgrounds. Information on the street name signs shall be readable from both sides of the sign. Signs shall be installed on a steel post. The vertical distance from the road elevation to the bottom of the sign face shall be 7 feet with a minimum burial depth of 3 feet.
(e) Street name signs shall be installed by the city at the developer’s expense or the city shall direct the applicant to install said signs subject to the approval of the zoning administrator.
Sec. 6-323. Traffic signs and striping.
(a) Traffic control signs shall conform to the Manual on Uniform Traffic Control Devices, latest edition. The city shall install required traffic control signs at the subdivider’s or developer’s expense, or the city shall direct the applicant to install said signs subject to the approval of the zoning administrator.
(b) All newly constructed streets having 4 or more lanes (including auxiliary lanes) and existing streets being widened with one or more additional lanes shall be striped or the payment of said striping costs shall be required from the developer by the city prior to the approval of development conformance for the project. Striping shall be accomplished with paint meeting Georgia DOT standards conforming to the Manual on Uniform Traffic Control Devices.
Sec. 6-324. Street lighting.
(a) Required. Street lighting shall be required on all new public and private streets as follows:
1. At any new street intersection, regardless of use;
2. New residential subdivision streets; and
3. New commercial subdivision streets. Streets serving exclusively industrial uses shall not require street lighting except at street intersections.
(b) Standard. Street lighting, when required shall be installed according to design standards of the power company servicing the subdivision or development; provided however, the minimum height of a streetlight shall be 25 feet above the road surface.
(c) Plan approval. The subdivider or developer shall submit a street light layout prepared by the utility company which will provide the lighting service showing the exact location of streetlights within the subdivision. The lighting layout must be approved by the zoning administrator.
(d) Operation cost responsibility. The Commerce City Council will not assume responsibility for the operational costs of streetlights required by this section until the street right of way containing the streetlights has been accepted as a dedicated public right of way.
Sec. 6-325. Traffic calming devices.
All traffic calming devices shall be reviewed and approved by the Zoning Administrator prior to installation.
Sec. 6-326. Private streets.
(a) Private streets, if approved by the city, shall meet all requirements and standards that apply to public streets as specified in this Article and UDC.
(b) Any gate placed across a private street that limits access to a subdivision or development shall provide for unimpeded access by emergency vehicles, governmental vehicles on official business, and public and private delivery services including the U.S. Postal Service. Accessibility to such gated communities shall comply with all standards and requirements of the city for access activation and shall be of breakaway or other construction acceptable to the city.
Sec. 6-327. On-Street Parking for Local Residential Streets.
(a) Required. In addition to off-street parking such as driveways or other designated parking areas, all local residential streets constructed for and/or within major subdivisions shall include on-street parking to accommodate for a minimum of one (1) vehicle for every two (2) residences.
(b) Design. All on-street parking shall be included in the preliminary and final plat which shall be reviewed and approved by the Zoning Administrator prior to installation.
1. Parking shall be designated to one side of the street at a time and shall not extend to both sides of the street within the minimum pavement width (See figure below).
2. Designated parking shall be striped at the cost of the developer.
3. Designated parking shall be evenly dispersed throughout the development.
4. Off-street parking alternatives in addition to residential driveways may replace or supplement required on-street parking subject to review and approval at the discretion of the Zoning Administrator.
Example: On-Street Parking for Local Residential Street
(c) Restrictions and Enforcement. Homeowner’s Association (HOA) covenants must include and enforce restrictions for on-street parking outside of designated areas. Signs shall be erected advising that on-street parking is only allowed in designated areas.
Sec. 6-402. Sidewalk installation waiver.
Sec. 6-401. Sidewalks required.
Sidewalks are required to be installed by the developer at the time of development as follows:
(a) On both sides of all new commercial and industrial streets.
(b) On both sides of streets serving residential subdivisions.
(c) Along the side of existing city streets and roads that abut a subdivision where sidewalks are required, or abut a multi-family or nonresidential development.
Sec. 6-403. Sidewalk placement.
(a) Sidewalks shall be included within the dedicated non-pavement right-of-way of roads and shall parallel the street pavement as much as possible; provided, however, the Zoning Administrator may permit sidewalks to be designed and constructed so that they meander around permanent obstructions or deviate from a linear pattern for design purposes.
Sec. 6-404. Sidewalk construction.
(a) Sidewalks must comply with all requirements of the federal Americans with Disabilities Act.
(b) Concrete sidewalks shall be a minimum of 5 feet wide and 4 inches thick.
(c) Concrete shall be 3,000 psi at 28 days’ strength.
(d) Sidewalks shall be backfilled and any strip between curb and sidewalk planted with grass sod or landscaped as approved by the zoning administrator.
(e) Sidewalk construction within subdivisions may be deferred to the builder. In such instances no certificate of occupancy for a building shall be authorized until said required sidewalk is constructed.
(f) All sidewalks shall be grinded for evenness.
(g) All sidewalks shall follow the outer perimeter of a cul-de-sac.
Sec. 6-501. Driveways and deceleration lanes on state routes.
For subdivisions or land developments accessing state routes, the Georgia Department of Transportation requires a driveway permit and may require the installation of deceleration lanes and/or other improvements per its Regulations for Driveway and Encroachment Control, Revision 4.0, dated March 15, 2016, as may be amended from time to time. Such state approval and driveway permit shall be a precondition of subdivision and development permit approval.
Sec. 6-502. Driveway compliance.
(a) No driveway shall be connected to a city street or county road, and no curbs or medians on public streets or rights-of-ways shall be cut or altered for access unless approved by the Zoning Administrator, Public Works Director, or designee.
(b) No driveway or other improvement constructed on a city street or county road right of way shall be constructed or relocated or have its dimensions altered without the approval of the Zoning Administrator, Public Works Director, or designee.
(c) Driveways must be permitted. Approval of driveways shown on approved development plans shall constitute driveway approval unless specified otherwise in such approval.
Approval of driveways shown on a building permit application shall constitute driveway approval unless specified otherwise by such permit approval. A separate driveway permit shall be required, if the driveway proposed has not been shown on approved development plans or approved as part of a building permit.
Sec. 6-503. Residential driveways.
Residential driveways shall meet the following requirements:
(a) Limitation in number. Residential driveways shall be limited to one per lot, except that a circular driveway with two entrances onto a city street or county public road may be authorized if the driveway connections are separated by 100 feet or more.
(b) Width: 10 feet minimum, except for shared driveways which shall be at least 12 feet wide. A residential driveway shall not exceed a width (measured at the right of way line of the street to which the driveway is connected) of 12 feet, unless the driveway serves a garage or carport designed to park two or more cars located within 40 feet of the right of way, in which case the maximum residential driveway width shall be 20 feet. The maximum driveway widths of this paragraph shall not be construed to prevent additional surfacing for purposes of connecting the driveway to a garage or carport, or for additional uncovered parking, or for additional maneuvering space on the lot.
(c) Spacing from road intersection: Spacing of residential driveways shall be as required for purposes of observing minimum required sight distance, unless specifically approved otherwise as part of final plat approval for a common development or per individual driveway permit.
(d) Locations: Driveways will be restricted to locations where movements into and out of them can occur in a safe and orderly manner, subject to the approval of the zoning administrator.
Source: Florida Department of Transportation. 2008.
Driveway Information Guide.
(e) Angle of intersection with street: Driveway intersection with a street shall be right angled (80 degrees to 100 degrees).
Source: Florida Department of Transportation. 2008.
Driveway Information Guide.
(f) Driveway apron. The installation of concrete driveway aprons at any driveway connecting to a city street or county road are required and shall be constructed per the Georgia Department of Transportation Construction Detail “A1” Driveways with Tapered Entrances Concrete Valley Gutters.
(g) Slope and elevation. Any driveway entering on a roadway or street may be required to be sloped down from the street or roadway at a rate of ½ inch per 1 foot for a minimum of 10 feet. In any case, the finished driveway surface within the right-of-way where it abuts the adjacent road must be no higher in elevation than the roadbed.
(h) Drainage: As a condition of driveway approval, the Zoning Administrator is authorized to require a driveway applicant to install a storm drainage culvert of a size as approved by the Zoning Administrator (18-inch culvert typical where curb and gutter do not exist). All waters from driveways must enter onto the shoulders of adjacent roads and into the ditch or gutter. No water shall be permitted to enter onto the adjacent road surface or pavement.
(i) Sidewalk transitions: Where a sidewalk is provided or planned, the driveway shall be designed and constructed with sidewalk transitions as appropriate.
(j) Sight visibility clearance. With the exception of signposts and other structures less than 8 inches in diameter, structures and landscaping shall not exceed 3 feet in height within a triangle measuring 20 feet along the edge of a driveway and 20 feet along the street rightof-way line.
(k) No access easement. Residential lots in any major subdivision shall have no direct driveway access to a collector or arterial street unless approved by the zoning administrator, or to a State or U.S. numbered highway unless approved by the Georgia Department of Transportation and incorporated into the construction drawings for the project prior to issuance of a development permit by the city. An easement of at least 10 feet in width, across which there shall be no right of access, shall be provided along the entire width of lots in a major subdivision that abut any collector or arterial street.
Sec. 6-504. Nonresidential driveways.
Nonresidential driveways shall meet the following requirements. Driveways serving agricultural properties shall not require compliance with the requirements of this section.
(a) Number. Along any city street or county road, each lot shall be permitted no more than two points of vehicular access to each abutting public road; provided however, that lots with 150 feet of frontage or less shall have no more than one point of access to any one public street. The Zoning Administrator shall determine whether the points of access may be unrestricted or will have to be designed for right-in, right-out traffic flow.
(b) Two-way width: 24 feet minimum and 32 feet maximum.
(c) One-way width: 12 feet minimum and 18 feet maximum.
(d) Spacing from road intersection: Spacing of nonresidential driveways shall be as required by the Zoning Administrator for purposes of observing minimum required sight distance, unless specifically approved otherwise as part of final plat approval for a common development or per individual driveway permit.
(e) Distance from property lines: Curb cuts shall be located no closer than 20 feet from a property line, unless a common access driveway is approved by the zoning administrator, in which case there is no setback from the common property line.
(f) Locations: Driveways will be restricted to locations where movements into and out of them can occur in a safe and orderly manner, subject to the approval of the zoning administrator.
(g) Angle of intersection with street: Right angled (80 degrees to 100 degrees).
(h) Driveway apron. Installation of an asphalt or concrete driveway apron may be required for any nonresidential driveway connecting to a city street or county road. When a driveway apron is required, the minimum driveway radius for a shall be 15 feet for commercial and multi-family residential development and 25 feet for industrial development.
(i) Slope and elevation. Any driveway entering on a roadway or street may be required to be sloped down from the street or roadway at a rate of ½ inch per 1 foot for a minimum of 10 feet. In any case, the finished driveway surface within the right-of-way where it abuts the adjacent road must be no higher in elevation than the roadbed.
(j) Drainage: As a condition of driveway approval, the Zoning Administrator is authorized to require a driveway applicant to install a storm drainage culvert of a size as approved by the Zoning Administrator (18-inch culvert typical where curb and gutter do not exist). All waters from driveways must enter onto the shoulders of adjacent roads and into the ditch or gutter.
No water shall be permitted to enter onto the adjacent road surface or pavement.
(k) Sidewalk transitions: Where a sidewalk is provided or planned, the driveway shall be designed and constructed with sidewalk transitions as appropriate.
(l) Sight visibility clearance. With the exception of sign posts and other structures less than 8 inches in diameter, structures and landscaping shall not exceed 3 feet in height within a triangle measuring 10 feet along the edge of a driveway and 20 feet along the street right-ofway line.
Source: Stover, Vergil G., and Frank J. Koepke. 2002. Transportation and Land Development (2nd Ed.).
Washington, DC: Institute of Transportation Engineers.
(j) Alignment: Non-single-family residential driveways may be required to be aligned with existing or planned driveways on the opposite side of the road.
(k) Additional location restriction: A driveway shall not be allowed along a right-of-way miter.
(l) Additional travel lane. If the centerline of a driveway entrance on a major collector or arterial street is less than 400 feet from the centerline of an intersection, a continuous travel lane shall be constructed by the developer from the intersecting street to the driveway.
Sec. 6-601. Applicability.
This division shall apply to construction of any new parking lot containing 5 or more spaces, and to the expansion of an existing parking lot by 5 or more parking spaces.
Sec. 6-602. Plans and development permit required.
(a) Construction of a new parking lot containing 5 or more spaces, or the addition of 5 or more spaces to an existing parking lot, shall require issuance of a development permit.
(b) To ensure compliance with this Article, parking and circulation plans shall include the number of spaces provided, the minimum parking spaces required, the location of entrances, exits, aisles, curbing where required, landscaping, screening, surface materials, provisions for drainage and other specifications necessary to ensure compliance with this Article.
Sec. 6-603. Vehicular circulation.
Efficient and easily recognized vehicular circulation routes within a development are vital and shall be provided. Internal vehicle circulation shall be designed or redesigned in a manner that avoids conflicts between through-traffic (i.e., traffic flowing into and out of the site) and local traffic (i.e., traffic through parking areas). Interior vehicular circulation shall also be facilitated by the following means:
(a) Considering the entire parcel and its anticipated development, rather than simply a particular project, in formulating and approving access plans;
(b) Avoiding dead-end parking areas;
(c) Visually orienting the driver with a regular, logical system of interior driveways and roadways;
(d) Identifying entrance drives with small entry signs; and
(e) Preventing vehicles from driving across or through designated larger parking areas by placing raised landscaped dividers or walkways between parking aisles.
Sec. 6-604. Backing movements prohibited.
Except for parcels of land serving one-family or two-family dwellings, all areas devoted to offstreet parking shall be so designed such that no vehicle is required to back into a public street.
Sec. 6-605. Distance of parking space from right of way.
Except for parcels of land devoted to one-family or two-family dwellings, no parking space shall be located or accessed directly from a driveway within the first 40 feet of the driveway back from the street right-of-way line.
Sec. 6-606. Improvement setback.
Except for parcels of land devoted to one-family or two-family dwellings, off-street parking areas shall be set back from front, side, and rear property lines by at least 5 feet. Buffer and landscape strips may require larger setbacks. Unenclosed off-street parking for single-family and two-family dwellings and agricultural uses shall not be subject to compliance with this section.
Sec. 6-607. Area per parking space.
Every parking space shall provide a usable, rectangular area at least 9 feet wide by 20 feet long;
provided, however that parking spaces may be reduced in width as specifically authorized in this section.
(a) In parking areas for uses which require 20 parking spaces to be provided, compact parking spaces, with widths of 8.5 feet may be used for employee parking or overflow customer parking areas, but only if the compact parking spaces are clearly marked.
(b) Where authorized to reduce parking space width, no more than 20 percent of the number of parking spaces provided in the entire parking area may be designated compact auto parking.
Sec. 6-608. Demarcation.
(a) Every paved parking space shall be clearly demarcated by lines painted on or otherwise applied to the parking lot surface.
(b) One-way traffic aisles, where utilized, must be clearly marked either with directional arrows on the pavement at each intersection with another aisle, driveway, or street entrance, or by traffic directional signs.
(c) The Zoning Administrator may require the installation of concrete parking “stops” or other improvement to avoid encroachment of a vehicle onto landscaped areas.
Sec. 6-609. Parking space angle aisles and access aisle dimensions.
(a) Access aisles in parking lots serving parking spaces shall be perpendicular (90º) to the access aisle when serving two-way traffic (see figure).
(b) Parking spaces may be permitted with 60-degree or 45-degree angles to the access aisle, if one-way travel is required. Parking space angles less than 45 degrees to the access aisle are not allowed, except where the Zoning Administrator authorizes parking spaces that are parallel to the access aisle.
(c) Access aisle dimensions are required as provided in the following figure:
(d) The intersection of parking aisles with a ring road or other on-site roadway or driveway shall provide adequate intersection sight distance. Parking aisle end islands shall be curbed unless that requirement is waived for water quality purposes or in a rural/ exurban area; painted end islands are ineffective and are generally not permitted. End Islands Preserve Sight Distance Source: Stover, Vergil G., and Frank J. Koepke. 2002. Transportation and Land Development (2nd Ed.). Washington, DC: Institute of Transportation Engineers. Figure 8-15, p. 8-25.
Source: Stover, Vergil G., and Frank J. Koepke. 2002. Transportation and Land Development (2nd Ed.).
Washington, DC: Institute of Transportation Engineers. Figure 8-14, p. 8-24.
Inadequate Sight Distance Due To No Parking Aisle End Islands Sec. 6-610. Parking lot surfacing.
(a) Except as provided otherwise in this section, all off-street parking areas and all access drives for customer, visitor, and employee automobile parking serving uses other than single-family and two-family dwellings and agricultural uses shall be improved with a paved surface consisting of a minimum of a 6-inch graded aggregate base overlaid with a 2-inch Type B binder and a 1½-inch Type E or F asphalt surface.
(b) The Zoning Administrator may authorize other paving materials such as pervious pavers.
(c) The Zoning Administrator or may allow driveway approaches and parking lots to be graveled in rural residential districts and in other zoning districts where water quality effectiveness would be enhanced with use of alternative improvement materials. The Zoning Administrator may also waive paving requirements for developments in institutional, commercial and light industrial zoning districts but such waiver shall not be made for frequently used customer parking or handicapped parking as required by this division.
Sec. 6-611. Curbing.
Curbs meeting city specifications for vertical curbing shall be installed around the periphery of every parking lot, and shall extend along both sides of every access drive between the parking lot and the street or another parking lot or loading area, as applicable; provided, however, that the Zoning Administrator may waive the curbing requirement for unpaved parking areas and in cases where water quality effectiveness would be enhanced with use of infiltration devices, biofiltration swales, and other low impact development techniques in lieu of required curbs.
Sec. 6-612. Parking lot drainage.
Storm water drainage plans, including grading plans, shall be submitted to and approved by the Zoning Administrator as a part of and prior to the issuance of a development permit.
Sec. 6-613. Lighting.
(a) Any lights used to illuminate parking areas shall be arranged, located or screened to direct light away from any adjoining residential uses. “Shoe box” (full cutoff) lighting fixtures on poles shall be utilized for this purpose.
(b) Light poles should be located in landscaped strips. Where this cannot be accomplished, light poles must be placed on a reinforced concrete pedestal to protect them from damage or being knocked over.
Sec. 6-614. Landscaping.
All parking lots subject to compliance with this division must provide landscaping as required by this Article 9 of this UDC. Also, if located in the Highway Corridor Overlay District established by Article 4 of this UDC, additional landscaping requirements apply.
Sec. 6-615. Pedestrian facilities.
On any particular development site subject to this Article, where pedestrian circulation crosses vehicular routes, a change in grade, materials, textures or colors, or appropriate striping or demarcation, shall be provided to emphasize the point of intersection between pedestrians and vehicles and improve its visibility and safety. For instance, brick pavers and other special paving materials can help to distinguish pedestrian walkway surfaces from vehicular access ways.
Illustrative On-site Pedestrian Crossings Source: Marya Morris. Smart Codes: Model Land-Development Regulations. Planning Advisory Service Report No. 566. Chicago: American Planning Association, 2009. Figure 2.3 Except for detached, singlefamily dwellings, pedestrian
access must be provided to individual developments and each establishment within the development. Pedestrian ways shall be well defined, take as direct a path as possible, and they should be separated where practical from automobile access ways. Parking aisle dividers are appropriate locations for pedestrian access facilities.
Direct Pedestrian Travel from Street to Store Front Source: Stover, Vergil G., and Frank J. Koepke. 2002. Transportation and Land Development (2nd Ed.). Washington, DC: Institute of Transportation Engineers. Figure 8-28, p. 8-35.
When multiple buildings are proposed, they shall be linked with on-site pedestrian walkways of at least 5 feet in width. Sidewalks on individual properties must connect to the sidewalk system within public road right-of-way, where such system exists or is planned, and to adjacent parcels when determined to be compatible and required by the zoning administrator.
Sec. 6-701. Off-street parking required.
(a) Permanent off-street parking spaces shall be provided in accordance with the requirements of this Article at the time of the establishment of any use, or erection of any building; of occupancy of a building by a new use; and when any principal building is enlarged or increased in capacity by adding dwelling units, guest rooms, seats, or floor area.
(b) Off-street parking shall be required for any change of use or change of operation that would result in a requirement for more parking than the existing use. Additional parking shall be required only in proportion to the extent of the change, not for the entire building or use.
(c) All required off-street parking areas shall be ready for use, including surfacing as required, prior to occupancy of the property.
(d) Loading spaces, including truck trailer storage spaces, if provided, shall not count toward meeting the minimum off-street parking requirements of this division.
(e) Development within the CBD zoning district shall be exempt from compliance with the off-street parking requirements of this division.
Sec. 6-702. Interpretations.
(a) Fractions. Where a calculation of minimum or maximum parking or loading spaces results in a fraction, the required number of parking spaces shall be construed to be (rounded up to) the next highest whole number of spaces.
(b) Parking space requirement not specified. Where the parking requirement for a particular use is not described in this Article, and where no similar use is listed, the Zoning Administrator shall determine the number of spaces to be provided based on requirements for similar uses, location of the proposed use, the number of employees on the largest shift, total square footage, potential customer use, and other expected demand and traffic generated by the proposed use. At the discretion of a development applicant, a parking generation study prepared by a qualified professional may be submitted to aid the Zoning Administrator in making such a determination; if submitted, it shall be considered by the Zoning Administrator prior to making a determination.
(c) Computations for multiple floor uses within a building. In cases where a building contains some combination of office space, retail or wholesale sales area, and/or bulk storage area, the Zoning Administrator may authorize that the building space be divided into such floor space use areas and combined computations of floor areas (e.g., warehousing, retail, and/or office) utilized in meeting the off-street parking or loading space requirements of this Article.
(d) Maneuvering lanes not considered parking. Areas designated for temporary occupancy of vehicles while maneuvering on a site, such as queuing lanes for a drive-in window, are not considered and shall not be counted as parking spaces for purposes of meeting the requirements of this Article.
Sec. 6-703. Minimum number of off-street parking spaces required.
(a) Reference to requirements table. Unless specifically provided otherwise in this division, on each lot where a building, structure, or use exists, each site shall be designed to provide and shall provide for off-street parking in the minimum amounts specified in Table 6-7-1.
(b) Reduction. No existing or future off-street parking area shall be reduced in capacity to less than the minimum required number of spaces or altered in design or function to less than the minimum standards, unless specifically provided for otherwise in this Article.
Table 6-7-1 Minimum Number of Off-Street Parking Spaces Required
USE MINIMUM PARKING REQUIRED
COMMERCIAL USES
Adult entertainment 1 per 200 square feet Animal hospital; kennel 1 per 400 square feet Appliance sales and repair 1 per 500 square feet Art gallery 1 per 400 square feet Auction house or yard 1 per 300 square feet of building or 1 per 1,000 square feet of open area Automated teller machine, no drivethrough
2 per machine Auto parts store 1 per 500 square feet Automobile sales 1 per 200 square feet of repair space plus 1 per 400 square feet of showroom/office
Automobile service and repair 1 per 250 square feet Bank, credit union, savings and loan 1 per 300 square feet Barber shop or beauty parlor 1 per 300 square feet Bed and breakfast inn 2 for the owner-operator plus 1 per guest bedroom Bowling alley 3 per lane
Carpet or floor covering store 1 per 300 square feet of retail sales and office area, plus if applicable, warehouse requirements for designated storage, receiving, and shipping area
Car wash, staffed or automated 2 stacking spaces for each car wash lane plus 2 drying spaces per lane Contractor’s establishment 1 per 300 square feet of office space and 1 per 2,000 square feet of outdoor storage
Convenience store without franchise food outlet 1 per 200 square feet Convenience store with franchise food outlet 1 per 150 square feet Dance hall 1 per 125 square feet Day care center 1 per 300 square feet Day care center, adult 1 per 400 square feet Dry cleaner 1 per 250 square feet Equipment rental 1 per 300 square feet Farm equipment or supply 1 per 600 square feet Farmer’s market 1 per 250 square feet Flea market 1 per merchant booth plus 1 per 250 square feet of floor or open market area
Funeral home or mortuary 1 per 3 seats in largest chapel or viewing room (15 spaces minimum) Furniture and home furnishing store 1 per 600 square feet
Grocery store 1 per 300 square feet Hardware store 1 per 400 square feet Health or fitness club 1 per 200 square feet Hotel, extended stay 1.5 per unit lodging unit Hotel or motel 1 per lodging unit, plus one per each 150 square feet of banquet, assembly, meeting, or restaurant seating area
Laundromat 1 for each 3 washer/dryer combinations Nursery or garden center 1 per 300 square feet plus 1 per 1,500 square feet outdoor sales or display area
Office, general or professional 1 per 300 square feet Office, medical or dental 1 per 250 square feet Open air sales 1 per 250 square feet of indoor floor space plus 1 per 600 square feet of outdoor sales
USE MINIMUM PARKING REQUIRED
Personal service establishment 1 per 250 square feet Photographic studio 1 per 300 square feet Radio or television station 1 per employee plus 5 spaces Restaurant, bar, or tavern 1 per 100 square feet Retail store (not otherwise listed) 1 per 275 square feet Salvage yard 1 per employee plus 1 per 1,000 square feet of salvage area Self-storage facility (mini-warehouse) See Sec. 3-112
Service station 1 per 250 square feet of office space plus 2 per service bay Shopping center 1 per 275 square feet
Tire store 1 per employee plus 1 per 500 square feet Tow service 1 per employee plus 1 per tow truck plus 2 spaces Truck stop 1 semi-trailer space per 200 square feet Manufacturing, processing, assembling 1 per 1,300 square feet Warehouse or wholesale 1 per 4,000 square feet Airport 1 per employee on the largest shift, plus 1 per 1,000 square feet of terminal space
Amphitheater 1 per 4 fixed seats and/or 1 per 25 square feet of open spectator area Assembly hall; auditorium; nonprofit
club or lodge 1 per 4 seats in room with greatest seating capacity or 1 per 40 square feet in largest assembly area without fixed seating
Church, temple, synagogue and place of worship 1 per 4 seats in room with greatest seating capacity or 1 per 40 square feet in largest assembly area without fixed seating
Community center 1 per 400 square feet Correctional institution 1 per employee plus 1 per 25 inmates Crisis center 1 per 400 square feet Fire and/or emergency medical service station 1 per employee plus 1 per each 3 volunteer personnel + 1 per 200 square feet
Government office 1 per 300 square feet Group home or boarding house 1 per 3 residents or beds Hospital 1.5 per bed Library 1 per 400 square feet Museum 1 per 500 square feet Nursing home 1 per 3 beds Post office 1 per 200 square feet Retirement community 0.75 per dwelling unit 0BSchool 1 per 300 square feet 1BSchool for the arts 1 per 300 square feet 2BSchool, trade or business, or college 1 per 200 square feet
3BRESIDENTIAL USES
4BApartment, one bedroom 1.5 per unit plus 0.1 per unit for guest space 5BApartment, two bedroom 1.5 per unit plus 0.1 per unit for guest space 6BApartment, three bedroom 2 per unit plus 0.2 per unit for guest space 7BBoarding or rooming house or group
home 1 per employee plus 0.5 per rooming unit 8BDormitory, fraternity or sorority house 1 per rooming unit plus 5 spaces 9BHome occupation
Residence within building containing a non-residential use 1 per unit Single family detached or attached (townhouse) 2 per unit Two-family dwelling (duplex) 2 per unit Athletic field 20 spaces per field
USE MINIMUM PARKING REQUIRED
Billiard hall/amusement arcade 1 per 200 square feet Bowling alley 2 per each bowling lane (add parking for billiard hall/ amusement arcade, if provided)
Community center 1 per 300 square feet Golf course 2.5 per hole, plus 1 per 250 square feet of pro shop and/or club house Golf driving range, principal use 0.75 per tee
Ice or roller skating rink 1 per 200 square feet Miniature golf 2 per hole Stadium or sport arena 1 per 12 feet of bench seating Swimming pool – subdivision amenity 1 per 150 square feet of surface water area Swimming pool – public 1 per 125 square feet of surface water area
Tennis or racquet ball court 2 per court Theater, cinema 1 per four fixed seats
AGRICULTURAL/OTHER
Animal shelter 1 per 400 square feet Landfill 1 per employee plus 5 spaces Quarry or extractive industry 1 per employee plus 5 spaces Note: Unless otherwise noted, the parking requirement shall be based on the gross square footage of the building or buildings devoted to the particular use specified.
Sec. 6-704. Minimum number of accessible parking spaces required.
(a) Reference to requirements. Regulations and dimensions for handicapped parking spaces shall be per requirements of the Americans with Disabilities Act (ADA) (Public Law 101-
136) and the Georgia Accessibility Code (Chapter 120-3-20 adopted by the Safety Fire Commissioner). The required number of handicapped accessible spaces, which must be provided on-site, shall be as provided in Table 6-7-2.
Table 6-7-2 Handicapped Parking Requirements Total Required Parking Spaces Minimum Number of Accessible Spaces 1 to 25 1 26 to 50 2 51 to 75 3 76 to 100 4 101 to 150 5 151 to 200 6 201 to 300 7 301 to 400 8 401 to 500 9 501 to 1000 2 percent of total 1001 and over 20 plus 1 for each 100 over 1000
(b) Part of overall requirements. Said spaces shall count toward the requirements for offstreet parking as specified in Table 6-7-1.
(c) Aisle specifications and van accessibility. Handicap accessible parking spaces shall have an adjacent aisle 5 feet wide. If 8 or more handicapped spaces are required, then one in every 8 handicapped spaces shall be adjacent to an aisle 8 feet wide and the space shall be signed “van accessible.” For van spaces, the width of the parking space shall be at least 11 feet. Handicapped parking space aisles shall be clearly demarcated by lines painted on or otherwise applied to the parking lot surface.
(d) Surface slope. Handicap accessible parking spaces shall be located on a surface with a slope not exceeding 1 vertical foot in 50 horizontal feet (1:50).
(e) Ramps. Wheelchair ramps shall be provided in accordance with applicable specifications at locations appropriate to normal travel routes from the parking lot to the principal use.
(f) Signage. Accessible parking spaces shall be designated as reserved by a sign showing the symbol of accessibility, per applicable state law requirements. Such signs shall be located so that they cannot be obscured by a vehicle parked in that space.
Sec. 6-705. Administrative variances.
(a) Upon application and for a fee as determined appropriate by the City Council, the Zoning Administrator may authorize an administrative variance to reduce minimum required parking to a rate of no more than 20 percent below the minimum required, based upon the scale and impacts of the request, for good cause shown.
(b) The Zoning Administrator may require an applicant for administrative variance to include documentation from an acceptable industry publication (e.g., Institute of Transportation Engineers, Urban Land Institute, American Planning Association, etc.) or a study prepared by a qualified professional that documents parking demands.
(c) In approving administrative variances to the reduce the minimum parking requirements of this division, the Zoning Administrator may as a condition of approval require certain area on the same lot to be reserved or set-aside for additional parking area for future use if needed.
Sec. 6-706. Stacking spaces for drive-through facilities or service windows.
Stacking spaces shall be provided for any use having a drive-through facility or areas having drop-off and pick-up areas in accordance with this section.
(a) Stacking spaces shall begin at the window or communication/mechanical device (e.g., order board) first encountered by the vehicle user. Financial institutions with drivethrough windows, car washes (automated or staffed facilities), drive-through coffee sales facilities, and any other uses with drive-through facilities shall provide 3 stacking spaces for each window or drive-through service facility. Restaurants with drive-through facilities shall at least provide 5 stacking spaces for each window or drive-through service facility.
(b) Stacking spaces and lanes for drive-through stations shall not impede on- and off-site traffic movements, shall not cross or pass-through off-street parking areas, and shall not create a potentially unsafe condition where crossed by pedestrian access to a public entrance of a building.
(c) Drive-through lanes shall be separated by striping or curbing from off-street parking areas. Individual lanes shall be striped, marked, or otherwise distinctly delineated.
(d) All drive-through facilities shall be provided with a bypass lane with a minimum width of 10 feet, aside the drive-through lane.
(e) Approach lanes for drive-through facilities shall be provided with a bypass lane with a minimum width of ten (10) feet.
(f) Alleys or driveways in residentially zoned areas adjacent to drive-through facilities shall not be used for circulation of customer traffic.
(g) Each stacking space shall be a minimum of ten feet by 20 feet.
(h) The number of stacking spaces shall be provided as follows:
Activity Type Minimum Stack Measured From Automated teller machine 3 per machine Teller Machine Bank teller lane 3 per lane Teller or Window Car wash stall, automatic 6 Entrance Car wash stall, self-service 1 Entrance Convenience store drivethrough Prohibited Gasoline Pump Island 20 feet from each end of the pump island Restaurant, drive-through 6 Order Box. Stacking for at least 4 of the 6 vehicles shall be provided between the order box and pick-up window.
Other Determined by the Zoning Administrator Sec. 6-707. Shared use of parking spaces.
The parking spaces provided for separate uses may be combined in one parking lot but the required spaces assigned to each use may not be assigned to another use, except as follows:
(a) Shared parking between day and night users. One-half of the parking spaces assigned to a church, theater, or assembly hall whose peak attendance will be at night or on Sundays may be assigned to a use that will be closed at night or on Sundays.
(b) Mixed use developments. Parking spaces may be shared by more than one use if the Zoning Administrator finds that the total number of spaces will be adequate at the peak hours of the uses they serve. The ratios shown on Table 6-7-3 may be used in determining the time of day and the day of the week at which the maximum number of spaces will be needed by the uses served by the shared parking facility.
Table 6-7-3 Percentage of Parking Spaces Demanded by Time Period Use Weekdays Weekends Night 6 a.m. to 5 p.m.
5 p.m. to 1 a.m.
6 a.m. to 5 p.m.
5 p.m. to 1 a.m.
1 a.m. to 6 a.m.
Office 100% 10% 10% 5% 5% Retail 60% 90% 100% 70% 5% Hotel 75% 100% 75% 100% 75% Restaurant 50% 100% 100% 100% 10% Entertainment/ Recreation 40% 100% 80% 100% 10% Church 10% 25% 100% 100% 10% Medical 80% 20% 10% 10% 10% By way of example, the following illustrates shared parking calculations for a particular mixed-use development:
Factor For Spaces Office 3.5/1,000 100,000 sf 350 Retail 5/1,000 1000,000 sf 500 Hotel w/Restaurant 1.5/Room 100 rooms 150 Family Restaurant 9.5/1,000 20,000 sf 190 Theater ¼ seats 200 seats 50 Church ¼ seats 400 seats 100 Total If figured separately 1,340 Spaces required applying the peak demand percentages to the example:
Weekdays Weekends Nighttime 6am-5pm 5pm-1am 6am-5pm 5pm-1am 1am-6am Office 350 35 35 18 18 Retail 300 450 500 350 25 Hotel w/Restaurant 113 150 113 150 113 Family Restaurant 95 190 190 190 19 Theater 20 50 40 50 5 Church 50 50 100 100 10 Total 928 925 978 858 189 Highest demand = 978 (instead of 1,340)
(c) Availability of shared spaces. Parking spaces that are proposed to be shared among two or more uses must be clearly available to each use and not appear in any way to be serving a particular use, either through signage dedicating the spaces or through design techniques that would tend to orient use of the spaces to a particular business or building.
(d) Recordation of shared parking agreement. Shared parking arrangements must be committed to writing in an instrument acceptable to the Zoning Administrator and approved by the owners of each of the affected properties or uses. The instrument must be recorded with the Clerk of Superior Court, and a copy of the recorded document must be supplied to the zoning administrator.
Sec. 6-708. Reduction for demand management.
(a) The Zoning Administrator may in individual cases administratively authorize a proportional reduction in the required minimum number of parking spaces for office, institutional, industrial, and public uses with 50 or more employee parking spaces, if a formal carpool or van pool program is instituted.
(b) For purposes of this section, carpool is defined as 2 or more persons per car, and vanpool is defined as 5 or more persons per van. Any carpool or vanpool program shall provide at least 5 spaces reserved for carpool or vanpool vehicles and shall be clearly marked “Reserved – Carpool/Vanpool Only” through signage or pavement markings.
(c) Designated carpool/vanpool spaces shall be the closest employee parking spaces to the building entrance normally used by employees, except for any handicapped parking spaces provided.
Sec. 6-801. Off-street loading required.
(a) On the same lot with every building, structure or part thereof, erected or occupied for manufacturing, storage, warehouse, truck freight terminal, department store, wholesale store, grocery supermarket, hotel, hospital, mortuary, dry cleaning plant, retail business, or other uses similarly involving the receipt or distribution of vehicles, materials or merchandise, there shall be provided and maintained adequate space for the standing, loading, and unloading of such materials to avoid undue interference with public use of streets, alleys, and private or public parking areas. Source: Stover, Vergil G., and Frank J. Koepke. 2002.
Transportation and Land Development (2nd Ed.). Washington, DC:
Institute of Transportation Engineers. Figure 10-5, p. 10-9.
(b) Development within the CB zoning district shall be exempt from compliance with the off-street loading requirements of this division.
Sec. 6-802. Minimum number of on-site loading spaces required.
(a) One off-street loading space shall be provided for the first 10,000 square feet of gross floor area or fractional part thereof for light industrial use and one off-street loading space for the first 5,000 square feet of gross floor area or fractional part thereof for retail or other non-industrial use for which a loading space is required.
(b) One additional space shall be required for each additional 25,000 square feet of gross floor area or fractional part thereof for light industrial use and for each additional 10,000 square feet for retail or other non-industrial use.
Sec. 6-803. Location of loading spaces.
Loading areas shall be located to the rear of the building, unless site design precludes a rear location, in which case loading shall be to the side of a building.
Sec. 6-804. Loading area specifications.
Unless otherwise approved by the zoning administrator, loading spaces shall be a minimum of 14 feet wide, 40 feet long, with 14 feet of height clearance. When the development requires loading and unloading by full-size tractortrailers, loading spaces and access apron shall be a total of 155 feet.
Sec. 6-805. Permanent Reservation.
Area reserved for off-street loading in accordance with this ordinance must not be reduced or changed to any other use unless the permitted use that the off-street loading serves is discontinued or modified. However, equivalent loading space may be provided and approved by the zoning administrator.
Sec. 6-806 . Administrative variance.
The Zoning Administrator is authorized to modify the loading area specifications of this division and reduce or waive off-street loading space requirements for good cause shown, after application for administrative variance.
Article 7 Development Permitting
ARTICLE 7
DEVELOPMENT PERMITTING
DIVISION I DEVELOPMENT PERMITTING
DIVISION II UTILITIES
Sec. 7-101. Land development permitting overview.
There are two types of permits that are required to proceed with land development in the city (unless exempted from such requirements by this UDC): a land disturbance permit, and a development permit.
(a) Land disturbance permit. The land disturbance permit is required and issued by the city pursuant to the Soil Erosion and Sedimentation Control Act. The review process is addressed specifically by the Georgia Department of Natural Resources, Environmental Protection Division. The procedures for filing for a land disturbance permit are specified in Article 8 of this UDC. Any land disturbance permit also requires a development permit if the work involves installation of utilities, paving, and building.
(b) Development permit. The development permit is issued by the Zoning Administrator to ensure that land development activities comply with the city’s zoning, overlay, and other provisions of this UDC. The procedures for filing for a development permit are specified in this Article. When a land disturbance permit is required, the procedures for issuing a development permit are coordinated therewith.
(c) Work within city right of way. When utility installation, utility connection or a driveway is proposed within any city right of way, independent of other land development such that no land disturbance permit or development permit is required, a separate driveway permit and/or utility encroachment permit specified in this Article shall be required. Proper permits must be obtained from Jackson County if such work occurs within a County right of way.
Sec. 7-102. Requirement to obtain a development permit.
(a) Unless specifically exempted by this division, a development permit shall be required prior to commencing any land development or improvement on private land, including building. A development permit shall be required to be issued to authorize all activities, unless specifically exempted, associated with development activity regulated by this UDC, including, but not limited to, clearing and grubbing, grading and the construction of such improvements as streets, surface parking areas and driveways, storm water drainage facilities, sidewalks, or other structures permanently placed on or in the property except for buildings, signs, or other structures requiring the issuance of a building permit.
(b) It shall be unlawful for any person to commence or proceed with land development or land-disturbing activity until development plans are approved and a land disturbance permit, if required by Article 8 of this UDC, and development permit, if required by this Article, is issued by the zoning administrator.
Sec. 7-103. Exemptions from development permit.
A development permit shall not be required for any of the following activities; provided, however, that such exemption from a development permit does not necessarily imply exemption from obtaining a land disturbance permit (see Article 8 of this UDC).
(a) Work authorized by or conducted pursuant to the requirements or directives of local, state, and federal departments, agencies and authorities.
(b) Emergency work authorized by the zoning administrator, where a bona fide emergency exists.
(c) Timber harvesting, consistent with the requirements of this UDC, and forestry activities.
(d) Agricultural activities not involving construction of a building or structure.
(e) Construction of one single, detached, single-family dwelling unit or manufactured home (where permitted), including accessory structures and uses, on a given lot of record.
(f) Development within a city right of way (other than work within a right of way associated with approved development plans) but only if a driveway permit or utility encroachment permit has been issued as required by this UDC.
(g) The Zoning Administrator may authorize an additional exemption from the requirement to obtain a development permit for activity on a lot of record that is no more than two acres, when it can be confirmed without the need to prepare plans in accordance with this division, that the proposed activity complies with all applicable UDC requirements.
Sec. 7-104. Pre-application.
An applicant for a development permit is strongly encouraged but not required to schedule a preapplication meeting with the zoning administrator. Such meeting may also be attended by other review agencies as appropriate. Where other agencies are not represented at the pre-application meeting, a development permit applicant is encouraged to seek advance comments from internal and external agencies with jurisdiction over the development proposal.
Sec. 7-105. Application for development permit.
An application for a development permit shall include the following, as applicable; completed applications shall be submitted to the zoning administrator. Unless otherwise specified by the zoning administrator, all plans are to be submitted electronically and in hard copy.
(a) Application for land-disturbance permit. Unless exempt from the requirement to obtain a land-disturbance permit, the application for development permit shall contain or provide reference to the application for land disturbance permit.
(b) Application form. An application form with information specified by the zoning administrator. Said application form may include but is not limited to name of applicant and contact information, owner and contact information, name of project with location information, proposed source of water service and sewer or septic tank, the name of the professional designer, and the proposed use of the development. The application must be authorized by the property owner.
(c) Development name. The name of each development project must have the approval of the zoning administrator. The name shall not duplicate nor closely approximate the name of an existing subdivision or development project in Jackson County or any of its cities.
(d) Address. Provide an address for the site, if already assigned. If not assigned, contact the Jackson County E-911 coordinator (GIS Department) to obtain an address.
(e) Checklist(s). A checklist for development permit application submissions, as may be provided by the zoning administrator.
(f) Fees. Payment of any development permit fee, and any associated fees, as established from time to time by the Commerce City Council.
(g) Water and sewer availability. The Zoning Administrator may require evidence of water and sewer availability and this requirement in turn may necessitate pre-payment of water or sanitary sewer capacity for the project.
(h) Plan sets. All development plans shall contain sheets for the following, as applicable:
1. Plat. A copy of the approved recorded plat of the subject property, demonstrating that the property to be developed is a lot of record or part of a lot of record. If land subdivision is proposed or implied in the development proposal, a proposed subdivision plat may be required to be submitted with the development permit application, or the process of subdivision may be authorized by the Zoning Administrator to be deferred until a later stage of the development process.
2. Site plan. A site plan, including at minimum the project location, total project area, natural features of the site (e.g., streams, drainage ways, significant vegetation, etc.)
and proposed development features as required by this UDC, including easements.
3. Phases. Proposed phasing of the development, if it is proposed to be built in phases or sections.
4. Grading plan. Grading plans as required and specified in this Article.
5. Soil erosion plans. Soil erosion plans are submitted as part of the land disturbance permit application. If a project is exempt from the requirement to obtain a land disturbance permit, the development permit application shall provide soil erosion plans sufficient to demonstrate compliance with best management practices and stream buffers.
6. Stormwater management plan. Stormwater management plans are submitted as a part of the land-disturbance permit application.
7. Tree protection and landscaping plan. All information and plans required by this UDC, as may be applicable.
8. Utilities plan. Plans for water, sanitary sewer, and other utilities as may be required by the Zoning Administrator and utility provider.
9. Street improvement plan. If the development proposes new streets, whether public or private, or if this UDC requires improvement of a city street, the development permit application shall include information demonstrating compliance with the requirements of this UDC for the improvement of abutting city streets.
10. Other. Other information may be specified by the zoning administrator, as may be necessary to review the development plan and ensure compliance with this UDC.
Sec. 7-106. Professional preparation of plans.
All development plans and supporting studies shall be prepared by or under the supervision of a professional engineer or by another professional as more specifically required by this UDC for the type of plan submitted.
Sec. 7-107. Development plan specifications.
Development plans shall contain the following (on one or more sheets), unless otherwise approved by the zoning administrator:
(a) Scale. Plans shall be clearly and legibly drawn at an engineering scale convenient to illustrate the details of the project. Sheet size shall not exceed 36 inches by 42 inches.
Plan and profile sheets, if any, shall have a horizontal scale of no less than 1 inch to 100 feet and a vertical scale of no less than 1 inch to 10 feet. The Zoning Administrator may approve deviations from these required scales when appropriate.
(b) Project boundary. Plans shall be based on the boundaries of a lot as shown on a recorded plat, or if not yet subdivided and recorded, on a boundary survey delineating the entirety of the property contained within the project. Boundary lines of the perimeter of the tract shall be indicated by a heavy line giving lengths to the nearest one-hundredth of a foot and bearings to the nearest second.
(c) Adjoining property information. Provide all adjoining property owners, subdivision names, lot numbers, lot lines, and block letters, and zoning districts for adjoining properties.
(d) Project name and phase. The name of the project shall be indicated. If the project is located within a subdivision, the name of the subdivision, lot, and block number must also be shown. If the development project is part of a phased development or masterplanned development, identify the unit number, division, phase, or stage of development.
(e) Zoning and prior approvals. The existing zoning district and if applicable overlay district of the project site, and reference if applicable to conditions of zoning, variance, special use, or other permissions including case numbers and dates of approval.
(f) Owner and developer. Name, address, telephone number, and e-mail address of the owner of record, and of the developer (if not the owner).
(g) Professional contacts. Name, address, and telephone number of each professional firm associated with the site development plans (engineer, landscape architect, etc.).
(h) Map requisites. Date of survey, north point, and graphic scale, source of datum, date of plan drawing, and space for revision dates.
(i) Use. Proposed use of the site, including gross square footage for each different use type or building.
(j) Location references. Location, district, land lot(s) and parcel(s) acreage or area in square feet.
(k) Location sketch. A location sketch showing the development site in relation to the surrounding area with regard to well-known landmarks such as major thoroughfares or railroads. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, but not less than 1 inch equal to 2,000 feet. U.S. Geological Survey quadrangle maps may be used as a reference guide for the location sketch.
(l) Buildings, access, and parking. Size, location, and ground elevation of all proposed buildings and existing buildings to remain or to be demolished, and minimum required building setback lines, the location of parking and loading areas, driveways, curb cuts and where required designated fire lanes. Each building shall be identified with a number or letter. See Article 6 of this UDC for access, driveway, and parking requirements.
(m)Topography and grading. Existing contour lines based on sea level datum shall be drawn at intervals of not more than two (2) feet and shall include the entire site and all abutting public streets. Contour lines shall be based on field surveys or photogrammetric methods from aerial photographs. The basis for the topographic contour shown shall be specified and dated. Grading plans shall show proposed contours. Grading shall be performed in accordance with the lines and grades indicated on the approved grading plan.
(n) Natural features within the proposed development. These include drainage channels, bodies of water, and other known significant features such as extensive exposed rock. On all water courses the direction of flow shall be indicated. The 100-year floodplain shall be delineated and the source of the depicted floodplain information shall be indicated (i.e., reference to map panel numbers and dates). The acreage or area in square feet within the floodplain shall be indicated. See Article 11 of this UDC for additional requirements when development is proposed to be located in a floodplain or flood hazard area.
(o) Man-made features. These include those features existing within and adjacent to the proposed development including existing right-of-way width and pavement widths of adjoining streets, street names, the location and dimensions of existing bridges, easements (all purposes), culverts and other drainage facilities, water, sewer, and other existing utility lines and structures, the names of jurisdiction lines; existing structures on the site and their disposition, and other appropriate built-environment information.
(p) Trees, buffers, landscaping. If buffers or other landscaping or screening treatments are required, show the location, size, and type (natural or planted) on the plans conforming to the requirements of this UDC, as applicable.
(q) Utilities and other easements. Easements for water and sanitary sewer as may be required by the utility provider with jurisdiction.
(r) Standard drawings. The Zoning Administrator may require that the development plans include standard drawings if adopted by the city, or a standard drawing of any utility provider with jurisdiction over the development project. Where no standard drawing is available but is needed as determined by the zoning administrator, the applicant’s engineer or designer shall provide any such standard drawing requested, or Jackson County standard drawings shall be used.
(s) Signature blocks. The Zoning Administrator may require signature blocks with pertinent information to be signed by the owner/developer, the plan preparer, a utility provider, an external agency, and approval block for signature by the zoning administrator.
(t) Additional information. Other information as may be specified by the zoning administrator, as may be necessary to review the development plan and ensure compliance with this UDC.
Sec. 7-108. Completeness check.
(a) The application shall be checked for completeness within 10 business days of submission. Incomplete applications will not be processed.
(b) If all documents and plans are not submitted, the development plan application will not be reviewed.
(c) The Zoning Administrator will notify the applicant of any deficiencies and will advise the applicant on what is needed to complete the application and initiate review.
Sec. 7-109. External reviews of development plans.
The applicant shall be responsible for obtaining approvals from all other agencies with regulatory jurisdiction over the project. Accordingly, the applicant may be required by the Zoning Administrator to secure development approval from other agencies with regulatory jurisdiction. Plans shall be submitted by the applicant to these external agencies, for comments and approvals (the Zoning Administrator is not responsible for that function). Approval by the external agency is to be communicated to the zoning administrator. The applicant shall work directly with each external agency as necessary to resolve all issues to receive that agency’s approval.
(a) Environmental Protection Division or Soil and Water Conservation District.
Development plans which include a land disturbance permit application require the review of soil erosion and sedimentation control plans by either the Environmental Protection Division or the Soil and Water Conservation District (see Article 8 of this UDC). Such reviews are coordinated by the zoning administrator.
(b) Georgia Department of Transportation. If the development is on a state highway, also make application directly to the Georgia Department of Transportation district office with jurisdiction, following that agency’s procedures for driveways and encroachments.
(c) Environmental health. If the development is to be served by on-site sewage disposal system, also make application directly to the Jackson County Environmental Health Department following that agency’s procedures.
(d) Non-city utility provider. If the development is served by a utility provider other than the city, also make application directly to that agency following that agency’s procedures.
The Zoning Administrator is not responsible for delays in approval of development plans when a development permit applicant is required to be approved by an external agency but has not obtained approval from that external agency with jurisdiction over the development proposal.
Sec. 7-110. Development permit application processing.
(a) Administrative procedures. The Zoning Administrator is authorized to establish and modify administrative procedures regarding the development plan review administrative process to provide for expeditious decision making and to ensure fairness in the process.
(b) Time frame. Decisions on development permits shall be issued by the Zoning Administrator within 40 calendar days of the city’s notice of plan application completeness. This time period contemplates an applicant simultaneously completes external agency permitting processes.
(c) Criteria for decisions on development permit applications. The Zoning Administrator shall review the application for compliance with the following criteria, which shall not be limiting:
1. Development code and zoning conditions. Development plans must be consistent with all applicable Articles and sections of this UDC, and any conditions of zoning, special use, or variance approval, if applicable.
2. Previously approved plats and plans. When property to be developed is included on an approved final plat, master plan, or other plan approved by the city, development plans shall be in substantial accordance with said plat or plan as determined by the zoning administrator. Significant departures from any such requirements may require the resubmission of plat, master plan, or other plan previously approved, as determined by the zoning administrator.
3. Usability or variance. The Zoning Administrator may not approve any development permit application or plan that shows a lot or situation that would clearly require a variance in order to be reasonably usable, whether due to the presence of flood plain, unusual configuration, zoning compliance, lack of public utilities, or for any other reason.
(d) Noncompliance. If the development permit application and plans are found to not comply with the requirements of this UDC, the Zoning Administrator shall indicate on the drawing or in writing all comments related to lack of compliance with this UDC. The Zoning Administrator shall deny or withhold approval of the development permit application in cases where the proposed development does not meet the requirements of this UDC or the comments of any other internal or external agency with jurisdiction to review the development permit application.
(e) Revisions. Development plan applications shall be revised and resubmitted to accommodate the comments by review agencies and those issued to the applicant by the zoning administrator. If revisions are not resubmitted within a time frame specified by the zoning administrator, the application will be denied. Plan drawings that are submitted for revision must specifically identify those areas that are to be considered for review and approval. The revisions shall be noted in tabular form in a revision block on the plan drawings.
(f) Compliance and approval. When the Zoning Administrator has determined that the development permit application complies with the requirements of this UDC, it will be approved.
Sec. 7-111. Pre-construction meeting and acknowledgment memorandum.
When development plan sets have been approved, the Zoning Administrator shall provide his/her signature, and retain two sets and return two sets to the applicant. The property owner may be required to sign a pre-construction memorandum acknowledging receipt of approved development plans and responsibilities of the property owner and applicant, including but not limited to calls for development inspections.
Sec. 7-112. Permit issuance and posting.
When a development permit is issued, it shall be assigned a number by the zoning administrator, and the applicant shall be supplied a development permit which must be posted on the development site prior to commencement of any land disturbing activity. The development permit shall be posted in a conspicuous place so that they will be visible from the roadway providingfrontage.
Sec. 7-113. Duration of development permit.
(a) Expiration. A development permit shall remain in effect for a period of six consecutive months after which time the permit and plans will become null and void and a new permit will be required if no development activity has begun and has been diligently pursued.
(b) Suspension or revocation. A development permit may be suspended, revoked or modified, as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in title is not in compliance with the approved erosion and sedimentation control plan or that the holder or his successor in title is in violation of this
UDC.
Sec. 7-114. Authority to investigate and inspect, right of entry.
(a) The Zoning Administrator, Building Official, or designee shall have the power to conduct such investigations as it may reasonably deem necessary to carry out duties as prescribed in this chapter, and for this purpose to enter at reasonable time upon any property, public or private, for the purpose of investigating and inspecting the sites of land-disturbing and development activities.
(b) No person shall refuse entry or access to any authorized representative or agent of the city or state environmental protection division who requests entry for the purposes of inspection, and who presents appropriate credentials, nor shall any person obstruct, hamper, or interfere with any such representative while in the process of carrying out his official duties.
Sec. 7-115. Development inspections.
Inspections are required for each of the following phases, as applicable to the actual work to be performed under the development permit:
(a) Erosion and sedimentation control. Required erosion and sedimentation control measures must be installed in accordance with the approved soil erosion and sedimentation control plan prior to any development activity and as development progresses. Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, inspection of erosion and sedimentation control measures and protective devices for undisturbed areas shall be required. Inspection of erosion and sedimentation control measures will be conducted on a continuing basis.
(b) Stormwater facilities. Construction of the stormwater system shall be initiated as part of the grading of the site. Storm water detention facilities shall be constructed prior to the installation of any other site improvements, and may be utilized under proper design as sedimentation basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and ditches, shall be coordinated with the construction of streets and other site improvements, as appropriate. Upon installation of storm drainage pipe, detention, or other storm water facilities, inspection and approval shall be required prior to continuation with subgrade preparation.
(c) Grading. Upon completion of street grading, if applicable, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.
(d) Street curbing and gutter (if provided). After grading is completed and approved, the curb lines shall be staked by the developer’s registered land surveyor. Inspection shall be requested after the subgrade is compacted and forms or string line have been set. Street width and vertical and horizontal alignment may be spot checked.
(e) Sub-grade of streets. After the earth work has been completed, all storm drainage and other underground utilities have been installed under the roadbed, and the backfill in all such ditches thoroughly compacted, the subgrade shall be brought to the lines, grades and cross section shown on the plans. If any sections of the subgrade are composed of unsuitable or unstable material, such material shall be removed to the depth directed by the Inspector and replaced with suitable, thoroughly compacted material. Prior to placement of the street base, the subgrade shall be compacted to 95% density. Testing for sub-grade compaction will be required, including two tests at each sanitary sewer manhole.
(f) Utilities. Before any street base is applied, all of the underground utilities—water mains, sewer mains, gas mains, or any other underground utilities, and all service connections related thereto, that will be located under the street base shall be installed completely and provided throughout the length of the street and across the flat section. If a public water system is to be installed, the improvements are to be reviewed, approved and inspected by the water provider.
(g) Street base. The base shall be string-lined for depth and crown. The street base shall be roll-tested with an 18-ton tandem dump truck and shall pass to the satisfaction of the Inspector. When testing is required by the Inspector, it is the responsibility of the developer to ensure that all required tests are made and reported to the Inspector. The cost of all testing and quality control shall be performed at the expense of the developer by qualified testing laboratories. If deemed necessary by the inspector, additional tests will be required.
(h) Paving. The inspector shall be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored and the street will be cored after completion to check thickness and density. Satisfactory test results of the cores shall be delivered to the Zoning Administrator and utility provider (where utilities are involved) prior to approval of a final subdivision plat if applicable.
(i) Tree protection and landscaping. Inspections for tree protection measures and the installation of landscaping are required.
(j) Final. A final inspection of the development, once complete, shall be required.
Sec. 7-116. Field changes.
(a) After issuance of a development permit, if changes are desired or made necessary as a result of field conditions, the design engineer must contact the Zoning Administrator to coordinate the review and approval of the requested revision.
(b) All field changes shall be documented as revisions to the approved development plans and correctly shown on as-built surveys.
(c) Discrepancies between as-built surveys and approved development plans shall be corrected as required by the Zoning Administrator and may result in delays in approving final plats, building permits or certificates of occupancy.
Sec. 7-117. Reference to specifications.
Where this UDC establishes specifications to be followed, said specifications shall be met, where applicable. The following regulations and manuals are hereby adopted (as may be amended from time to time), and development shall be consistent with them, as applicable, unless otherwise approved by the zoning administrator.
(a) On-site sewage management. Georgia Department of Public Health, Environmental Health Section, Manual for On-site Sewage Management Systems, revised January 2016.
(b) Soil erosion control. Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil and Water Conservation Commission.
(c) Stormwater management. Georgia Stormwater Management Manual: Volume 1: Local Government Guide (2016 Editions); Volume 2: Technical Handbook (2016 Edition); and Volume 3; Pollution Prevention Guidebook (2012).
(d) Surveys. Georgia Administrative Code Department 180, State Board of Registration for Professional Engineers and Land Surveyors, Chapter 180-7, Technical Standards for Property Surveys.
(e) Access management. Georgia Department of Transportation Regulations for Driveway and Encroachment Control, Revision 4.0, dated March 15, 2016.
(f) Utility encroachment. “Utility Accommodation Policy and Standards,” promulgated and published by the Georgia Department of Transportation Division of Operations, Office of Utilities, dated 2016, and as may be amended from time to time.
(g) Traffic control. Manual on Uniform Traffic Control Devices, latest edition, published by the Federal Highway Administration of the U.S. Department of Transportation.
(h) Landscaping. ANSI 300 Standards: The generally accepted (consensus) industry standards for tree care practices, developed by the Tree Care Industry Association and written by a committee called the Accredited Standards Committee A300. These standards are based on current research and sound practice for writing specifications to manage trees, shrubs, and other woody plants.
Sec. 7-118. Disclaimers.
(a) No transfer of responsibility. Approval of development plans by the city shall not imply or transfer acceptance of responsibility for the application of the principles of engineering, architecture, landscape architecture or any other profession, from the professional, corporation or individual under whose hand or supervision the development plans were prepared. The completion of inspections and authorization for work continuation shall not transfer responsibility for the quality of the work performed or materials used from the owner, nor imply or transfer acceptance of responsibility for project design or engineering from the professional, corporation or individual under whose hand or supervision the development plans were prepared.
(b) No waiver of compliance. No development permit issued by the Zoning Administrator shall be interpreted to relieve any owner of the responsibility of maintaining full compliance with all applicable codes, ordinances and other regulations. Any development permit issued in error or in contradiction to the provisions of this UDC shall be considered to have been null and void upon its issuance.
(c) No liability for damage. The approval of plans under the provisions of this Article and the issuance of a development permit shall not relieve any person from the responsibility for damage to any person or property otherwise imposed by law, nor shall such plan approval or development permit issuance impose any liability upon the city for damage to any person or property.
Sec. 7-119. Development permit modifications.
(a) If modifications are requested to an approved development permit, the Zoning Administrator shall determine whether the modification is a major change or a minor change.
(b) For major changes, the applicant shall be required to submit plans and follow the procedures of this chapter to obtain a new (modified) development permit.
(c) For changes deemed to be minor, the Zoning Administrator may charge a fee for minor development permit revisions specified in a fee schedule adopted by the Commerce City Council.
Sec. 7-120. Noncompliance and enforcement.
(a) Warning and written notice to comply. If, through inspection, it is deemed that a person engaged in land-disturbing or development activities has failed to obtain the required development permit, or has failed to comply with the approved plan, with permit conditions, or with the provisions of this development code, a warning and written notice to comply shall be served upon that person. The notice shall set forth the measures necessary to achieve compliance and shall state the time within which such measures must be completed. If the person engaged in the land-disturbing or development activity fails to comply within the time specified, he shall be deemed in violation of this chapter.
(b) Stop work orders. If the violation is not corrected within the time specified in the written notice to comply, the Zoning Administrator or designee shall issue a stop-work order requiring that land-disturbing or development activities be stopped until necessary corrective action or mitigation has occurred; provided, however, that, if the violation presents an imminent threat to public health or waters of the state or if the land-disturbing or development activities are conducted without obtaining the necessary permit, the Zoning Administrator shall issue an immediate stop-work order in lieu of a warning. All stop-work orders shall be effective immediately upon issuance and shall be in effect until the necessary corrective action or mitigation has occurred. Such stop work orders shall apply to all land-disturbing or development activity on the site with the exception of the installation and maintenance of temporary or permanent erosion and sediment controls.
(c) Suspension or revocation of permit. The Zoning Administrator may suspend or revoke a development permit if it is deemed that a person engaged in land-disturbing or development activities has failed to comply with the approved plan, with permit conditions, or with the provisions of this UDC.
(d) Land disturbance bond forfeiture. If the person engaged in the land-disturbing or development activity fails to comply within the time specified, he shall be deemed in violation of this chapter and, in addition to other penalties, shall be deemed to have forfeited the land disturbance bond, if required to post one under the provisions of this chapter. The city may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.
(e) Monetary penalties. Any person who violates any provisions of this chapter, or any permit condition or limitation established pursuant to this chapter, or who negligently or intentionally fails or refuses to comply with any stop work order issued by the Zoning Administrator as provided in this section shall be liable for a civil penalty not to exceed $2,500.00 per day. For the purpose of enforcing the provisions of this section, notwithstanding any provisions in any city charter to the contrary, city courts shall be authorized to impose penalty not to exceed $2,500.00 for each violation. Each day during which a violation, or failure or refusal to comply continues, shall be a separate violation.
Sec. 7-121. Completion of development.
(a) Upon completion of the project, the applicant or other responsible party may be required to submit a final hydrological study and shall submit all as-built plans of the project, in electronic format, that may be required by the zoning administrator. In addition, the applicant shall submit electronic file copies of information as specified by the Zoning Administrator which unless otherwise specified shall be limited to water lines, sanitary sewer lines, road centerlines, and lot lines for parcels. Building permits may be withheld pending receipt of the electronic files.
(b) Upon application and for a fee, the Zoning Administrator may provide a certificate of project compliance.
(c) Once a development project is complete and the site has been stabilized in the opinion of the zoning administrator, Building Official, or designee, the land disturbance bond (if required) shall be released by the zoning administrator.
Sec. 7-201. Generally.
No development permit shall be approved by the Zoning Administrator until all utility improvements, if required by this Article or UDC generally, have been constructed or installed in a satisfactory manner and approved by the Zoning Administrator and public utility provider as applicable.
Sec. 7-202. Water generally.
(a) All habitable buildings shall be connected to a water system capable of providing water for health and emergency purposes, including adequate fire protection.
(b) No building permit shall be issued for any building within a subdivision, or for the development of land, if there is not present to the lot in question or to the land development an adequate water supply.
Sec. 7-203. Water mains.
(a) When a public water main is accessible, the subdivider or land developer shall install water supply facilities, including fire hydrants, that meet or exceed the specifications of the city. Water mains within subdivisions and land developments must be provided with connections to each lot in the subdivision and each land development.
(b) The size of water mains shall be justified by hydraulic analysis performed by a professional engineer and approved by the City utility director or designee.
(c) Easements shall be provided for all utility infrastructure, and such easements shall be at least 10 feet in width on each side of the centerline of the main.
Sec. 7-204. Well water.
(a) If a municipal or other public water supply is not available to the subdivision or land development at the time of constructing improvements for a subdivision or land development, then the subdivider or developer shall provide an adequate alternative water source and an adequate water storage facility.
(b) In subdivisions or land developments with a residential density of one unit per acre or less and when a public water system is not available, individual wells may be used in a manner so that an adequate supply of potable water will be available to every lot in the subdivision or to the land development.
(c) When individual wells are proposed to be used for water supply, water samples shall be submitted to, and individual wells shall be approved by, the Jackson County Environmental Health Department. Approvals shall be submitted to Zoning Administrator prior to final subdivision plat for a subdivision or development permit approval for a land development.
Sec. 7-205. Community water system.
(a) If a municipal or other public water supply is not available to the subdivision or land development at the time of constructing improvements for a subdivision or land development, then the subdivider or developer shall provide an adequate alternative water source and an adequate water storage facility.
(b) Any community water system, if permitted, shall provide a minimum flow of 400 gallons of potable water per day per each lot platted, whether or not each lot is to be immediately developed; shall be sanitary; and shall have a minimum pressure of 20 pounds per square inch at each lot in the subdivision or each land development to be served. For all common non-public water supply systems, acceptable management, maintenance, and distribution policies and procedures shall be established. These policies and procedures shall be required to guarantee the provision of adequate supplies to each perspective lot owner on a continuing, ongoing basis, and to provide acceptable means for repairs and unforeseen events.
(c) The community water system plan shall be approved by the Jackson County Environmental Health Department and a letter of approval from the Georgia Department of Natural Resources shall accompany the final plat or land development application.
Sec. 7-206. Fire hydrants.
(a) Fire hydrants shall be required for all nonresidential land developments and all subdivisions except those permitted to be served by individual on-site wells. Fire hydrants with appropriate water pressure at appropriate intervals throughout the subdivision or land development shall be provided by the subdivider or land developer as required by the fire department or fire service district with jurisdiction.
(b) The location and construction of fire hydrants shall be in accordance with city standard specifications.
(c) To eliminate future street cuts, all underground utilities for fire hydrants, together with the fire hydrants themselves, and all other supply improvements shall be installed before any final paving of a street within the right-of-way shared by such underground utilities.
Sec. 7-207. Wastewater generally.
(a) All habitable buildings and buildable lots shall be served by an approved means of wastewater collection and treatment. Each subdivision and land development shall be served by adequate sewage disposal facilities.
(b) No building permit shall be issued for any building within a subdivision or for the development of land, if there is not present throughout the subdivision or to the land development an adequate system of wastewater collection and treatment.
Sec. 7-208. Connection to public sewerage system.
(a) When a public sanitary sewerage system is reasonably accessible, as determined by the City Engineer or designee, the subdivider or land developer shall connect with same and provide sewers accessible to each lot in the subdivision or to each land development. If a public sanitary sewer is reasonably accessible, it shall be unlawful to connect any new habitable building upon any such property to an individual sewage disposal system.
(b) When a public sanitary sewerage system is not immediately accessible but is anticipated to be available within a period of three years, the applicant shall install sanitary sewer lines, laterals, and mains from the street curb to a point in the subdivision or land development boundary so that a future connection with the public sewer main can be made. The Zoning Administrator may condition the approval of a subdivision or may require as a condition of land development approval on submission of an agreement to connect to the public sewerage system upon its availability.
(c) Design and engineering of sanitary sewers shall be in accordance with the city specifications. Sanitary sewers shall be located within street or alley rights-of-way unless topography dictates otherwise.
(d) When located outside a right of way, easements shall be provided for sanitary sewer lines, and such easements shall be at least 10 feet in width on each side of the centerline of the sewer line.
Sec. 7-209. Alternative wastewater systems.
If sanitary sewer is not reasonably available at the time of the development of the subdivision or land development, and if sanitary sewer is not anticipated to be available within a period of three years to serve the subdivision or land development in question, then on-site septic tanks, an oxidation pond, or another method of treatment of sanitary sewerage may be approved and shall be installed by and at the expense of the subdivider, land developer, or lot purchaser, in conformity with the requirements of the Jackson County Environmental Health Department.
Sec. 7-210. Septic tank.
Where individual onsite wastewater disposal systems are proposed and allowed, individual lot sizes and widths must exhibit appropriate regard for the peculiar health, drainage, and maintenance characteristics on the site. Additionally, detailed soil tests may be required in order to verify the ability of the lots to safely contain and dispose of septic system effluent. All septic tanks and onsite wastewater disposal systems are subject to the approval of the Jackson County Environmental Health Department.
Sec. 7-211. Oversizing of water and sewer mains.
The subdivider or land developer shall construct such oversized water and sanitary sewer improvements that the City determines necessary, provided that the subdivider or land developer shall not be obligated for the additional cost of such improvements that are not uniquely required for that subdivision or land development, and provided the subdivider or land developer agrees to a proposal by the city to share in the cost arrangements for over-sizing such improvements. A formula may be developed by the city engineer or designee to provide for a sharing of the cost of such improvements needed to serve the subdivision or land development when certain of the improvements are necessary to serve future subdivisions or land developments in the vicinity.
Sec. 7-212. Stormwater Drainage.
(a) An adequate drainage system, separate and independent of any sanitary sewer system and including any necessary ditches, pipes, culverts, intersectional drains, drop inlets, etc., shall be provided for the proper drainage of all surface water for all subdivisions and land developments.
(b) Sizing and location of all drainage structures shall be the responsibility of a registered professional engineer or land surveyor, and construction shall be in accordance with the specifications of the city or utility provider with jurisdiction.
(c) The city may require the use of on-site control methods such as retention or detention to mitigate the stormwater and drainage impacts of a proposed subdivisions or land development. The Zoning Administrator shall not approve any preliminary plat of a subdivision or construction plans for any land development that does not make adequate provision for storm and floodwater runoff.
(d) No building permit shall be issued for any building within a subdivision or for the development of land, if there is not present throughout the subdivision or land development an adequate system of drainage and stormwater management.
(e) When located outside a right of way, easements shall be provided for drainage, and such easements shall be at least 20 feet wide.
Sec. 7-213. Gas, electric, and other utilities.
(a) All utility facilities, including but not limited to gas, electric power, telephone, cable television, and broadband shall be located underground throughout the subdivision or land development. Whenever existing utility facilities are located above ground, except when existing on public roads and rights-of-way, they shall be removed and placed underground.
(b) Easements shall be provided for utilities, private and public, and such easements shall be at least 20 feet wide.
Sec. 7-302. Utility encroachment permit procedure.
Sec. 7-301. Utility encroachment permit required.
(a) It shall be unlawful for any utility to excavate or to construct, install, maintain, renew, remove, or relocate facilities in, on, along, over or under the public rights of way of the city without a utility encroachment permit from the city engineer or designee in accordance with the terms of this Article. The Zoning Administrator shall have an administrative role in assisting the city with processing utility encroachment permit applications.
(b) The requirement to obtain a utility encroachment permit may be waived by the Zoning Administrator in cases where utility work contemplated within the public rights of way of the city is shown on construction plans for a private development that has been reviewed and approved by the Zoning Administrator and a development permit has been issued in accordance with applicable provisions of this UDC.
(c) This section shall not be construed as requiring a separate utility encroachment permit for a driveway or for installation of a storm drainage culvert if such driveway or storm drainage culvert is authorized by the Zoning Administrator under a separate permit or authorization pursuant to this UDC.
Sec. 8-702. Utility encroachment permit procedure.
Utility encroachment permits shall be obtained from the Zoning Administrator upon application made on forms prescribed by the Zoning Administrator and city engineer. The written application shall include the following:
(a) The name and address of the utility;
(b) The nature, extent, and location of any work proposed to be done, along with satisfactory plans as attachments showing in detail the location of the proposed facility or operations as described in the permit application. The plans shall show the size or capacity of facilities to be installed; their relationship to street features such as right-of-way lines, pavement edge, structures, attachments to current infrastructure, etc., horizontal and vertical clearance to critical elements of the roadway and any other information necessary by the city engineer to evaluate the impact on the street and its operation
(c) The name and address of the person or firm who is to do such work;
(d) The name, street address, email address if applicable and telephone and facsimile numbers of one or more facilities representative(s).
(e) The projected starting and finishing dates for the work;
(f) An indemnity bond or other acceptable security in an amount to be set by the city to pay any damages to any part of the city road system or other city property or to any city employee or member of the public caused by activity or work of the utility performed under authority of the permit issued;
(g) A copy, if requested, of the registrant’s certificate of authority (or other acceptable evidence of authority to operate) from the Georgia Public Service Commission and/or the FCC and any other similar approvals, permits, or agreements;
(h) A copy, if requested, of the service agreement, if applicable or other legal instrument that authorizes the utility to use or occupy the right of way for the purpose described in the application;
(i) Traffic safety plan; and
(j) The application shall be accompanied by a permit review fee, as established by the City Council.
Sec. 7-303. Incomplete permit application.
If a permit application is incomplete, the Zoning Administrator shall notify the applicant and shall provide a reasonable period of time in which to revise the application.
Sec. 7-304. Permit review and decision.
(a) Unless the permit application is extraordinarily complicated and extensive, in which case more time may be taken, the Zoning Administrator shall have 30 calendar days from the posted application submission deadline to review (including distribution to the city engineer) the permit application for compliance with the requirements of this division and to evaluate the application in terms of the impact of work proposed in the permit with regard to the following: impacts on safety, visual quality of streets, traffic flow, other users of the right of way; and the difficulty and length of time of the project.
(b) The Zoning Administrator shall issue the requested permit if there are no concerns with regard to the criteria of this division. The Zoning Administrator or city engineer may place conditions of approval on any permit issued. If there are concerns with issuing the requested permit, the Zoning Administrator shall indicate those concerns or objections in writing to the applicant and deny the requested permit.
(c) Any applicant aggrieved of a decision of the Zoning Administrator to deny a utility encroachment permit under the provisions of this division may file in writing and sent via certified mail an appeal to the zoning administrator, who shall schedule the appeal in accordance with procedures of this UDC for appeal of administrative decisions.
Sec. 7-305. Permit commencement, expiration and extension.
(a) Each permit issued by the city engineer (via the zoning administrator) shall have a set commencement and expiration date based on information provided in the applicant’s permit application. When the construction under any permit is completed, the utility shall notify the city engineer and zoning administrator. The permit shall remain in place until construction or activity authorized under the permit is completed or until its expiration date unless the utility is in default.
(b) If work is not begun within six months of the date of permit issuance, the permit will automatically expire.
(c) The Zoning Administrator is authorized but shall not be obligated to grant an extension to a permit prior to expiration, upon application, and provided that a permit review fee required for a permit application is paid.
Sec. 7-306. Permit default.
The Zoning Administrator may find a utility in default and give written notice of default to a utility if it is determined that a utility has:
(a) Violated any provision, requirement, or condition of a utility encroachment permit, or any law of the city,, county, state, or federal government;
(b) Attempted to evade any provision or requirement of this division;
(c) Practiced any fraud or deceit upon the city; or
(d) Made a material misrepresentation or omission of fact in its permit application.
Sec. 7-307. Termination of permit.
If a utility fails to cure a default within 10 calendar days after such notice is provided to the utility by the city, then such default shall be a material breach and the city may exercise any remedies or rights it has at law or in equity to terminate the permit. If the Zoning Administrator decides there is cause or reason to terminate, the following procedure shall be followed:
(a) The Zoning Administrator shall serve a utility with a written notice of the reason or cause for proposed termination and shall allow a utility a minimum of 20 calendar days to cure its breach; and
(b) If the utility fails to cure within 10 calendar days, the city may declare the permit terminated.
Sec. 7-308. Utility accommodation policy and standards.
(a) The document known as “utility accommodation policy and standards,” promulgated and published by the Georgia Department of Transportation Division of Operations, Office of Utilities, dated 2016, and as may be amended from time to time, is hereby adopted in its entirety as if fully set forth in this division, as minimum required standards.
(b) A copy of the “utility accommodation policy and standards” shall be maintained by the Zoning Administrator and shall be available for public inspection.
(c) References in the “utility accommodation policy and standards” to state personnel, agencies, and fees shall be interpreted, where required, as meaning the City of Commerce equivalents.
(d) Any conflicts between the provisions of this division and the “utility accommodation policy and standards” shall be resolved in favor of the “utility accommodation policy and standards.”
Article 8 Soil Erosion, Sedimentation, and Pollution Control
ARTICLE 8
SOIL EROSION, SEDIMENTATION, AND POLLUTION CONTROL
DIVISION I GENERAL PROVISIONS
DIVISION II MINIMUM REQUIREMENTS/BEST MANAGEMENT PRACTICES
DIVISION III APPLICATION AND PERMIT PROCESS
DIVISION IV INSPECTION AND ENFORCEMENT
DIVISION V. EDUCATION AND CERTIFICATION
Sec. 8-101. Title.
Sec. 8-801. Title.
This Article shall be known as “The City of Commerce Soil Erosion, Sedimentation and Pollution Control Ordinance.”
Sec. 8-102. Definitions.
The following definitions shall apply in the interpretation and enforcement of this Article, unless otherwise specifically stated:
Best Management Practices (BMPs): These practices include sound conservation and engineering practices to prevent and minimize erosion and resultant sedimentation which are consistent with, and no less stringent than, those practices contained in the “Manual for Erosion and Sediment Control in Georgia” published by the Commission as of January 1 of the year in which the land-disturbing activity was permitted.
Board: The State of Georgia Board of Natural Resources.
Buffer: The area of land immediately adjacent to the banks of state waters in its natural state of vegetation, which facilitates the protection of water quality and aquatic habitat.
Certified personnel: A person who has successfully completed the appropriate certification course approved by the Georgia Soil and Water Conservation Commission.
Commission: The Georgia Soil and Water Conservation Commission (GSWCC).
CPESC: Certified Professional in Erosion and Sediment Control with current certification by Certified Professional in Erosion and Sediment Control Inc., which is also referred to as CPESC or CPESC, Inc.
Cut: A portion of land surface or area from which earth has been removed or will be removed by excavation; the depth below original ground surface to the excavated surface; also known as excavation.
Department: The State of Georgia Department of Natural Resources (DNR).
Design professional: A professional licensed by the State of Georgia in the field of: engineering, architecture, landscape architecture, forestry, geology, or land surveying; or a person that is a Certified Professional in Erosion and Sediment Control (CPESC) with a current certification by EnviroCert, Inc. Design professionals shall practice in a manner that complies with applicable Georgia law governing professional licensure.
Director: The Director of the State of Georgia Environmental Protection Division of the Department of Natural Resources, or an authorized representative.
District: The Soil and Water Conservation District with jurisdiction.
Division: The Environmental Protection Division (EPD) of the State of Georgia Department of Natural Resources.
Drainage structure: A device composed of a virtually non-erodible material such as concrete, steel, plastic or other such material that conveys water from one place to another by intercepting the flow and carrying it to a release point for storm water management, drainage control, or flood control purposes.
Erosion: The process by which land surface is worn away by the action of wind, water, ice or gravity.
Erosion, sedimentation and pollution control plan: A plan required by the Erosion and Sedimentation Act, O.C.G.A. Chapter 12-7, that includes, as a minimum protection at least as stringent as the State General Permit, best management practices, and requirements of this Article.
Fill: A portion of land surface to which soil or other solid material has been added; the depth above the original ground surface or an excavation.
Final stabilization: All soil disturbing activities at the site have been completed, and that for unpaved areas and areas not covered by permanent structures and areas located outside the waste disposal limits of a landfill cell that has been certified by EPD for waste disposal, 100 percent of the soil surface is uniformly covered in permanent vegetation with a density of 70 percent or greater, or landscaped according to the Plan (uniformly covered with landscaping materials in planned landscaped areas) or equivalent permanent stabilization measures as defined in the Manual (excluding a crop of annual vegetation and seeding of target crop perennials appropriate for the region). Final stabilization applies to each phase of construction.
Finished grade: The final elevation and contour of the ground after cutting or filling and conforming to the proposed design.
Grading: Altering the shape of ground surfaces to a predetermined condition, including stripping, cutting, filling, stockpiling and shaping or any combination thereof and shall include the land in its cut or filled condition.
Ground elevation: The original elevation of the ground surface prior to cutting or filling.
Land-disturbing activity: Any activity which may result in soil erosion from water or wind and the movement of sediments into state waters or onto lands within the state, including, but not limited to, clearing, dredging, grading, excavating, transporting, and filling of land but not including agricultural practices as described in this Article.
Larger common plan of development or sale: A contiguous area where multiple separate and distinct construction activities are occurring under one plan of development or sale. For the purposes of this paragraph, “plan” means an announcement; piece of documentation such as a sign, public notice or hearing, sales pitch, advertisement, drawing, permit application, zoning request, or computer design; or physical demarcation such as boundary signs, lot stakes, or surveyor markings, indicating that construction activities may occur on a specific plot.
Local issuing authority: The governing authority of any county or municipality which is certified pursuant to subsection (a) O.C.G.A. 12-7-8. The City of Commerce is a local issuing authority.
Natural ground surface: The ground surface in its original state before any grading, excavation or filling.
Nephelometric Turbidity Units (NTU): Numerical units of measure based upon photometric analytical techniques for measuring the light scattered by finely divided particles of a substance in suspension. This technique is used to estimate the extent of turbidity in water in which colloidally dispersed or suspended particles are present.
NOI: A notice of intent form provided by the Environmental Protection Division for coverage under the state general permit.
NOT: A notice of termination form provided by the Environmental Protection Division to terminate coverage under the State General Permit.
Operator: The party or parties that have: (A) operational control of construction project plans and specifications, including the ability to make modifications to those plans and specifications;
or (B) day-to-day operational control of those activities that are necessary to ensure compliance with an erosion, sedimentation and pollution control plan for the site or other permit conditions, such as a person authorized to direct workers at a site to carry out activities required by the erosion, sedimentation and pollution control plan or to comply with other permit conditions.
Outfall: The location where storm water in a discernible, confined and discrete conveyance, leaves a facility or site or, if there is a receiving water on site, becomes a point source discharging into that receiving water.
Permit: The authorization necessary to conduct a land-disturbing activity under the provisions of this Article or UDC.
Person: Any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, state agency, municipality or other political subdivision of the State of Georgia, any interstate body or any other legal entity.
Phase or phased: Sub-parts or segments of construction projects where the sub-part or segment is constructed and stabilized prior to completing construction activities on the entire construction site.
Project: The entire proposed development project, regardless of the size of the area of land to be disturbed.
Properly designed: Designed in accordance with the design requirements and specifications contained in the “Manual for Erosion and Sediment Control in Georgia” (Manual) published by the Georgia Soil and Water Conservation Commission as of January 1 of the year in which the land-disturbing activity was permitted and amendments to the Manual as approved by the Commission up until the date of Notice of Intent (NOI) submittal.
Roadway drainage structure: A device such as a bridge, culvert, or ditch, composed of a virtually non-erodible material such as concrete, steel, plastic, or other such material that conveys water under a roadway by intercepting the flow on one side of a traveled roadway consisting of one or more defined lanes, with or without shoulder areas, and carrying water to a release point on the other side.
Sediment: Solid material, both organic and inorganic, that is in suspension, is being transported, or has been moved from its site of origin by wind, water, ice, or gravity as a product of erosion.
Sedimentation: The process by which eroded material is transported and deposited by the action of water, wind, ice or gravity.
Soil and Water Conservation District approved plan: An erosion, sedimentation and pollution control plan approved in writing by the Soil and Water Conservation District with jurisdiction.
Stabilization: The process of establishing an enduring soil cover of vegetation by the installation of temporary or permanent structures for the purpose of reducing to a minimum the erosion process and the resultant transport of sediment by wind, water, ice or gravity.
State General Permit: The National Pollution Discharge Elimination System (NPDES) general permit or permits for storm water runoff from construction activities as is now in effect or as may be amended or reissued in the future pursuant to the state’s authority to implement the same through federal delegation under the Federal Water Pollution Control Act, as amended, 33 U.S.C.
Section 1251, et seq., and subsection (f) of Code Section 12-5-30.
State waters: Any and all rivers, streams, creeks, branches, lakes, reservoirs, ponds, drainage systems, springs, wells, and other bodies of surface or subsurface water, natural or artificial, lying within or forming a part of the boundaries of Georgia which are not entirely confined and retained completely upon the property of a single individual, partnership, or corporation.
Structural erosion, sedimentation and pollution control practices: Practices for the stabilization of erodible or sediment-producing areas by utilizing the mechanical properties of matter for the purpose of either changing the surface of the land or storing, regulating or disposing of runoff to prevent excessive sediment loss. Examples of structural erosion and sediment control practices are riprap, sediment basins, dikes, level spreaders, waterways or outlets, diversions, grade stabilization structures and sediment traps, etc. Such practices can be found in the publication, Manual for Erosion and Sediment Control in Georgia.
Vegetative erosion and sedimentation control measures: Measures for stabilization of erodible or sediment-producing areas by covering the soil using one of the following approaches: (a) Permanent seeding, sprigging or planting, producing long-term vegetative cover, or (b) Temporary seeding, producing short-term vegetative cover; or (c) Sodding, covering areas with a turf of perennial sod-forming grass. Such measures may be found in the publication, Manual for Erosion and Sediment Control in Georgia.
Watercourse: Any natural or artificial watercourse, stream, river, creek, channel, ditch, canal, conduit, culvert, drain, waterway, gully, ravine, or wash in which water flows either continuously or intermittently and which has a definite channel, bed and banks, and including any area adjacent thereto subject to inundation by reason of overflow or floodwater.
Wetlands: Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, bogs, and similar areas.
Sec. 8-103. Applicability.
This Article shall apply to all property within the corporate limits of the City of Commerce.
Sec. 8-104. Exemptions.
This Article shall apply to any land-disturbing activity undertaken by any person on any land except for the following:
(a) Surface mining, as the same is defined in O.C.G.A. 12-4-72, “The Georgia Surface Mining Act of 1968;”
(b) Granite quarrying and land clearing for such quarrying;
(c) Such minor land-disturbing activities as home gardens and individual home landscaping, repairs, maintenance work, fences, and other related activities which result in minor soil erosion;
(d) The construction of single-family residences, when such construction disturbs less than one acre and is not a part of a larger common plan of development or sale with a planned disturbance of equal to or greater than one acre and not otherwise exempted under this paragraph; provided, however, that construction of any such residence shall conform to the minimum requirements as set forth in O.C.G.A. 12-7-6 and this Article;
(e) Agricultural operations as defined in O.C.G.A. 1-3-3, “definitions”, to include raising, harvesting or storing of products of the field or orchard; feeding, breeding or managing livestock or poultry; producing or storing feed for use in the production of livestock, including but not limited to cattle, calves, swine, hogs, goats, sheep, and rabbits or for use in the production of poultry, including but not limited to chickens, hens and turkeys;
producing plants, trees, fowl, or animals; the production of aquaculture, horticultural, dairy, livestock, poultry, eggs and apiarian products; farm buildings and farm ponds;
(f) Forestry land management practices, including harvesting; provided, however, that when such exempt forestry practices cause or result in land-disturbing or other activities otherwise prohibited in a buffer, as established in this Article, no other land-disturbing activities, except for normal forest management practices, shall be allowed on the entire property upon which the forestry practices were conducted for a period of three years after completion of such forestry practices;
(g) Any project carried out under the technical supervision of the Natural Resources Conservation Service (NRCS) of the United States Department of Agriculture;
(h) Any project involving less than one acre of disturbed area; provided, however, that this exemption shall not apply to any land-disturbing activity within a larger common plan of development or sale with a planned disturbance of equal to or greater than one acre or within 200 feet of the bank of any state waters, and for purposes of this paragraph, “state waters” excludes channels and drainage ways which have water in them only during and immediately after rainfall events and intermittent streams which do not have water in them year-round; provided, however, that any person responsible for a project which involves less than one acre, which involves land-disturbing activity, and which is within 200 feet of any such excluded channel or drainage way, must prevent sediment from moving beyond the boundaries of the property on which such project is located and provided, further, that nothing contained herein shall prevent the local issuing authority from regulating any such project which is not specifically exempted by this Article;
(i) Construction or maintenance projects, or both, undertaken or financed in whole or in part, or both, by the Department of Transportation, the Georgia Highway Authority, or the State Road and Tollway Authority; or any road construction or maintenance project, or both, undertaken by any county or municipality; provided, however, that construction or maintenance projects of the Department of Transportation or the State Road and Tollway Authority which disturb one or more contiguous acres of land shall be subject to provisions of O.C.G.A. 12-7-7.1; except where the Department of Transportation, the Georgia Highway Authority, or the State Road and Tollway Authority is a secondary permittee for a project located within a larger common plan of development or sale under the state general permit, in which case a copy of a notice of intent under the state general permit shall be submitted to the Local Issuing Authority, the Local Issuing Authority shall enforce compliance with the minimum requirements set forth in O.C.G.A. 12-7-6 as if a permit had been issued, and violations shall be subject to the same penalties as violations by permit holders;
(j) Any land-disturbing activities conducted by any electric membership corporation or municipal electrical system or any public utility under the regulatory jurisdiction of the Public Service Commission, any utility under the regulatory jurisdiction of the Federal Energy Regulatory Commission, any cable television system as defined in O.C.G.A. 36- 18-1, or any agency or instrumentality of the United States engaged in the generation, transmission, or distribution of power; except where an electric membership corporation or municipal electrical system or any public utility under the regulatory jurisdiction of the Public Service Commission, any utility under the regulatory jurisdiction of the Federal Energy Regulatory Commission, any cable television system as defined in O.C.G.A. 36- 18-1, or any agency or instrumentality of the United states engaged in the generation, transmission, or distribution of power is a secondary permittee for a project located within a larger common plan of development or sale under the state general permit, in which case the Local Issuing Authority shall enforce compliance with the minimum requirements set forth in O.C.G.A. 12-7-6 as if a permit had been issued, and violations shall be subject to the same penalties as violations by permit holders; and
(k) Any public water system reservoir.
Sec. 8-105. Prohibition on cumulative exemptions.
It is the intent of the city to prohibit an applicant from dividing up land disturbance activities into less than one-acre increments in order to qualify for exemption from this Article. Accordingly, notwithstanding the exemption described in paragraph (h) of Sec. 8-104, there shall be no exemption authorized, even if the amount of land disturbance is less than one acre, if a permit application is for property that is contiguous to a parcel or tract that was exempted from the requirement to obtain a land disturbance permit because it had less than one acre disturbed.
Sec. 8-201. General Requirements.
(a) Excessive soil erosion and resulting sedimentation can take place during land-disturbing activities if requirements of this ordinance and the NPDES General Permit are not met.
Therefore, plans for those land-disturbing activities which are not exempted by this Article shall contain provisions for application of soil erosion, sedimentation and pollution control measures and practices. The provisions shall be incorporated into the erosion, sedimentation and pollution control plans.
(b) Soil erosion, sedimentation and pollution control measures and practices shall conform to the minimum requirements of this Article. The application of measures and practices shall apply to all features of the site, including street and utility installations, drainage facilities and other temporary and permanent improvements. Measures shall be installed to prevent or control erosion, sedimentation and pollution during all stages of any land-disturbing activity in accordance with requirements of this ordinance and the NPDES General Permit.
(c) Best management practices as set forth in this Article shall be required for all landdisturbing activities. Proper design, installation, and maintenance of best management practices shall constitute a complete defense to any action by the Director or to any other allegation of noncompliance with this Article or any substantially similar terms contained in a permit for the discharge of storm water issued pursuant to subsection (f) of O.C.G.A.
12-5-30, the “Georgia Water Quality Control Act.” As used in this Article, the terms “proper design” and “properly designed” mean designed in accordance with the hydraulic design specifications contained in the Manual for Erosion and Sediment Control in Georgia specified in O.C.G.A. 12-7-6 subsection (b).
(d) A discharge of storm water runoff from disturbed areas where best management practices have not been properly designed, installed, and maintained shall constitute a separate violation of any land-disturbing permit issued by a local issuing authority or of any state general permit issued by the Division pursuant to subsection (f) of O.C.G.A. 12-5-30, the “Georgia Water Quality Control Act”, for each day on which such discharge results in the turbidity of receiving waters being increased by more than 25 nephelometric turbidity units for waters supporting warm water fisheries. The turbidity of the receiving waters shall be measured in accordance with guidelines to be issued by the Director. This paragraph shall not apply to any land disturbance associated with the construction of single-family homes which are not part of a larger common plan of development or sale unless the planned disturbance for such construction is greater than 1 acre.
(e) Failure to properly design, install, or maintain best management practices shall constitute a violation of any land-disturbing permit issued by a local issuing authority or of any state general permit issued by the Division pursuant to subsection (f) of Code Section 12- 5-30, the “Georgia Water Quality Control Act”, for each day on which such failure occurs.
(f) The Director may require, in accordance with regulations adopted by the Board, reasonable and prudent monitoring of the turbidity level of receiving waters into which discharges from land disturbing activities occur.
Sec. 8-202. Adherence to erosion control manual and additional requirements.
The rules and regulations, ordinances, or resolutions adopted pursuant to O.C.G.A.12-7-1 et. seq.
for the purpose of governing land-disturbing activities shall require, as a minimum, protections at least as stringent as the state general permit; and best management practices, including sound conservation and engineering practices to prevent and minimize erosion and resultant sedimentation, which are consistent with, and no less stringent than, those practices contained in the Manual for Erosion and Sediment Control in Georgia published by the Georgia Soil and Water Conservation Commission as of January 1 of the year in which the land-disturbing activity was permitted, as well as the following:
(a) Stripping of vegetation, re-grading and other development activities shall be conducted in a manner so as to minimize erosion;
(b) Cut-fill operations must be kept to a minimum;
(c) Development plans must conform to topography and soil type so as to create the lowest practicable erosion potential;
(d) Whenever feasible, natural vegetation shall be retained, protected and supplemented;
(e) The disturbed area and the duration of exposure to erosive elements shall be kept to a practicable minimum;
(f) Disturbed soil shall be stabilized as quickly as practicable;
(g) Temporary vegetation or mulching shall be employed to protect exposed critical areas during development;
(h) Permanent vegetation and structural erosion control practices shall be installed as soon as practicable;
(i) To the extent necessary, sediment in run-off water must be trapped by the use of debris basins, sediment basins, silt traps, or similar measures until the disturbed area is stabilized. As used in this paragraph, a disturbed area is stabilized when it is brought to a condition of continuous compliance with the requirements of O.C.G.A. 12-7-1 et. seq.;
(j) Adequate provisions must be provided to minimize damage from surface water to the cut face of excavations or the sloping of fills;
(k) Cuts and fills may not endanger adjoining property;
(l) Fills may not encroach upon natural watercourses or constructed channels in a manner so as to adversely affect other property owners;
(m)Grading equipment must cross flowing streams by means of bridges or culverts except when such methods are not feasible, provided, in any case, that such crossings are kept to a minimum;
(n) Land-disturbing activity plans for erosion, sedimentation and pollution control shall include provisions for treatment or control of any source of sediments and adequate sedimentation control facilities to retain sediments on-site or preclude sedimentation of adjacent waters beyond the levels specified in this Article.
(o) There is established a 50 foot buffer along the banks of all state waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action, except where the Director determines to allow a variance that is at least as protective of natural resources and the environment, where otherwise allowed by the Director pursuant to O.C.G.A. 12-2-8, where a drainage structure or a roadway drainage structure must be constructed, provided that adequate erosion control measures are incorporated in the project plans and specifications, and are implemented; or along any ephemeral stream. As used in this provision, the term 'ephemeral stream' means a stream:
that under normal circumstances has water flowing only during and for a short duration after precipitation events; that has the channel located above the ground-water table year round; for which ground water is not a source of water; and for which runoff from precipitation is the primary source of water flow, Unless exempted as along an ephemeral stream, the buffers of at least 25 feet established pursuant to part 6 of Article 5, Chapter 5 of Title 12, the “Georgia Water Quality Control Act”, shall remain in force unless a variance is granted by the Director as provided in this paragraph. The following requirements shall apply to any such buffer:
1. No land-disturbing activities shall be conducted within a buffer and a buffer shall remain in its natural, undisturbed state of vegetation until all land-disturbing activities on the construction site are completed. Once the final stabilization of the site is achieved, a buffer may be thinned or trimmed of vegetation as long as a protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed; provided, however, that any person constructing a single-family residence, when such residence is constructed by or under contract with the owner for his or her own occupancy, may thin or trim vegetation in a buffer at any time as long as protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed; and
2. The buffer shall not apply to stream crossings for water lines or sewer lines, provided that they occur at an angle, as measured from the point of crossing, within 25 degrees of perpendicular to the stream; cause a width of disturbance of not more than 50 feet within the buffer; and adequate erosion control measures are incorporated into the project plans and specifications and are implemented.
(p) In common developments, commercial developments, industrial developments and residential developments encompassing more than one (1) residential structure, a sediment barrier shall be constructed around the entire perimeter of the disturbed area.
The sediment barrier shall consist of two rows of GA DOTD and GSWCC approved Type A or Type C silt fence spaced thirty-six (36) inches apart and the disturbed area between the two rows shall be properly stabilized in accordance with current best management practices. In any disturbed areas that exist along all state waters, other sensitive areas, and in areas of lower elevations, the sediment barrier shall be constructed of two rows of Type C silt fence, the two rows should be placed a minimum of thirty-six (36) inches apart and the disturbed area between the two rows shall be properly stabilized in accordance with current best management practices. Within these areas the use of Type C Alternative silt fencing, commonly known as C-Pop, is prohibited. Barriers will be overlapped by a minimum of 18” when multiple types of sediment barriers are used in a single run on a site.
(q) In single residential and in-fill lots, a sediment barrier shall be constructed around the entire perimeter of the disturbed area. The sediment barrier shall consist of two rows of GA DOTD and GSWCC approved Type A, Type C, or Type C Alternative silt fence placed in two rows and spaced thirty-six (36) inches apart and the disturbed area between the two rows shall be properly stabilized in accordance with current best management practices. In any disturbed areas that exist along all state waters, other sensitive areas, and in areas of lower elevations, the sediment barrier shall be constructed of two rows of Type C silt fence. The two rows should be placed a minimum of 36” apart and the disturbed area between the two rows shall be properly stabilized in accordance with current best management practices. Within these specific areas, the use of Type C Alternative silt fencing, commonly known as C-Pop, is prohibited. Barriers will be overlapped by a minimum of 18” when multiple types of sediment barriers are used in a single run on a site.
(Amended 06/15/2026) Sec. 8-203. Injury not proof of violation.
The fact that land-disturbing activity for which a permit has been issued results in injury to the property of another shall not create a presumption of a violation of the standards provided for in this Article or the terms of the permit.
Sec. 8-301. General.
The property owner, developer and designated planners and engineers shall design and review before submittal the general development plans. The local issuing authority shall review the tract to be developed and the area surrounding it. They shall consult the zoning ordinance, stormwater management ordinance, subdivision ordinance, flood damage prevention ordinance, this Article, and any other ordinances, rules, regulations or permits, which regulate the development of land within the jurisdictional boundaries of the local issuing authority. However, the owner and/or operator are the only parties who may obtain a permit.
Sec. 8-302. Permit application requirements.
No person shall conduct any land-disturbing activity within the jurisdictional boundaries of the City of Commerce without first obtaining a permit from the City of Commerce to perform such activity and providing a copy of Notice of Intent (NOI) submitted to EPD, if applicable.
The following permit applications procedures are hereby established and shall control processing and issuance of permits under this Article:
(a) Plan and data. The application for a permit shall be submitted to the City of Commerce and must include the applicant’s erosion, sedimentation and pollution control plan with supporting data, as necessary. Said plans shall include, as a minimum, the data specified in this Article. Erosion, sedimentation and pollution control plans, together with supporting data, must demonstrate affirmatively that the land disturbing activity proposed will be carried out in such a manner that the provisions of this Article will be met.
Applications for a permit will not be accepted unless accompanied by four copies of the applicant’s erosion, sedimentation and pollution control plans. All applications shall contain a certification stating that the plan preparer or the designee thereof visited the site prior to creation of the plan in accordance with EPD Rule 391-3-7 .10.
(b) Fees. In addition to the local permitting fees, fees will also be assessed pursuant to paragraph (5) subsection (a) of O.C.G.A. 12-5-23, provided that such fees shall not exceed $80.00 per acre of land-disturbing activity, and these fees shall be calculated and paid by the primary permittee as defined in the state general permit for each acre of landdisturbing activity included in the planned development or each phase of development.
All applicable fees shall be paid prior to issuance of the land disturbance permit. In a jurisdiction that is certified pursuant to subsection (a) of O.C.G.A. 12-7-8 half of such fees levied shall be submitted to the division; except that any and all fees due from an entity which is required to give notice pursuant to paragraph (9) or (10) of O.C.G.A. 12- 7-17 shall be submitted in full to the division, regardless of the existence of a local issuing authority in the jurisdiction.
(c) District review of plans. Following receipt of an application and plan for a permit and following completion of local review for compliance, the local issuing authority shall refer the application and plan to the District for its review and approval or disapproval concerning the adequacy of the erosion, sedimentation and pollution control plan. The district shall approve or deny a plan within 35 calendar days of receipt. Failure of the district to act within 35 calendar days shall be considered an approval of the pending plan. The results of the district review shall be forwarded to the local issuing authority.
No permit will be issued unless the plan has been approved by the district, and any variances required by this Article have been obtained, all fees have been paid, and bonding, if required per this Article, have been obtained. Such review will not be required if the local issuing authority and the district have entered into an agreement which allows the local issuing authority to conduct such review and approval of the plan without referring the application and plan to the district. The local issuing authority with plan review authority shall approve or disapprove a revised plan submittal within 35 calendar days of receipt. Failure of the local issuing authority with plan review authority to act within 35 calendar days shall be considered an approval of the revised plan submittal.
(d) Denial for violations. If a permit applicant has had two or more violations of previous permits, this Article, or the Erosion and Sedimentation Act, as amended, within three years prior to the date of filing the application under consideration, the local issuing authority may deny the permit application.
(e) Bond. The local issuing authority may require the permit applicant to post a bond in the form of government security, cash, irrevocable letter of credit, or any combination thereof up to, but not exceeding, $3,000.00 per acre or fraction thereof of the proposed landdisturbing activity, prior to issuing the permit. If the applicant does not comply with this section or with the conditions of the permit after issuance, the local issuing authority may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.
These provisions shall not apply unless there is in effect an ordinance or statute specifically providing for hearing and judicial review of any determination or order of the local issuing authority with respect to alleged permit violations.
Sec. 8-303. Plan requirements.
All erosion, sedimentation and pollution control plans shall comply with the following requirements:
(a) Plans must be prepared to meet the minimum requirements of this Article, or through the use of more stringent, alternate design criteria which conform to sound conservation and engineering practices. The Manual for Erosion and Sediment Control in Georgia is hereby incorporated by reference into this Article.
(b) The plan for the land-disturbing activity shall consider the interrelationship of the soil types, geological and hydrological characteristics, topography, watershed, vegetation, proposed permanent structures including roadways, constructed waterways, sediment control and storm water management facilities, local ordinances and state laws. Maps, drawings and supportive computations shall bear the signature and seal of the certified design professional.
(c) Persons involved in land development design, review, permitting, construction, monitoring, or inspections or any land disturbing activity shall meet the education and training certification requirements, dependent on his or her level of involvement with the process, as developed by the commission and in consultation with the division and the Stakeholder Advisory Board created pursuant to O.C.G.A. 12-7-20.
(d) Data required for site plan shall include all the information required from the appropriate erosion, sedimentation and pollution control plan review checklist established by the commission as of January 1 of the year in which the land-disturbing activity was permitted.
Sec. 8-304. Permits.
Permits shall be issued or denied as soon as practicable but in any event not later than 45 calendar days after receipt by the local issuing authority of a completed application, providing variances and bonding are obtained, where necessary and all applicable fees have been paid prior to permit issuance. The permit shall include conditions under which the activity may be undertaken.
(a) Permit requires plan approval. No permit shall be issued by the local issuing authority unless the erosion, sedimentation and pollution control plan has been approved by the district and the local issuing authority has affirmatively determined that the plan is in compliance with this Article, any variances required are obtained, bonding requirements, if necessary, are met and all ordinances and rules and regulations in effect within the jurisdictional boundaries of the local issuing authority are met. If the permit is denied, the reason for denial shall be furnished to the applicant.
(b) Land disturbance consistent with this Article. Any land-disturbing activities by a local issuing authority shall be subject to the same requirements of this Article, and any other ordinances relating to land development, as are applied to private persons, and the division shall enforce such requirements upon the local issuing authority.
(c) Phasing. If the tract is to be developed in phases, then a separate permit shall be required for each phase.
(d) Suspension, revocation, or modification of permit. The permit may be suspended, revoked, or modified by the local issuing authority, as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in the title is not in compliance with the approved erosion and sedimentation control plan or that the holder or his successor in title is in violation of this Article. A holder of a permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the permit.
Sec. 8-401. Inspections.
(a) Inspections and regulation of permittees. The city will periodically inspect the sites of land-disturbing activities for which permits have been issued to determine if the activities are being conducted in accordance with the plan and if the measures required in the plan are effective in controlling erosion and sedimentation. Also, the local issuing authority shall regulate primary, secondary and tertiary permittees as such terms are defined in the state general permit.
(b) Permitee responsibilities. Primary permittees shall be responsible for installation and maintenance of best management practices where the primary permittee is conducting land-disturbing activities. Secondary permittees shall be responsible for installation and maintenance of best management practices where the secondary permittee is conducting land-disturbing activities. Tertiary permittees shall be responsible for installation and maintenance where the tertiary permittee is conducting land-disturbing activities.
(c) Notice to comply for non-compliance. If, through inspection, it is deemed that a person engaged in land-disturbing activities as defined herein has failed to comply with the approved plan, with permit conditions, or with the provisions of this Article, a written notice to comply shall be served upon that person. The notice shall set forth the measures necessary to achieve compliance and shall state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he shall be deemed in violation of this Article.
Sec. 8-402. Required amendment to this Article.
The local issuing authority shall amend its ordinances to the extent appropriate within 12 months of any amendments to the Erosion and Sedimentation Act of 1975.
Sec. 8-403. Investigations.
The city shall have the power to conduct such investigations as it may reasonably deem necessary to carry out duties as prescribed in this Article, and for this purpose to enter at reasonable times upon any property, public or private, for the purpose of investigation and inspecting the sites of land-disturbing activities.
Sec. 8-404. No refusal of access.
No person shall refuse entry or access to any authorized representative or agent of the city, the local issuing authority, the commission, the district, or division who requests entry for the purposes of inspection, and who presents appropriate credentials, nor shall any person obstruct, hamper or interfere with any such representative while in the process of carrying out his official duties.
Sec. 8-405. Review of actions.
(a) Review by district or commission. The district or the commission or both shall semiannually review the actions of counties and municipalities which have been certified as local issuing authorities pursuant to O.C.G.A. 12-7-8 (a). The district or the commission or both may provide technical assistance to any county or municipality for the purpose of improving the effectiveness of the county’s or municipality’s erosion, sedimentation and pollution control program. The district or the commission shall notify the division and request investigation by the division if any deficient or ineffective local program is found.
(b) Review of local issuing authority actions. The division may periodically review the actions of counties and municipalities which have been certified as local issuing authorities pursuant to Code Section 12-7-8 (a). Such review may include, but shall not be limited to, review of the administration and enforcement of a governing authority’s ordinance and review of conformance with an agreement, if any, between the district and the governing authority. If such review indicates that the governing authority of any county or municipality certified pursuant to O.C.G.A. 12-7-8 (a) has not administered or enforced its ordinances or has not conducted the program in accordance with any agreement entered into pursuant to O.C.G.A. 12-7-7 (e), the division shall notify the governing authority of the county or municipality in writing. The governing authority of any municipality so notified shall have 90 calendar days within which to take the necessary corrective action to retain certification as a local issuing authority. If the municipality does not take necessary corrective action within 90 calendar days after notification by the division, the division shall revoke the certification of the municipality as a local issuing authority.
Sec. 8-406. Failure to obtain a permit for land-disturbing activity.
If any person commences any land-disturbing activity requiring a land-disturbing permit as prescribed in this Article without first obtaining said permit, the person shall be subject to revocation of his business license, work permit or other authorization for the conduct of a business and associated work activities within the jurisdictional boundaries of the local issuing authority.
Sec. 8-407. Stop work orders.
For the first and second violations of the provisions of this Article, the director or the local issuing authority may elect to issue a written warning to the violator but is also authorized to immediately issue a stop work order concurrent with any warning or violation until necessary corrective action or mitigation has occurred. If the violation presents an imminent threat to public health, property, or waters of the state or if the land-disturbing activities are conducted without obtaining the necessary permit, the director or the local issuing authority shall issue an immediate stop-work order.
(a) For a third and each subsequent violation, the director or the local issuing authority shall issue an immediate stop-work order; and
(b) All stop-work orders shall be effective immediately upon issuance and shall be in effect until the necessary corrective action or mitigation has occurred.
(c) When a violation in the form of taking action without a permit, failure to maintain a stream buffer, or significant amounts of sediment, as determined by the local issuing authority or by the director or his or her designee, have been or are being discharged into state waters and where best management practices have not been properly designed, installed, and maintained, a stop work order shall be issued by the local issuing authority or by the director or his or her designee. All such stop work orders shall be effective immediately upon issuance and shall be in effect until the necessary corrective action or mitigation has occurred. Such stop work orders shall apply to all land-disturbing activity on the site with the exception of the installation and maintenance of temporary or permanent erosion and sediment controls.
Sec. 8-408. Bond forfeiture.
If, through inspection, it is determined that a person engaged in land-disturbing activities has failed to comply with the approved plan, a written notice to comply shall be served upon that person. The notice shall set forth the measures necessary to achieve compliance with the plan and shall state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he shall be deemed in violation of this Article and, in addition to other penalties, shall be deemed to have forfeited his performance bond, if required to post one under the provisions of this Article. The local issuing authority may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.
Sec. 8-409. Monetary penalties.
Any person who violates any provisions of this Article, or any permit condition or limitation established pursuant to this Article, or who negligently or intentionally fails or refuses to comply with any final or emergency order of the director issued as provided in this Article shall be liable for a civil penalty not to exceed $2,500.00 per violation per day. For the purpose of enforcing the provisions of this Article, notwithstanding any provisions in any city ordinance or charter to the contrary, municipal courts shall be authorized to impose penalties not to exceed $2,500.00 for each violation. Each day during which a violation, or failure or refusal to comply continues, shall be a separate violation.
Sec. 8-501. Education and training certification requirements.
Persons involved in land development design, review, permitting, construction, monitoring, or inspection or any land-disturbing activity shall meet the education and training certification requirements, dependent on their level of involvement with the process, as developed by the commission in consultation with the division and the stakeholder advisory board created pursuant to O.C.G.A. 12-7-20.
Sec. 8-502. On-site responsibility.
(a) For each site on which land-disturbing activity occurs, each entity or person acting as either a primary, secondary, or tertiary permittee, as defined in the state general permit, shall have as a minimum one person who is in responsible charge of erosion and sedimentation control activities on behalf of said entity or person and meets the applicable education or training certification requirements developed by the commission present on site whenever land-disturbing activities are conducted on that site. A project site shall herein be defined as any land-disturbance site or multiple sites within a larger common plan of development or sale permitted by an owner or operator for compliance with the state general permit.
(b) Persons or entities involved in projects not requiring a state general permit but otherwise requiring certified personnel on site may contract with certified persons to meet the requirements of this Article.
(c) If a state general permittee who has operational control of land-disturbing activities for a site has met the certification requirements of paragraph (1) of subsection (b) of O.C.G.A.
12-7-19, then any person or entity involved in land-disturbing activity at that site and operating in a subcontractor capacity for such permittee shall meet those educational requirements specified in paragraph (4) of subsection (b) of O.C.G.A 12-7-19 and shall not be required to meet any educational requirements that exceed those specified in said paragraph.
Sec. 8-603. Effective date.
Sec. 8-601. Administrative remedies.
The suspension, revocation, modification or grant with condition of a permit by the local issuing authority upon finding that the holder is not in compliance with the approved erosion, sediment and pollution control plan; or that the holder is in violation of permit conditions; or that the holder is in violation of any ordinance; shall entitle the person submitting the plan or holding the permit to a hearing before the Commerce City Council within 30 calendar days after receipt by the local issuing authority of written notice of appeal.
Sec. 8-602. Judicial review.
Any person, aggrieved by a decision or order of the local issuing authority, after exhausting his administrative remedies, shall have the right to appeal de novo to the Superior Court of Jackson County.
Sec. 8-604. Validity.
Should any section, paragraph, clause, phrase, or provision of this Article be adjudged invalid or held unconstitutional, such decisions shall not affect the remaining portions of this Article or
UDC.
Sec. 8-605. Liability.
(a) Neither the approval of a plan under the provisions of this Article, nor the compliance with provisions of this Article shall relieve any person from the responsibility for damage to any person or property otherwise imposed by law nor impose any liability upon the local issuing authority or District for damage to any person or property.
(b) The fact that a land-disturbing activity for which a permit has been issued results in injury to the property of another shall neither constitute proof of nor create a presumption of a violation of the standards provided for in this Article or the terms of the permit.
(c) No provision of this Article shall permit any persons to violate the Georgia Erosion and Sedimentation Act of 1975, the Georgia Water Quality Control Act or the rules and regulations promulgated and approved thereunder or pollute any Waters of the State as defined thereby.
Article 9 Buffers, Tree Protection, and Landscaping
ARTICLE 9
BUFFERS, TREE PROTECTION, AND LANDSCAPING
DIVISION I BUFFERS
DIVISION II TREE PROTECTION
DIVISION III LANDSCAPING
Sec. 9-101. Reference to requirements.
(a) Zoning buffers. Article 2, Table 2-2A and Table 2-2B of this UDC establish minimum buffer widths between certain zoning districts, which vary by zoning district.
(b) Stream buffers. Stream buffers are established in Article 8 of this UDC. Article 5 of this UDC establishes river corridor and water supply watershed protection districts which require stream buffers.
Sec. 9-102. Definitions.
ANSI 300 Standards: The generally accepted (consensus) industry standards for tree care practices, developed by the Tree Care Industry Association and written by a committee called the Accredited Standards Committee A300. These standards are based on current research and sound practice for writing specifications to manage trees, shrubs, and other woody plants.
Caliper: The diameter of a tree (usually nursery stock) measured at a point 6 inches above the ground or top of root ball for up to and including 4-inch caliper trees, and at a point 12 inches above the ground or top of root ball for larger sizes. For purposes of measuring tree density of existing trees, caliper is measured 4 feet above the ground.
Deciduous: A perennial plant with foliage that is cast off annually.
Drip line: A perimeter formed by the points farthest away from the trunk of a tree where precipitation falling from the branches of that tree lands on the ground.
Evergreen: A plant with foliage that is retained and remains green year-round.
Ground cover: A low growing plant, other than turf grass, which forms a continuous cover over the ground surface.
Hardwood tree: Any tree that is not coniferous (cone bearing). This definition is based on the colloquialism and does not necessarily reflect any true qualities of the tree.
Landscape plan: A graphic and written document containing criteria, specifications and detailed plans to arrange and modify the effects of natural features. A landscape plan consists of a site plan showing the boundaries of the property and the location of proposed plant materials, in relation to surroundings and improvements, along with a planting schedule and any additional specifications required by the Zoning Administrator.
Landscaped open space: That portion of a given lot, not covered by buildings, parking, access and service areas, or detention ponds, that is designed to enhance privacy and the amenity of the development by providing open spaces and/or landscaping features, screening and buffering for the benefit of the occupants or those in neighboring areas, or a general appearance of openness.
Landscaped open space may include, but need not be limited to, grass lawns, decorative planting, berms, walls and fences, pervious walkways, ornamental objects such as fountains, statues and other similar natural and man-made objects, wooded areas, and water courses, any or all of which are designed and arranged to produce an aesthetically pleasing effect within the development.
Landscaping: Shrubs, vines, turf, ground cover and other landscape materials which are utilized to enhance the aesthetic and functional qualities of a site.
Opaque: Impenetrable to view.
Overstory tree: Any deciduous or evergreen tree that has the potential to grow to a mature height of 40 feet or more.
Parking screen: A continuous hedge of evergreen shrubs attaining a height of at least 3 feet above grade.
Screening: An opaque visual screen with a height of at least 6 feet.
Shrub: A self-supporting woody plant that normally reaches a height of less than 15 feet.
Tree: Any living, self-supporting woody perennial plant which normally obtains a trunk diameter of at least 2 inches and a height of at least 10 feet, and typically has one main stem or trunk and many branches.
Tree protection area: An area designated for the purpose of saving natural trees, preserving the root system of natural trees and/or preserving natural buffers; tree protection areas include the critical root zones of all trees to be protected, as well as the above-ground portions of the trees.
Turf: Ground cover composed of one or more species of perennial grass that is grown as a permanent lawn.
Xeriscaping: Landscaping characterized by the use of vegetation that is drought-tolerant or low water use.
Sec. 9-103. Zoning buffer requirements.
(a) When required. Zoning buffers are required (See Table 2-2A and Table 2-2B) to be provided at the time of construction of any new development, subject to the requirements of this Article.
Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.