(b) Disturbance. Zoning buffers when required shall remain undisturbed, except where necessary to add vegetation to meet screening requirements, unless encroachments or grading are specifically authorized by the Zoning Administrator. Unless encroachments or grading are specifically authorized, or unless a variance is granted, existing trees within a required zoning buffer shall not be removed.
(c) Minimum required screening.
1. Required buffers shall provide screening, as defined, with a natural buffer of existing vegetation.
2. Where the full width of the required buffer does not exist or where existing vegetation is sparse such that it does not meet the screening standard, the buffer shall be replanted at the required minimum width.
3. Natural buffers may contain deciduous vegetation but shall contain evergreen trees suitable to local growing conditions that will provide an opaque visual screen during all seasons of the year.
4. Unless existing vegetation provides the required screening or another alternative that meets the requirements for opaque visual screening is approved by the Zoning Administrator, one evergreen tree, with a minimum height of 4 feet at planting, with branches touching the ground shall be planted for each 30 feet of buffer length, for each 10 feet of required buffer width. Rows of evergreen trees shall be staggered.
Evergreen screening shrubs planted 4 feet on center shall also be used where necessary to provide the required screening.
(d) Buffer encroachments. Zoning buffers shall contain no driveways, parking areas, patios, stormwater detention facilities, or any other structures or accessory uses except that underground utilities may be permitted to cross a buffer if the screening standards of this UDC will be subsequently achieved.
(e) Maintenance. Every required buffer required shall be maintained by the owner of the property where the buffer is located, so as to provide an opaque visual screen to a height of at least 6 feet on a continuous, year-round basis.
(f) Shown on plans. All required buffers shall be shown on grading and landscaping plans.
Sec. 9-205. Tree Save Requirements Sec. 9-206. Tree Survey Plan and Inventory Sec. 9-207. Shade Trees Planted by Developer Sec. 9-201. Findings.
Trees provide food and shelter for wildlife; reduce noise, glare and provide wind breaks; purify the air through transpiration; intercept airborne particulate matter and reduce some air pollutants;
provide oxygen and reduce the level of carbon monoxide in the air; provide vital roles in erosion control, soil conservation, and the reduction in stormwater runoff; moderate the climate; increase property values; provide aesthetic amenities; and improve the quality of water.
Sec. 9-202. Tree protection required.
Tree protection requirements of this division shall be applied to every activity that requires the issuance of a land-disturbance permit or development permit under this UDC, except for activities otherwise exempted by this division or UDC.
Sec. 9-203. Designation of tree protection areas.
The following areas shall be designated as tree protection areas, within which it shall be unlawful to remove trees unless specifically provided otherwise by this Article:
(a) Stream buffers. Stream buffers required by state law (see Article 8 of this UDC) shall be designated and delineated as tree protection areas on grading plans, landscaping plans, and final plats. See also Article 5 of this UDC for additional river and stream buffer requirements.
(b) Zoning buffers. Natural buffers when required by Table 2-2A and Table 2-2B of this UDC shall be designated and delineated as tree protection areas on grading plans, landscaping plans, and as buffers on final plats.
(c) Existing trees to be retained. Land developers and subdividers will be required to consider designing land developments and subdivisions in a way that protects existing trees to the maximum extent possible, while allowing for reasonable development of the site. Where a development site or subdivision has existing trees outside of required stream buffers and zoning buffers, and such trees are to be retained, the critical root zones around all such trees to be retained shall be designated and delineated as tree protection areas on grading plans, landscaping plans, and final plats as tree protection areas.
Sec. 9-204. Exemptions.
(a) The removal of trees from an owner-occupied, single-family lot not located within a subdivision.
(b) The removal of trees from horticultural properties such as farms, nurseries, or orchards.
(c) The necessary removal of trees by a utility company within dedicated utility easements.
(d) The removal of trees on public rights-of-way conducted by, or on behalf of, or an activity pursuant to work to be dedicated to a federal, state, county, municipal or other governmental agency in pursuance of its lawful activities or functions in the construction or improvement of public rights-of-way.
(e) The removal of trees from lakes and detention ponds and drainage easements.
(f) The removal of any tree which has become or threatens to become a danger to human life or property.
Section 9-205.1. Existing Tree Canopy Coverage.
(a) Prior to engaging in land disturbance or land development, it shall be the duty of land developers to calculate existing tree canopy coverage on any site to be disturbed or developed. To calculate existing tree canopy area, measure the average canopy radius for each tree retained. Use the formula: radius x 3.14 squared. Total the sum of tree canopy areas and divide the gross area to obtain canopy coverage.
(b) Sites with existing trees. The extent of tree canopy coverage can and shall be estimated based on a current or reasonably current (i.e., not more than three years from the date an application for land disturbance or land development is submitted) aerial photograph of the site. A copy of the aerial photograph utilized shall be provided as part of the application for land disturbance or land development. Estimates of tree canopy coverage should be verified in the field by the applicant (with date of field verification so noted in the application) and are subject to verification in the field by the city.
(c) Sites without trees. Where no tree canopy exists on the site to be subdivided, disturbed, or developed, the applicant shall indicate such in the application for land disturbance or land development with a landscape site plan.
(Amended 01/21/2025) Section 9-205.2. Existing Canopy to be Retained.
Where a development site or lot has an existing tree canopy, the developer or subdivider shall propose all or some of the existing trees be retained and designated as tree protection areas. In Critical Area Protection Areas (CAPA), significant trees must be retained. Outside of CAPA and perimeter landscaping buffers, existing significant trees and tree canopy are also incentivized for retention. The following provisions will apply to designation of tree protection areas for purposes of meeting the tree canopy requirements of this chapter:
(a) Existing tree canopy on the parcel of land to be subdivided, disturbed or developed should be retained to the maximum extent possible.
(b) Trees that conflict with the building envelope, that are within areas that must be cleared for parking and loading spaces, or in other places on the site where infrastructure must be installed, are to be approved for removal unless an alternative site design is considered feasible and the trees within such area are of high value as determined by the Zoning Administrator.
(c) If tree canopy must be and is authorized to be removed from the site, healthy, native hardwood trees that are 24 inches or more diameter breast height and significant stands of trees are the highest priority for retention. To incentivize retention of treesthat are 24 inches or more diameter breast height, such trees retained and protected per this chapter shall be given 1.5 times the future tree canopy listed in the Tree Species List or 1.5 times the actual tree canopy, whichever is greater. In such cases, the area of tree canopy for which credit is given shall always remain in tree canopy, and there shall be no other use of the area other than for tree growth. The area shall remain permeable and undeveloped. Pine tree canopy shall be considered the lowest priority for preservation.
(Amended 01/21/2025) Section 9-205.3. Minimum Tree Canopy Coverage Requirements by Land Use.
(a) Minimum ratios. All subdivisions and land developments shall meet the minimum tree canopy coverage requirements for the land use as indicated in Table for Minimum Tree Canopy Coverage Requirements by Land Use
Table 9-205.1 Table for Minimum Tree Canopy Coverage Requirements by Land Use Land Use Minimum Tree Canopy Coverage Required (% of development site or lot) Residential; single-family attached or twofamily subdivisions 35% Residential, multi-family 35% Residential, fee simple townhouse 15% Planned Unit Development Office or Institutional 50% Commercial 50% Commercial, downtown None Industrial 35% Mixed use 25% Note 1. The total site area included within a major residential subdivision shall be required to meet the requirements of this section at the time of preliminary platting, but individual lots within a major or minor subdivision shall not be subject to the minimum tree canopy coverage requirements of this section.
(b) Exemption for lakes and ponds. The area within natural or manmade bodies of water of two or more acres may be subtracted from calculations of tree canopy required.
(c) Determination, uncertainty, and interpretation. With respect to classifying land use for purposes of this section, the Zoning Administrator shall determine the land use as that use which is the principal use of the development site or lot. The Zoning Administrator shall be authorized to interpret the land use classifications in cases of uncertainty.
(d) Compliance. A major subdivision or land development may meet the minimum tree canopy coverage requirements of this section, by virtue of the tree canopy existing and to be retained on the site, in which case additional tree canopy coverage is encouraged but not required to be provided. Development sites and major subdivisions which have existing trees which result in a tree canopy coverage that meets or exceeds the requirements of this section will not be required to plant additional trees, except as may be required to meet parking lot landscaping, landscape strip, street tree planting, and/or buffer requirements of this land use management code. If a site does not have sufficient existing tree canopy, plans for the major subdivision or land development shall indicate additional tree planting in a manner that will meet the minimum requirements of this section.
(e) Timing of compliance. Compliance with the requirements of this chapter will be determined at the time of development plan review (including review of tree protection areas and a landscaping plan proposing tree canopy) for a land development and at the time of preliminary subdivision plat review for a major subdivision.
(f) Canopy cover credit for individual trees. For the purposes of this chapter, the tree canopy cover that is credited to an individual tree shall be either the actual square foot area of the crown's projection directly down onto the ground, or the tree canopy coverage at maturity as specified for the species as listed in the Commerce Tree Species List, whichever is greater. Any tree of a species not on the Commerce Tree Species List shall be given a tree canopy cover at maturity for the size typical of the species using standard landscaping references.
(Amended 01/21/2025) Section 9-205.4. Addition of Trees to Meet Minimum Tree Canopy Coverage Requirements.
(a) When required. When a development site or major subdivision does not meet the minimum tree canopy coverage required by this Section 9-205.3 via the maintenance of existing trees on site at the time of development or major subdivision, respectively, the developer or subdivider shall be required to plant trees on the development site or in the major subdivision’s boundaries sufficient to meet the requirements of Section 9-205.3.
(b) Locations. Trees may be planted throughout the development site or lot, although preference should be given to parking lots, and the front yard of the property.
(c) Species selection standards. Species shall be selected that are tolerant of growing conditions on the site, including growing space, sunlight, soil moisture, temperature and soil volume. No more than 25 percent of all trees planted on a lot shall be of any one species.
(d) Pine tree limitation. Where trees must be added to achieve the required tree canopy coverage requirement for the development site or lot, pine trees shall not comprise more than 25 percent of the tree canopy planted.
(Amended 01/21/2025) Section 9-205.5. Tree Bank.
(a) Tree bank established. Off-Site Mitigation (Tree Banking). An alternative means of compliance may be available in certain instances, called the Commerce Tree Bank, which is hereby established.
(b) Purchase of canopy credits. If the city determines that tree canopy coverage requirements of this chapter cannot be met on a particular site, due to lack of existing tree canopy coverage, a lack of suitable places on the development site, or within the subdivision to plant trees for canopy, or other condition that renders it impractical to fully comply with this chapter, owners of property confirmed by the city as being unable to achieve the tree canopy coverage requirements of this chapter on a particular site may at their option purchase canopy credits from the Commerce Tree Bank to compensate for tree canopy deficits.
(c) Limitations on purchase of tree canopy credits. All requirements for trees in required front landscape strips, parking lot interiors, and buffers must be met before donations to the tree fund in lieu of planting will be authorized, and in no case shall more than fifty percent (50%) of the tree canopy required on the site be satisfied by donations to the tree bank.
(d) Calculation of the cost of canopy credits. Canopy deficit is calculated by subtracting the area of tree canopy achieved on site by saved and planted trees from the required tree canopy coverage, rounded up to the nearest 900 square foot increment. Each 900- square foot increment shall equal one canopy credit. Canopy credits may be purchased from the Commerce Tree Bank at a cost of $400.00 per credit. This cost assignment is based on average wholesale cost for trees of various sizes that would provide comparable canopy, plus shipping, labor, installation, and a two-year maintenance program.
(e) Use of funds. Funds maintained in the Commerce Tree Bank shall be administered by the Zoning Administrator with consultation by the Commerce City Council and shall be spent on an appropriate combination of: (1) tree establishment on public properties and public rights of ways or within easements on private properties abutting street rights-of-ways which do not already have street trees alongside them; (2) maintenance of trees on public properties and public rights of ways or within easements on private properties abutting street rights of ways; (3) community education; and (4) Other environmental projects in which trees are an integral part. The Zoning Administrator shall establish an annual program for administration of these funds to be approved by the City Council as part of the annual City budget.
(Amended 01/21/2025) Sec. 9-208 Maintenance of Planted Trees.
The developer shall be responsible for replacing any tree that dies within three (3) years of the completion of the entire development or, if a phased development, within three (3) years of the completion of the phase in which the now dead tree was planted.
Sec. 9-209 Tree Replanting Standards.
Unless otherwise approved by the City Council or their designee, trees selected for replanting must be on the Tree Planting listed in Sec. 9-210. Trees selected from planting must be free from injury, pests, disease, nutritional disorders, or root defects, and must be of good vigor in order to assure a reasonable expectation of survivability. It is desirable that replanted trees be ecologically compatible with the site and neighboring sites. Accordingly, the replanted trees shall be of the same or similar species to those removed when practical.
Sec. 9-210 Recommended Species List of Trees Common Name Genus & Species Canopy Size Overstory Landscape Areas Road FrontageStreet Road FrontageYard Parking Lot Tree Islands 400 to 600 sq ft Parking Lot Tree Islands 100 to 399 sq ft Buffers Riparian /Drainage Areas Utility Corridors
OVERSTORY
Bald Cypress Taxodium distinchum Overstory X X Basswood, American (Linden) Tilia americana Overstory X X Beech, American Fagus grandifolia Overstory X X Birch, River (std.)
Betula nigra Midstory X X X X X Elm, Chinese Ulmus parvifolia Overstory X X Elm, Winged Ulmas alata Overstory X X X X Hickory Carya spp. Overstory X Honeylocust (seedless) Gleditsia triacanthos Overstory X Magnolia, Southern Magnolia grandiflora Overstory X X X Maple, Sugar Acer saccharum Overstory X X X X Oak, Black Quercus velutina Overstory X X X Oak, Chestnut Quercus prinus Overstory X X X X Oak, Laurel Quercus hemisphaerica Overstory X X X X Oak, Northern Red Quercus rubra Overstory X X X Oak, Nuttal Quercus nuttalli Overstory X X X X Oak, Overcup Quercus lyrata Overstory X X X X Oak, Post Quercus stellata Overstory X X X X Oak, Scarlet Quercus coccinea Overstory X X X X Oak, Shumard Quercus shumardii Overstory X X X X Oak, Swamp White Quercus bicolor Overstory X X X X Oak, Water Quercus nigra Overstory X X X Oak, White Quercus alba Overstory X X X X Oak, Willow Quercus phellos Overstory X X X X Pecan Carya illinoesis Overstory X X X Poplar, Tulip Liriodendron tulipifera Overstory X X Sweetgum (fruitless) Liquidambar styraciflua ‘Rotundiloba’ Overstory X X Sycamore, American Platanus occidnetalis Overstory X Walnut, Black Juglans nigra Overstory X X
MIDSTORY
Birch, River (std.)
Betula nigra Midstory X X X X X Cherrylaurel, Carolina Prunus caroliniana Midstory X X X X Hophornbeam, American Ostrya virginiana Midstory X X X Hornbeam, American Carpinus caroliniana Midstory X X X X X Locust, Black (seedless) Robinia pseudoacacia Midstory X X X Magnolia, Southern “Little Gem” Magnolia grandiflora ‘Little Gem’ Midstory X X X X X Magnolia, Sweetbay Magnolia virginiana Midstory X X X X Maple, Red (var.)
Acer rubrum Midstory X X X X X X Maple, Southern Sugar Acer barbatum Midstory X X X X X X X Pine, Virginia Pinus virginiana Midstory X Redcedar, Eastern Juniperus virginiana Midstory X X X Sassafras Sassafras albidum Midstory X X Silverbell, Carolina Halesia carolina Midstory X Sourwood Oxydendrum arboreum Midstory X X
UNDERSTORY
& SMALL
Hawthorn, Washington Crataegus phaenopyrum Understory X X X X Redbud, Eastern Cercis canadenssis Understory X X X X X X Alder, Hazel Alnus, serrulate Small X X X Holly, American Ilex opaca Small X X X (Amended 01/21/2025) Sec. 9-211. Tree protection fencing required.
(a) Protection. Trees protection areas shall be actively protected during land disturbance and land development with tree protection fencing, installed at the boundaries of all tree protection areas prior to any land development or land disturbance activity.
(b) Barrier required. Tree fencing shall be a minimum of 4 foot in height and comprised of chain-link fencing, orange laminated plastic fencing supported by posts, wooden post and rail fencing, or other equivalent barrier (see figure below).
(c) Duration. Tree protection fencing required by this section shall remain in place until land development and construction activities are complete, or a certificate of occupancy is issued, or until authorization is given by the Zoning Administrator to remove the tree protection fencing.
Tree Protection Detail Sec. 9-212. Prohibitions within tree protection areas.
Except as specifically authorized in this Article, tree protection areas shall remain in a natural, undisturbed condition; activities related to development within a tree protection area shall be prohibited. This specifically includes prohibition of the following within a tree protection area:
(a) vehicle or equipment parking, storage or traffic;
(b) materials or supplies storage;
(c) placement of temporary or permanent structures;
(d) equipment maintenance or washout;
(e) wounding of tree trunks; wounding or breakage of limbs or branches greater than four inches in diameter; topping or other improper pruning, such as stub cuts or flush cuts;
(f) fires or excessive heat from equipment exhausts;
(g) site or lot clearing or grubbing;
(h) soil excavation or soil cuts or fills;
(i) grading; trenching; tilling; soil compaction;
(j) top dressing with fill or soil greater than two inches in depth; and
(k) paving.
The Zoning Administrator may require that this section of the UDC appear verbatim on tree protection and landscaping plans.
Sec. 9-213. Tree damage.
Any tree within a tree protection area that is damaged during land disturbance, land development, or building or site construction shall be treated according to ANSI 300 standards. If damage necessitates removal of a tree, it shall be replaced with a tree or trees of similar species and size.
Sec. 9-301. Reference to requirements.
(a) Minimum requirements. Article 2, Table 2-2A of this UDC establishes minimum landscaped open space requirements for certain uses and minimum front landscape strips for certain uses. See also Article 4 for properties lying with the Highway Corridor Overlay District, which specifies additional landscaping requirements.
(b) Location and purpose. Required landscaping shall be installed in all yard areas, along the perimeter of the lot, around buildings, and all other portions of the property not specifically utilized for driveways, parking, loading, or other functions for which landscaping may not be practical as determined by the Zoning Administrator.
Landscaping shall be utilized for such purposes including, but not limited to:
1. Establishing a visual separation or screen of parking areas from the public right-of-way;
2. Providing a separation of pedestrian and service areas;
3. Providing a separation where the lot or parcel opposite of the boundary of the proposed development is a residentially zoned;
4. Providing a vertical transition from the grounds to the building;
5. Maintaining and enhancing natural drainage patterns; and
6. Maintaining the small-town character of Commerce through the aesthetics of landscaping as Commerce continues to grow.
(c) Partially developed lots. At the discretion of the Zoning Administrator, projects with substantial portions of the parcel area left for future development may be exempt from landscaping the undeveloped portion of the property. If any portion of the undeveloped area of the lot fronts a public right-of-way, standard improvements such as curb, gutter, sidewalk, and installation of street trees and other appropriate landscaping shall be required at the time of development.
(d) Expansion or additional development of lots. If a parcel with existing development is proposed for additional development, the Zoning Administrator has the discretion to review the landscaping installed on the entire property and may require improvements to be installed or conformance with other provisions of this section.
(e) Change of Use. When a structure's use is changed to a use other than single-family and there is no change in exterior appearance, the applicant shall conform with the landscaping requirements of this chapter.
(f) Exemption. Agriculture structures and agriculture uses in agricultural districts, Singlefamily and two-family dwellings unless required to install landscaping as a condition of project approval, and accessory dwelling units are exempt from the requirements of this division. Minor improvements or repairs to existing development that do not result in an increase in floor area are also exempt; however, major façade renovations may generate a landscaping requirement.
Sec. 9-302. Obstructions to sight visibility.
(a) All landscaping and trees planted adjacent to street rights of way and driveway intersections with rights of way must be installed in a manner that maintains minimum vision clearances on the adjacent right of way and the driveway approach.
(b) No shrub or tree with heights of between 2½ feet and 12 feet shall be located within 20 feet of the intersection of the right-of-way lines of streets, roads, highways or railroads, or within 20 feet of the intersection of a street right-of-way and either edge of a driveway.
(c) No landscaping shall be allowed that obstructs or impairs the vision of any vehicle operator at the intersection of any public rights-of-way, at any entrance onto or exit from a public road, or any other location where said obstruction would create a hazard to life or property.
Sec. 9-303. Frontage landscape strip.
(a) Width.
1. Minimum width. The minimum width of a frontage landscape strip shall be as specified in Table 2-2A and Table 2-2B of this UDC for the zoning district in which the development site is located, except as otherwise provided in this section.
2. Modification of width. The width of a minimum required frontage landscape strip shall typically be uniform across the frontage of the lot; provided, however, the Zoning Administrator may authorize the width of a minimum required frontage landscape strip to be varied so long as the total area of the frontage landscape strip equals or exceeds the total area that would otherwise be required for the frontage landscape strip. In no event shall a required frontage landscape strip be reduced to less than 3 feet under the provisions of this paragraph.
3. Natural vegetation in lieu of frontage landscape strip. The Zoning Administrator may authorize the retention of existing natural vegetation in lieu of a required frontage landscape strip, if retaining existing landscaping would provide an equivalent number of trees and shrubs as required by this section.
(b) Trees.
1. Planting rate. For any frontage landscape strip required by this UDC, trees shall be maintained or planted at the rate of at least one tree for every 40 feet of length of street frontage, or portion thereof (excluding driveways), for each 10 feet of required landscape strip width.
2. Spacing and arrangement. Trees may be spaced in a uniform manner or they may be clustered for a more natural or decorative arrangement.
3. Species. Such trees may be hardwoods or softwoods, but must be of a type that is suitable to local growing conditions.
4. Minimum size. At the time of planting, trees within required front landscape strips shall have a minimum caliper of at least 2 inches.
(c) Shrubs.
1. Rate. Shrubs shall be installed within any required frontage landscape strip at the rate of at least 10 shrubs for every 40 feet of length of street frontage, or portion thereof (excluding driveways), for each 10 feet of required landscape strip width.
2. Minimum size. Shrubs installed within any required frontage landscape strip must be at least 18 inches in height at the time of planting and must be capable of reaching a height of at least 2 feet at maturity.
(d) Authorized accessory uses within front landscape strips. The following uses are authorized within frontage landscape strips:
1. Driveways and sidewalks. Driveways and sidewalks may be located within a required frontage landscape strip to the extent needed to cross the landscape strip.
2. Walls. Retaining walls, and walls or fences authorized by the Zoning Administrator for screening or aesthetic effect, may be located in a required frontage landscape strip.
3. Signage. If permitted by this UDC, a ground sign may be located within a required frontage landscape strip.
4. Utilities. Underground utilities may cross a required frontage landscape strip. Fire hydrants shall also be authorized to be located within a required frontage landscape strip.
5. Stormwater. Detention ponds shall not be authorized within required frontage landscape strips. However, a land development project that incorporates low impact development principles consistent with the Georgia Stormwater Management Manual (e.g., vegetative swale) may be authorized by the Zoning Administrator to be located within required frontage landscape strip. Stormwater Best Management Practices (BMPs) may be applied or incorporated within front landscaping strips, and a front landscaping strip may if appropriate be accepted as a BMP.
(e) Relationship to utility easements. Where a development site has an existing or proposed utility easement abutting and running parallel or approximately parallel to the right of way in the same location as a minimum required frontage landscape strip, the landscape strip shall be relocated interior to the utility easement that abuts and parallels or approximately parallels the right of way; provided, however, the Zoning Administrator may authorize part of the minimum frontage landscape strip be located within the utility easement only if the utility easement owner authorizes the planting of trees and shrubs within the utility easement.
Sec. 9-304. Side lot line landscape strips.
Landscape strips alongside lot lines are not required except when screening of a parking lot is required, in which case a side landscape strip along the parking lot shall be provided.
Sec. 9-305. Parking lot landscaping.
(a) Applicability. This section shall apply to parking lots with 10 or more car parking spaces.
(b) Planting island. One parking lot tree for each 10 car parking spaces is required and shall be installed. No more than 10 contiguous car parking spaces shall be allowed without a minimum of one landscape island or peninsula containing one or more trees.
Illustrative Parking Lot Landscaping
(c) Minimum dimensions of islands. A landscape island within a parking lot shall have a minimum width of 9 feet and minimum depth of 16 feet measured from interior face of curb to interior face of curb; however, wider (12 or more feet) landscaping islands are strongly encouraged and may be required to provide sufficient growing area for certain canopy tree species selected.
Parking Lot Landscaping Island Detail Sec. 9-306. Approval of plant materials.
The Zoning Administrator is authorized to promulgate and publish and amend from time to time a list of approved plant species. Specific landscaping, trees, and buffer material are subject to the approval of the Zoning Administrator. For properties within the Highway Corridor Overlay District, see Sec. 4-217 of this UDC for planting list.
Sec. 9-307. General landscaping requirements.
(a) Native plants. The use of native plants is encouraged.
(b) Invasive and exotic species. Invasive or potentially invasive plants and exotic plants are prohibited.
(c) Xeriscaping and water conservation. Xeriscaping is encouraged. Ground covers should be used to supplement landscaping in appropriate areas to reduce extensive grass lawns that require regular watering in drought conditions.
(d) Trees. Trees selected for planting must be free from injury, pests, disease, nutritional disorders or root defects, and must be of good vigor in order to assure a reasonable expectation of survivability.
(e) Diversity. No more than 25% of trees or shrubs planted on any given site shall consist of any one species.
(f) Grass. Grass lawn areas should be sodded. However, if grass seed must be used, it shall be a variety suitable to the area that produces complete coverage as approved by the Zoning Administrator.
(g) Artificial landscaping. No artificial plants, trees, turf, or other vegetation shall be installed.
(h) ANSI 300 standards. Landscaping shall meet the requirements of ANSI 300 unless otherwise approved by the Zoning Administrator.
(i) Curb Stops. A curb or wheel stop shall be provided along interior parking lot landscape islands, perimeter landscape strips, and landscapes adjacent to street rights-of-ways, to prevent cars from encroaching on trees, shrubs, and landscapes, as approved by the Zoning Administrator.
(d) Minimum planting. Each landscape island shall contain a minimum of one tree having a minimum caliper of two inches at the time of planting.
Sec. 9-308. Parking lot screening.
(a) General. If the land development includes 10 or more parking spaces within a front yard, the shrubs must be arranged to provide a continuous visual screen to a height of three feet above grade between the front right of way and the parking lot. If the land development includes 10 or more parking spaces within a side yard, the shrubs must be arranged to provide a visual screen along the front right of way and that portion of the side yard parking lot. Where parking spaces within a front yard are visible from the front public right of way even with the frontage landscape strip, the continuous visual screen required by this subsection shall be extended along the side lot line for the length of the parking area that is visible from front public right of way. Parking lot screening may require the planting of shrubs at a higher rate than is otherwise be required by this Article.
(b) Perimeter parking lot landscaping: The parking lot perimeter landscaping requirements apply to all off-street parking lots that are not otherwise fully screened from view of adjacent public right-of-way. When a lot is located adjacent to a public right-of-way, alternatives should be considered to reduce the visual impact of the parking lot.
1. Use of landscape perimeter borders: Required landscape borders shall be dedicated solely for open space and landscaping. No structures of paving shall be located within the border area, with the exception of walls, walkways or other features incorporated into the landscaping.
2. Perimeter landscape border options: Any of the following types of perimeter landscape border detailed in the below chart, may be used to satisfy parking lot border landscaping requirements of this section.
Parking Lot Landscaping Screening Requirements Type (See Fig.
4.2 to Determine Type) Maximum Distance from Any Property Line Across Paved Parking Area Minimum Border Width Minimum Plant Units per 27 Feet of Perimeter Parking Area Minimum Required Site Features A applies to any parking2 25 10 — B 1501 10 20 — C 1001 8 15 24;inch;— 30;inch; berm3 D 1001 5 10 3 ft. wall4 E Type E Border provides an Alternative Plan option to provide flexibility and the opportunity for creativity. The Alternative Plan shall accomplish the purpose of this border Section and meet or exceed the requirements in this section to the satisfaction of the Zoning Administrator. 1 Minimum number of plant units: The minimum number of plant units to be located within the parking perimeter border shall be in addition to the requirements for the square footage of the lot. The number of units shall be calculated based upon the perimeter of the parking area.
2 Type A parking borders may be used on any parking lot. If the depth of the parking lot measured from the property line is more than 150 feet. Type A parking border shall be required. If the depth is from 100 to 150 feet, a Type A or Type B border is required. If the depth is less than 100 feet, Type A, B, C, or D border shall be required. The applicant may select the optional border. Depending on site design, a single site may have more than one landscape parking border type.
3 Landscaping is required on the berm.
4 On property line fronting a public or private road as required by the Zoning Administrator. Landscaping is required in between the wall and right-of-way.
3. Parking lot interior landscaping requirements. The parking lot interior landscaping requirements apply to the interior of all off-street parking lots that contain five or more parking spaces. Interior Planting Areas are required within all parking lots as specified in the subsection.
4. The size of planting areas used to satisfy parking lot interior landscaping requirements shall be sufficient to protect plant materials and ensure proper growth and maintenance.
5. Parking lot landscaping requirements when more than the maximum number of parking space is approved.
a. All aisles shall have landscaped areas at each end of the aisle.
b. Landscaped medians at least ten feet in width shall be required for aisles that align with street access.
Sec. 9-309. Plans.
(a) For any land disturbance, land development, or building subject to the requirements of this Article, buffer, tree protection and landscaping plans are required to be submitted with any application for a land disturbance permit, development permit, tertiary land disturbance permit, or for a building permit for new construction of buildings.
(b) Landscaping plans shall be of adequate size and detail so that the Zoning Administrator can see the land area to be planted and the appearance of plantings at the time of installation, at five years healthy growth, and at ten years healthy growth.
(c) Landscaping site plans and elevations shall be drawn in a professional manner with credible representations of drip lines, plant growth diameters, and plant sizes. The Zoning Administrator shall not require that plans and elevations be prepared by a licensed professional, but the Planning Commission may reject plans which do not accurately depict the site landscaping proposal in suitable detail for it to make a decision.
(d) Landscaping plans shall be accompanied by a planting schedule that identifies both the common and botanical name of each species. The schedule shall include the size at planting, the size a five years of growth, and ten years of growth if the proposed plants are different than the adopted plant schedule.
(e) Buffer, tree protection and landscaping plans shall be required for only that phase of development for which the land-disturbance permit, tertiary land-disturbance permit, development permit or building permit is being requested.
Sec. 9-310. Contents of tree protection and landscaping plans.
Tree protection and landscaping plans shall meet the following minimum requirements:
(a) A site plan with property boundaries, proposed buildings, parking areas, loading areas, required buffers, utility easements if any, and other pertinent information as may be required by the Zoning Administrator. The site plan shall show the location of all trees, shrubs, and landscaping.
(b) A planting schedule for all trees, shrubs, and ground covers proposed, with botanical name and common names of each species, the total number of each species planted, and total numbers of trees. Trees and shrubs shall be indicated on the plan using symbols and the symbols must appear in the planting schedule.
(c) Calculations demonstrating the plan meets the following, if applicable:
1. Minimum landscaped open space specified in Table 2-2A and Table 2-2B for the zoning district in which the property is located.
2. Required number of trees and shrubs within any required frontage landscape strip.
3. Parking lot landscaping requirements.
4. Zoning buffer and parking lot screening requirements.
(d) Standard details and notes with regard to planting instructions.
Sec. 9-311. Review of Landscape Plans In reviewing proposed performance landscape plans, favorable consideration shall be given to exceptional landscape designs that preserve and incorporate existing vegetation and demonstrate innovative design and use of plant materials. Performance landscape plans may be approved upon a finding that the plan meets or exceeds the purposes and objective of this section thorough either:
(a) Natural land characteristics or existing vegetation on the proposed development site;
or
(b) Innovative landscaping or architectural design.
Sec. 9-312. Maintenance of landscaping.
(a) Plants that are diseased, damaged beyond point of survival, or are dead shall be removed and replaced with a plant of the same species, variety or cultivator, as approved by the Zoning Administrator.
(b) All landscape materials shall be maintained and shall be kept clear of refuse and debris.
Sec. 9-313. Inspection.
An inspection shall be made by the Zoning Administrator of all landscape plantings to assure compliance with plan requirements prior to approval of a certificate of occupancy.
Sec. 9-314. Delayed installation and temporary occupancy requirements.
(a) Delayed installation. The Zoning Administrator may authorize the delay of planting in cases of drought or inappropriate season for planting, in which case the Zoning Administrator shall require a bond or other appropriate surety in an amount equal to the estimated costs of the landscaping deferred.
(b) Temporary occupancy requirements. A temporary certificate of occupancy may be issued prior to the installation of required landscaping upon execution of an agreement with the city and acceptance by the city of appropriate surety.
1. Land development that does not require or is normally utilized without obtaining a certificate of occupancy shall have landscaping installed per this section prior to the initiation of any use or any occupancy of the facility, structure, or grounds.
2. An agreement for temporary occupancy shall be used only under extenuating circumstances which prohibit the physical installation of landscaping at the time the certificate of occupancy is issued (drought, flooding, etc.). Financial or similar issues shall not constitute extenuating circumstances for the purposes of this section.
(c) Bond(s) required. Financial surety shall be equal to 110 percent of the estimated cost of the plant material, labor, and installation, and other materials.
1. The amount of the surety shall be calculated from a written cost estimate prepared by an appropriately licensed professional and provided to the Zoning
Administrator by the developer. If the Zoning Administrator finds that the cost estimates are not generally within accepted standards for estimating the costs of landscaping installation, the mayor shall require that surety be based on accepted estimating practices.
2. Each estimate shall be guaranteed valid at the maturity of the surety instrument.
3. An irrevocable letter of credit, security bond, performance bond issued by a bonding company, or any combination thereof shall be acceptable forms of surety.
Article 10 Stormwater Management
ARTICLE 10
STORMWATER MANAGEMENT
DIVISION I STORMWATER MANAGEMENT
DIVISION II DRAINAGE SPECIFICATIONS
Sec. 10-101. Findings.
(a) Land development projects and other land use conversions, and their associated changes to land cover, permanently alter the hydrologic response of local watersheds and increase stormwater runoff rates and volumes, which in turn increase flooding, stream channel erosion, and sediment transport and deposition.
(b) Land development projects and other land use conversions also contribute to increased nonpoint source pollution and degradation of receiving waters.
(c) The impacts of post-development stormwater runoff quantity and quality can adversely affect public safety, public and private property, drinking water supplies, recreation, fish and other aquatic life, property values and other uses of lands and waters.
(d) These adverse impacts can be controlled and minimized through regulation of stormwater runoff quantity and quality from land development by the use of structural facilities as well as nonstructural measures, such as the conservation of greenspace.
Sec. 10-102. Definitions.
Bioretention: A practice to manage and treat stormwater runoff by using a conditioned planting soil bed and planting materials to filter runoff stored within a shallow depression. The method combines physical filtering and adsorption with biological processes.
Channel: A natural or artificial watercourse with a definite bed and banks that conducts continuously or periodically flowing water.
Clean Water Act: The Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.), and any subsequent amendments thereto.
Construction activity: Activities subject to the Georgia Erosion and Sedimentation Control Act or NPDES General Construction Permits. These include construction projects resulting in land disturbance. Such activities include but are not limited to clearing and grubbing, grading, excavating, and demolition.
Conveyance: An aboveground or underground natural or man-made drainage feature, that provides for the collection and movement of stormwater, and shall include but not be limited to concrete or metal pipes, ditches, depressions, swales, roads with drainage systems, highways, city or county streets, curbs, gutters, inlets, catch basins, piped storm drains, pumping facilities, structural stormwater controls, drainage channels, reservoirs, rights of way, storm drains, culverts, street gutters, oil/water separators, modular pavements and other similar drainage structures.
Detention: The temporary storage of stormwater runoff in a stormwater management facility for the purpose of controlling peak discharge.
Detention facility: A retention basin or structure designed for temporary storage of stormwater runoff and gradual release of stored water at controlled rates.
Drainage: A general term applied to the removal of surface or subsurface water from a given area either by gravity or by pumping; most commonly applied to surface water.
Drainage easement: An easement appurtenant or attached to a tract or parcel of land allowing the owner of adjacent tracts or other persons to discharge stormwater runoff onto the tract or parcel of land subject to the terms of the drainage easement.
Drainage structure: A device composed of a virtually non-erodible material such as concrete, steel, plastic or other such material that conveys water from one place to another by intercepting the flow and carrying it to a release point for stormwater management, drainage control or flood control purposes.
Drainage system: The surface and subsurface system for the removal of water from the land, including both the natural elements of streams, marshes, swales and ponds, whether of an intermittent or continuous nature, and the man-made element which includes culverts, ditches, channels, detention facilities and the storm sewer system.
Dry well: A small excavated pit backfilled with aggregate, usually pea gravel or stone. Dry wells function as infiltration systems used to control runoff from building rooftops. Another special application of dry wells is modified catch basins, where inflow is a form of direct surface runoff.
Dry wells provide the majority of treatment by processes related to soil infiltration, including absorption, trapping, filtering, and bacterial degradation.
Erosion and sedimentation control plan: A plan designed to minimize the accelerated erosion and sediment runoff at a site during land disturbance activities.
Extended detention: The detention of stormwater runoff for an extended period, typically 24 hours or greater.
Filter strip: Typically, a band of close-growing vegetation, usually grass, planted between pollutant source areas and a downstream receiving waterbody. Vegetation can filter sediment from runoff. Thus, grass strips can be used to remove sediment from surface runoff. Vegetation also slows the velocity of runoff and helps maintain the infiltration capacity of a soil.
Georgia Stormwater Management Manual: A three-volume set which provides policy and technical details to implement this Article. The manual may be revised from time to time but at the time this Article is adopted includes: Volume 1: Local Government Guide (Latest Edition);
Volume 2: Technical Handbook (Laterst Edition); Georgia EPD placed the Manual in the Georgia State Highway Phase II stormwater permit that was released in 2016. The final GSMM is available at http://atlantaregional.com/environment/georgia-stormwater-manual.
Infiltration: The process by which stormwater runoff percolates into the subsoil.
Infiltration trench: An excavated trench that has been back-filled with stone to form a subsurface basin. Stormwater runoff is diverted into the trench and is stored until it can be infiltrated into the soil, usually over a period of several days. An infiltration trench may include pretreatment such as vegetated filter strips or grassed swales.
Level spreader: Typically, an outlet designed to convert concentrated runoff to sheet flow and disperse it uniformly across a slope to prevent erosion. Level spreaders can be used to convey sheet flow runoff from lawn areas within graded areas to bioretention facilities and transition areas.
Low-impact development: The integration of site ecological and environmental goals and requirements into all phases of urban planning and design from the individual lot level to the entire watershed. In the context of this Article, low-impact development is a set of stormwater design practices that are non-structural stormwater controls, specifically stormwater better site design practices.
National Pollutant Discharge Elimination System (NPDES) stormwater discharge permit: A permit issued by the Georgia EPD under authority delegated pursuant to 33 USC § 1342(b) that authorizes the discharge of pollutants to waters of the United States, whether the permit is applicable on an individual, group, or general area-wide basis.
Natural, undisturbed conditions: For redevelopment projects or where there are no flooding concerns, this term shall mean the condition of the site immediately prior to the implementation of the proposed project.
New development: A land development activity on a previously undisturbed site that has been maintained in a natural state.
Nonpoint source pollution: A form of water pollution that does not originate from a discrete point such as a sewage treatment plant or industrial plant discharge, but involves the transport of pollutants such as sediment, fertilizers, pesticides, heavy metals, oil, grease, bacteria, organic materials, and other contaminants from land to surface water and groundwater via mechanisms such as precipitation, stormwater runoff and leaching. Nonpoint source pollution is a by-product of land use practices such as agricultural, silvicultural, mining, construction and subsurface disposal as well as from urban runoff sources.
Nonstructural stormwater management practice or nonstructural practice: Any natural or planted vegetation or other nonstructural component of the stormwater management plan that enhances stormwater quantity and/or quality control or other stormwater management benefits and includes, but is not limited to, riparian buffers, greenspace areas, overland flow filtration areas, natural basins and vegetated channels.
Off-site facility: A stormwater management facility located outside the boundaries of a development site.
On-site facility. A stormwater management facility located within the boundaries of a development site.
Permeable: Soil or other material that allows the infiltration or passage of water or other liquids.
Pollutant: Anything that causes or contributes to pollution. Pollutants may include, but are not limited to: paints, varnishes, and solvents; petroleum hydrocarbons; automotive fluids; cooking grease; detergents (biodegradable or otherwise); degreasers; cleaning chemicals; non-hazardous liquid and solid wastes and yard wastes; refuse, rubbish, garbage, litter, or other discarded or abandoned objects and accumulations, so that same may cause or contribute to pollution;
floatables; pesticides, herbicides, and fertilizers; liquid and solid wastes; process waste water and wash water; sewage, fecal coliform and pathogens; dissolved and particulate metals; animal wastes; wastes and residues that result from constructing a building or structure; concrete and cement; and noxious or offensive matter of any kind.
Pollution: The man-made or man-induced alteration of the chemical, physical, biological, thermal and radiological integrity of water.
Regional stormwater management facility or regional facility: Stormwater management facilities designed to control stormwater runoff from multiple properties where the owners or developers of the individual properties may assist in financing the facility and the requirement for on-site stormwater management facilities is either eliminated or reduced.
Stormwater better site design: Nonstructural site design approaches and techniques that can reduce the impact of a site on the watershed and can provide for nonstructural stormwater management. Stormwater better site design includes conserving and protecting natural areas and greenspace, reducing impervious cover and using natural features for stormwater management.
Stormwater credits for better site design: A set of stormwater “credits” can be used to provide developers and site designers an incentive to implement better site design practices that can reduce the volume of stormwater runoff and minimize the pollutant loads from a site. The credit system directly translates into cost savings to the developer by reducing the size of structural stormwater control and conveyance facilities.
Stormwater management: The collection, conveyance, storage, treatment and disposal of stormwater runoff in a manner intended to prevent increased flood damage, stream bank channel erosion and habitat and water quality degradation, and to enhance and promote public health, safety and general welfare.
Stormwater management facility: Any infrastructure that controls or conveys stormwater runoff.
Stormwater management measure: Any stormwater management facility or nonstructural stormwater practice.
Stormwater management plan: A document describing the manner in which existing runoff characteristics will be affected by a land development project and containing measures for complying with the provisions of this Article.
Stormwater management system: The full array of structural and nonstructural stormwater management facilities and practices used to capture, convey and control the quantity and quality of the stormwater runoff from a site.
Stormwater retrofit: A stormwater management practice designed for a developed site that previously had either no stormwater management practice in place or a practice inadequate to meet the stormwater management requirements of the site.
Stormwater runoff: The flow of surface water resulting from precipitation.
Structural stormwater control: A structural stormwater management facility or device that controls stormwater runoff and changes the characteristics of that runoff including, but not limited to, the quantity and quality, the period of release or the velocity of flow of such runoff.
Swale: An open drainage channel designed to detain or infiltrate stormwater runoff. Grassed swales consist of two types: the dry swale, which provides both quantity (volume) and quality control by facilitating stormwater infiltration; and the wet swale, which uses residence time and natural growth to reduce peak discharge and provide water quality treatment before discharge to a downstream location.
Sec. 10-103. Applicability.
(a) No person, owner or developer shall perform any land development activities without first meeting the applicable requirements of this Article prior to commencing the proposed activity.
(b) Unless specifically exempted by this Article, all persons proposing development or construction shall prepare and submit a stormwater management plan for approval by the Zoning Administrator as a part of the development and/or land-disturbing permitting processes required by Articles 7 and 8, respectively, of this UDC.
Sec. 10-104. Exemptions.
The following activities are exempt from this Article:
(a) Individual single-family or duplex residential lots that are not part of a subdivision or phased development project with less than 1.0 acres of disturbed area;
(b) Additions or modifications to existing single-family or duplex residential structures;
(c) Agricultural or silvicultural land management activities within areas lawfully used or zoned for these activities; and,
(d) Repairs to any stormwater management facility or practice deemed necessary by the Public Works Director or their designee.
(e) Land disturbing activity conducted by local, state, authority, or federal agencies, solely to respond to an emergency need to protect life, limb, or property or conduct emergency repairs or are under 1.0 acres.
Sec. 10-105. Approval of stormwater management plan.
No final plat for a major subdivision, no land-disturbance or development permit, and no building permit shall be approved or issued until and unless the stormwater management plan, if required by this Article, has been reviewed and approved by the Public Works Director or designee.
Sec. 10-106. Installation of an adequate drainage system.
(a) An adequate drainage system, including necessary ditches, pipes, culverts, drains, inlets, or other stormwater management features which may include better design practices, shall be provided for the proper drainage or infiltration of all surface water on all development and construction sites unless specifically exempted by this Article.
(b) The location and size of all proposed drainage improvements shall be designed in accordance with and meet all standards relating to stormwater drainage under this Article and technical standards of this UDC as applicable.
(c) Stormwater drainage facilities shall be installed in accordance with the approved stormwater management plan. Construction of the stormwater system shall be initiated as part of the grading of the site. Stormwater Management facilities shall be constructed prior to the installation of any other site improvements and may be utilized under proper design as sedimentation basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and ditches shall be coordinated with the construction of streets and other site improvements, as appropriate.
Sec. 10-107. Contents of stormwater management plan.
A stormwater management plan, when required, shall include sufficient information to evaluate the environmental characteristics of the affected areas, the potential impacts of the proposed development on water resources, and the effectiveness and acceptability of measures proposed for managing stormwater runoff. Information included shall meet the requirements of the Georgia Stormwater Management Manual, Latest Edition. Additionally, the following information shall be provided:
(a) Size and location of existing storm sewers, drains, culverts, or other underground facilities within the tract or within the right-of-way of streets or roads adjoining the tract.
Grades and invert elevations of storm sewers shall be shown.
(b) Location and profiles of all storm drainage pipes and slopes of receiving channels.
(c) 25-year design storm hydraulic grade lines shall be shown on all pipes that cross streets and 100-year on stormwater management system outfalls. Hydraulic grade lines shall fall below the crown of the proposed pipe.
(d) Stormwater management system location, design and construction details, including a soils map and investigation for all sites proposed as ponds or impoundments or for stormwater detention. Construction details shall include appropriate access (minimum 20- foot-wide access easement), a gravel access drive, fencing with locked gate, and landscaping to screen the installation.
(e) Location and typical construction details of all inlets and catch basins, headwalls, and other drainage structures.
(f) Gutter spread calculations showing no more than 6’ lane encroachment for the 25-year Design Storm for each proposed catch basin and the 100-year ponding limits above each inlet headwall.
(g) Hydrologic and hydrologic analysis for the storm drainage system design.
(h) Pre-development and Post-development drainage area maps are required. No increase in peak runoff shall be allowed. For the Pre and Post conditions time of concentration (Tc) calculations must be provided along with all soil runoff coefficients.
Sec. 10-108. System maintenance.
(a) It shall be the responsibility of the developer to maintain all facilities required by the stormwater management plan during construction and for a two–year maintenance period following approval of a final subdivision plat or issuance of a certificate of occupancy, as applicable. The developer shall be responsible for removing temporary structures or facilities at the completion of the construction.
(b) The owner of the property shall be responsible for maintaining the permanent stormwater management facilities identified by the stormwater management plan to remain after construction is complete, following the two-year maintenance period.
(c) Should an owner or developer, whichever is the responsible party, fail to maintain the stormwater management facilities in a state of service intended by the stormwater management plan, then the Zoning Administrator shall notify the responsible party in writing of the deficiencies and specific minimum maintenance requirements to remedy such deficiencies.
(d) If the responsible party fails to perform the required maintenance work within a reasonable period of time (30 days maximum), then the owner shall be in violation of this
UDC.
Sec. 10-109. Location of stormwater detention facilities.
(a) In residential subdivisions, any detention facility must be located on a separate lot and owned by a homeowners’ association, which shall be responsible for its maintenance and continuing operation. The lot need not meet minimum lot size, minimum lot width, and minimum frontage requirements for the subdivision or the zoning district in which it is located.
(b) In nonresidential subdivisions, any detention facility may be located on a separate lot and owned by a property owners’ association, which shall be responsible for its maintenance and continuing operation; or located on each lot within the subdivision and constructed when the lot is developed.
(c) In multi-family residential and nonresidential development projects, detention facilities shall be provided for each development. The owner of the property shall be responsible for maintenance and continuing operation of the facilities.
(d) Stormwater detention facilities serving two or more developments may be approved by the zoning administrator, provided that private ownership of the facilities and provisions for their perpetual maintenance and continuing operation are clearly established in a manner acceptable to the zoning administrator. The City has the right, but not the obligation, to perform necessary maintenance and will bill the responsible party.
Sec. 10-201. All drainage structures.
(a) Allstorm water drainage structuresshall bedesigned tosafely accommodate the 25- year, twenty-four-hourevent.
(b) The drainage formula used in design of all drainage structures shall bedetermined by thedeveloper’sstate-approved professional engineer and based on sound engineering practice.
(c) Methodology used for the design of detention facilities shall be the Soil Conservation Service method using a Type II rainfall distribution.
Sec. 10-202. Design for detention and retention ponds.
Stormwatermanagementstructures(i.e.detention andretention)shall bedesigned based upon the 2, 5, 10, 25, 50 and 100-year, twenty-four hour events.
Sec. 10-203. Required pipe materials.
(a) All cross-drain pipes under streets carrying live streams and all bridges shall be designed for a 100-year storm event and shall be constructed of reinforced concrete pipe (RCP) from headwall to headwall or double walled High-Density Polyethylene
(HDPE).
(b) All piping within the right-of-way shall be RCP or double walled HDPE.
(c) Piping outside of the right-of-way may be reinforced concrete pipe (RCP) or doublewalled HDPE.
Sec. 10-204. Headwalls.
(a) The inlet and outlet end of all storm drain pipes for streets shall have concrete headwalls or ametalflared-end section with safety grates, city-approved grate and frame, or raised pedestal drop inlets meeting the standards of the Georgia DOT.
(b) Reinforced concrete headwalls are required for all pipes on live streams.
(c) All cross drainpipes that carry water from one side of the roadway to the other that are 30 inches in diameter or larger shall have cast in place headwalls on both the inlet and outlet ends per GDOT Standard 1125.
Sec. 10-205. Pipe sizes.
All drainage pipesin a city right-of-way shall be aminimum of 18 inches in diameter.
Sec. 10-206. Drainage ditches.
All man-made storm water drainage ditches shall be designed by a state-approved professional engineer. The ditch profile and typical cross sections, including the velocity of flow, drainage area, and normal depth shall be shown on plans. All ditchesshall be checked forshearstress and appropriate liners, grassing orrip-rap shall be specified. Under no condition will an unlined ditch be approved for velocities in excess of five FPS.
Article 11 Flood Damage Prevention
ARTICLE 11
FLOOD DAMAGE PREVENTION
DIVISION I GENERAL PROVISIONS
DIVISION II PERMITTING REQUIREMENTS
DIVISION III PROVISIONS FOR FLOOD HAZARD REDUCTION
floodway (A-zones).
Sec. 11-309. Standards for areas of special flood hazard (Zones AE) with established base flood elevations without designated floodways.
DIVISION IV VARIANCES AND APPEALS
Sec. 11-101. Authority.
Article IX, Section II of the Constitution of the State of Georgia and Section 36-1-20(a) of the Official Code of Georgia Annotated have delegated the responsibility to local governmental units to adopt regulations designed to promote the public health, safety, and general welfare of its citizenry.
Sec. 11-102. Findings.
(a) The flood hazard areas of Commerce, Georgia are subject to periodic inundation which results in loss of life and property, health and safety hazards, disruption of commerce and governmental services, extraordinary public expenditures for flood relief and protection, and impairment of the tax base, all of which adversely affect the public health, safety and general welfare.
(b) These flood losses are caused by the occupancy in flood hazard areas of uses vulnerable to floods, which are inadequately elevated, flood-proofed, or otherwise unprotected from flood damages, and by the cumulative effect of obstructions in floodplains causing increases in flood heights and velocities.
(c) The degree of flood protection required by this Article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur; flood heights may be increased by man-made or natural causes. This Article does not imply that land outside the areas of special flood hazard or uses permitted within such areas will be free from flooding or flood damages. This Article shall not create liability on the part of the City of Commerce, or by any officer or employee thereof for any flood damage that results from reliance on this Article, or any administrative decision lawfully made hereunder.
Sec. 11-103. Purposes.
It is the purpose of this Article to promote the public health, safety, and general welfare and to minimize public and private losses due to flood conditions in specific areas by provisions applicable in the City of Commerce designed to:
(a) Require that uses vulnerable to floods, including facilities, which serve such uses, be protected against flood damage at the time of initial construction;
(b) Restrict or prohibit uses which are dangerous to health, safety and property due to water or erosion hazards, or which increase flood heights, velocities, or erosion;
(c) Control filling, grading, dredging and other development which may increase flood damage or erosion;
(d) Prevent or regulate the construction of flood barriers which will unnaturally divert flood waters or which may increase flood hazards to other lands; and
(e) Control the alteration of natural floodplains, stream channels, and natural protective barriers, which are involved in the accommodation of floodwaters.
Sec. 11-104. Objectives.
The objectives of this Article are to:
(a) Protect human life and health;
(b) Minimize damage to public facilities and utilities such as water and gas mains, electric, telephone and sewer lines, streets and bridges located in floodplains
(c) Help maintain a stable tax base by providing for the sound use and development of flood prone areas in such a manner as to minimize flood blight areas,
(d) Minimize expenditure of public money for costly flood control projects;
(e) Minimize the need for rescue and relief efforts associated with flooding and generally undertaken at the expense of the general public;
(f) Minimize prolonged business interruptions, and;
(g) Ensure that potential homebuyers are notified that property is in a flood area.
Sec. 11-105. Applicability.
This ordinance shall apply to all areas of special flood hazard within the city limits of Commerce, Georgia.
Sec. 11-106. Definitions.
Unless specifically defined below, words or phrases used in this section shall be interpreted so as to give them the meaning they have in common usage and to give this section its most reasonable application.
Accessory structure: A structure having minimal value and used for parking, storage and other non-habitable uses, such as garages, carports, storage sheds, pole barns, hay sheds and the like.
Addition (to an existing building): Any walled and roofed expansion to the perimeter of a building in which the addition is connected by a common load-bearing wall other than a firewall.
Any walled and roofed addition, which is connected by a firewall or is separated by an independent perimeter load-bearing wall, shall be considered “new construction.”
Administrator: The Zoning Administrator of the City of Commerce, Georgia.
Appeal: A request for a review of the zoning administrator’s interpretation of any provision of this Article.
Area of shallow flooding: A designated AO or AH Zone on a community's Flood Insurance Rate Map (FIRM) with base flood depths from one to three feet, and/or where a clearly defined channel does not exist, where the path of flooding is unpredictable and indeterminate, and where velocity flow may be evident.
Area of special flood hazard: The land in the floodplain within a community subject to a one percent or greater chance of flooding in any given year. In the absence of official designation by the Federal Emergency Management Agency, Areas of Special Flood Hazard shall be those designated by the local community and referenced in this Article.
Base flood: The flood having a one percent chance of being equaled or exceeded in any given year.
Base Flood Elevation (BFE): The elevation shown on the Flood Insurance Rate Map for Zones AE, AH, A1-A30, AR, AR/A, AR/AE, AR/A1-A30, AR/AH, AR/AO, V1-V30, and VE that indicates the water surface elevation resulting from a flood that has a one percent chance of equaling or exceeding that level in any given year.
Basement: That portion of a building having its floor sub grade (below ground level) on all sides.
Building: Any structure built for support, shelter, or enclosure for any occupancy or storage.
Critical facility: Any public or private facility, which, if flooded, would create an added dimension to the disaster or would increase the hazard to life and health. Critical facilities include: structures or facilities that produce, use, or store highly volatile, flammable, explosive, toxic, or water-reactive materials; hospitals and nursing homes, and housing for the elderly, which are likely to contain occupants who may not be sufficiently mobile to avoid the loss of life or injury during flood and storm events; emergency operation centers or data storage centers which contain records or services that may become lost or inoperative during flood and storm events; and generating plants, and other principal points of utility lines.
Development: Any man-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavating, drilling operations, and storage of materials or equipment.
Elevated building: A non-basement building built to have the lowest floor of the lowest enclosed area elevated above the ground level by means of fill, solid foundation perimeter walls, pilings, columns, piers, or shear walls adequately anchored so as not to impair the structural integrity of the building during a base flood event.
Existing construction: For the purposes of determining rates, structures for which the "start of construction" commenced before the effective date of the initial Flood Insurance Rate Maps for that community.
Existing manufactured home park or subdivision: A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum the installation of utilities, the construction of streets, and final site grading or the pouring of concrete pads) is completed before the effective date of the first floodplain management regulations adopted by the City of Commerce.
Expansion to an existing manufactured home park or subdivision: The preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed, including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads.
Flood or flooding: A general and temporary condition of partial or complete inundation of normally dry land areas from: the overflow of inland or tidal waters; or the unusual and rapid accumulation or runoff of surface waters from any source.
Flood Hazard Boundary Map (FHBM): An official map of a community, issued by the Federal Insurance Administration, where the boundaries of areas of special flood hazard have been defined as Zone A.
Flood Insurance Rate Map (FIRM): An official map of a community, issued by the Federal Insurance Administration, delineating the areas of special flood hazard and/or risk premium zones applicable to the community.
Flood Insurance Study: The official report by the Federal Insurance Administration evaluating flood hazards and containing flood profiles and water surface elevations of the base flood.
Floodplain: Any land area susceptible to flooding.
Flood proofing: Any combination of structural and non-structural additions, changes, or adjustments to structures, which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures, and their contents.
Floodway: The channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than a designated height.
Freeboard: A factor of safety usually expressed in feet above a flood level for purposes of floodplain management. “Freeboard” tends to compensate for the many unknown factors that could contribute to flood heights greater than the height calculated for a selected size flood and floodway conditions, such as wave action, bridge openings, and the hydrological effect of urbanization of the watershed.
Highest adjacent grade: The highest natural elevation of the ground surface, prior to construction, adjacent to the proposed foundation of a building.
Historic structure: Any structure that is: listed individually in the National Register of Historic Places (a listing maintained by the U.S. Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register; certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district; individually listed on a state inventory of historic places and determined as eligible by states with historic preservation programs which have been approved by the Secretary of the Interior; or individually listed on a local inventory of historic places and determined as eligible by communities with historic preservation programs that have been certified either (1) by an approved state program as determined by the Secretary of the Interior, or (2) directly by the Secretary of the Interior in states without approved programs.
Lowest floor: The lowest floor of the lowest enclosed area, including basement. An unfinished or flood resistant enclosure, used solely for parking of vehicles, building access, or storage, in an area other than a basement, is not considered a building's lowest floor, provided that such enclosure is not built so as to render the structure in violation of other provisions of this section.
Manufactured home: A building, transportable in one or more sections, built on a permanent chassis and designed to be used with or without a permanent foundation when connected to the required utilities. The term also includes park trailers, travel trailers, and similar transportable structures placed on a site for 180 consecutive days or longer and intended to be improved property.
Manufactured home park or subdivision: A parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
Mean sea level: The average height of the sea for all stages of the tide. It is used as a reference for establishing various elevations within the floodplain. For purposes of the National Flood Insurance Program, the National Geodetic Vertical Datum (NGVD) of 1929 or other datum, to which base flood elevations shown on a community’s Flood Insurance Rate Map are referenced.
National Geodetic Vertical Datum (NGVD): As corrected in 1929 is a vertical control used as a reference for establishing varying elevations within the floodplain.
New construction: For the purposes of determining insurance rates, structures for which the “start of construction” commenced after the effective date of the initial Flood Insurance Rate Map and includes any subsequent improvements to such structures. For floodplain management purposes, “new construction” means structures for which the “start of construction” commenced after the effective date of the first floodplain management ordinance adopted by the City of Commerce and includes any subsequent improvements to such structures.
New manufactured home park or subdivision: A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed after the effective date of the first floodplain management ordinance adopted by the City of Commerce.
North American Vertical Datum (NAVD): Has replaced the National Geodetic Vertical Datum of 1929 in existing and future FEMA Flood Modernization Maps.
Recreational vehicle: A vehicle, which is built on a single chassis; 400 square feet or less when measured at the largest horizontal projection; designed to be self-propelled or permanently towable by a light duty truck; and designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.
Start of construction: The date the development permit was issued, provided the actual start of construction, repair, reconstruction, or improvement was within 180 days of the permit date. The actual start means the first placement of permanent construction of the structure such as the pouring of slabs or footings, installation of piles, construction of columns, or any work beyond the stage of excavation, and includes the placement of a manufactured home on a foundation.
(Permanent construction does not include initial land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms; nor does it include the installation on the property of buildings appurtenant to the permitted structure, such as garages or sheds not occupied as dwelling units or part of the main structure. (NOTE:
accessory structures are NOT exempt from any ordinance requirements). For a substantial improvement, the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.
Structure: A walled and roofed building that is principally above ground, a manufactured home, a gas or liquid storage tank.
Subdivision: The division of a single lot into two or more lots for the purpose of sale or development.
Substantial damage: Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed fifty (50) percent of the market value of the structure before the damage occurred.
Substantial improvement: Any reconstruction, rehabilitation, addition, or other improvement of a structure, taking place during a 5-year period, in which the cumulative cost equals or exceeds fifty (50) percent of the market value of the structure prior to the “start of construction” of the improvement. Note: The market value of the structure should be (1) the appraised value of the structure prior to the start of the initial repair or improvement, or (2) in the case of damage, the value of the structure prior to the damage occurring. This term includes structures, which have incurred “substantial damage,” regardless of the actual amount of repair work performed.
For the purposes of this definition, “substantial improvement” is considered to occur when the first alteration of any wall, ceiling, floor, or other structural part of the building commences, whether or not that alteration affects the external dimensions of the building. The term does not, however, include (1) those improvements of a structure required to comply with existing violations of state or local health, sanitary, or safety code specifications which are solely necessary to assure safe living conditions and which have been identified by the Administrator or his or her designee, and not solely triggered by an improvement or repair project, or (2) any alteration of a “historic structure” provided that the alteration will not preclude the structure’s continued designation as a ”historic structure.”
Substantially improved existing manufactured home parks or subdivisions: Where the repair, reconstruction, rehabilitation or improvement of the streets, utilities and pads equals or exceeds 50 percent of the value of the streets, utilities and pads before the repair, reconstruction or improvement commenced.
Variance: A grant of relief from the requirements of this Article, which permits construction in a manner otherwise prohibited by this Article.
Violation: The failure of a structure or other development to be fully compliant with the community’s floodplain management regulations. A structure or other development without the elevation certificate, or other certifications, or other evidence of compliance required by this ordinance is presumed to be in violation until such time as that documentation is provided.
Sec. 11-107. Basis for area of special flood hazard.
(a) Flood insurance study. The areas of special flood hazard identified by the Federal Emergency Management Agency in its Flood Insurance Study (FIS), for Jackson County, Georgia and incorporated areas effective December 17, 2010, with accompanying maps and other supporting data and any revision thereto, are adopted by reference and declared a part of this Article.
(b) Flood insurance rate maps. The flood insurance rate maps for Jackson County, Georgia and incorporated areas effective December 17, 2010, are adopted as if fully contained within this Article and shall be the basis for determining areas of special flood hazard.
(c) Additional areas of special flood hazard. Areas of special flood hazard may also include those areas known to have flooded historically or defined through standard engineering analysis by governmental agencies or private parties but not yet incorporated in a Flood Insurance Study.
(d) Repository. The repository for public inspection of the Flood Insurance Study (FIS), accompanying maps and other supporting data and the Flood Insurance Rate Maps is the Department of Community Development, City of Commerce.
Sec. 11-201. Permit required.
No development activity shall commence within an area regulated by this Article until and unless a flood area permit shall have been approved by the zoning administrator. No development activity shall be approved unless it conforms with the provisions of this Article prior to the commencement of any development activities. No building or structure shall be constructed within an area regulated by this Article until and unless a flood area permit or building permit, or both if required shall have been approved by the zoning administrator. No building or structure shall be approved unless it conforms with the provisions of this Article prior to the construction of said building or structure.
Sec. 11-202. Permit procedures.
Application for a flood area permit shall be made to the Zoning Administrator on forms furnished by the department prior to any development activities, and may include, but not be limited to the following: plans in sufficient number as specified by the department, drawn to scale showing the elevations of the area in question and the nature, location, dimensions, of existing or proposed structures, earthen fill placement, storage of materials or equipment, and drainage facilities.
Sec. 11-203. Specific information required – application stage.
The following information is required at the application stage:
(a) Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures;
(b) Elevation in relation to mean sea level to which any non-residential structure will be flood-proofed;
(c) Design certification from a registered professional engineer or architect that any proposed non-residential flood-proofed structure will meet the flood-proofing criteria of this Article; and
(d) Description of the extent to which any watercourse will be altered or relocated as a result of a proposed development.
Sec. 11-204. Specific information required – construction stage.
The following information is required at the construction stage:
(a) For all new construction and substantial improvements, the permit holder shall provide to the Zoning Administrator an as-built certification of the regulatory floor elevation or flood-proofing level immediately after the lowest floor or flood proofing is completed.
Any lowest floor certification made relative to mean sea level shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same. When flood proofing is utilized for non-residential structures, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same.
(b) Any work undertaken prior to submission of these certifications shall be at the permit holder's risk. The Zoning Administrator shall review the above referenced certification data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further progressive work being allowed to proceed.
Failure to submit certification or failure to make said corrections required hereby, shall be cause to issue a stop-work order for the project
floodway (A-zones).
Sec. 11-309. Standards for areas of special flood hazard (Zones AE) with established base flood elevations without designated floodways.
Sec. 11-301. General standards.
In all areas of special flood hazard the following provisions are required:
(a) Anchoring. New construction and substantial improvements of existing structures shall be anchored to prevent flotation, collapse or lateral movement of the structure.
(b) Flood-resistant materials. New construction and substantial improvements of existing structures shall be constructed with materials and utility equipment resistant to flood damage.
(c) Construction methods and practices. New construction or substantial improvements of existing structures shall be constructed by methods and practices that minimize flood damage.
(d) Heating and air conditioning. All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
(e) Manufactured homes. Manufactured homes shall be anchored to prevent flotation, collapse, or lateral movement. Methods of anchoring may include, but are not limited to, use of over-the-top or frame ties to ground anchors. This standard shall be in addition to and consistent with applicable State requirements for resisting wind forces.
(f) Water supply. New and replacement water supply systems shall be designed to minimize or eliminate infiltration of flood waters into the system.
(g) Sewage systems. New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of flood waters into the systems and discharges from the systems into flood waters.
(h) On-site sewage disposal systems. On-site waste disposal systems shall be located and constructed to avoid impairment to them or contamination from them during flooding.
(i) Nonconformities. Any alteration, repair, reconstruction or improvement to a structure, which is not compliant with the provisions of this Article, shall be undertaken only if the non- conformity is not furthered, extended or replaced.
Sec. 11-302. Elevated buildings.
(a) In all areas of special flood hazard, all new construction or substantial improvements of existing structures that include any fully enclosed area located below the lowest floor formed by foundation and other exterior walls shall be designed so as to be an unfinished or flood resistant enclosure. The enclosure shall be designed to equalize hydrostatic flood forces on exterior walls by allowing for the automatic entry and exit of floodwater.
(b) Designs for complying with this requirement must either be certified by a professional engineer or architect or meet the following minimum criteria:
1. Provide a minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding;
2. The bottom of all openings shall be no higher than one foot above grade; and,
3. Openings may be equipped with screens, louvers, valves or other coverings or devices provided they permit the automatic flow of floodwater in both direction.
(c) So as not to violate the “lowest floor” criteria of this Article, the unfinished or flood resistant enclosure shall only be used for parking of vehicles, limited storage of maintenance equipment used in connection with the premises, or entry to the elevated area, and
(d) The interior portion of such enclosed area shall not be partitioned or finished into separate rooms.
Sec. 11-303. New construction and/or substantial improvements.
In all areas of special flood hazard the following provisions are required for new construction and/or substantial improvements:
(a) Where base flood elevation data are available, new construction and/or substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than three feet above the base flood elevation.
Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate equalization of flood hydrostatic forces on both sides of exterior walls shall be provided in accordance with standards of this Article for “elevated buildings.”
(b) All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be elevated at or above three feet above the base flood elevation.
Sec. 11-304. Non-residential construction.
(a) New construction and/or the substantial improvement of any structure located in A1-30, AE, or AH zones, may be flood-proofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be water tight to three (3) feet above the base flood elevation, with walls substantially impermeable to the passage of water, and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy.
(b) A registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the Zoning Administrator as set forth in this Article.
Sec. 11-305. Manufactured homes.
Where base flood elevation data are available:
(a) All manufactured homes placed and/or substantially improved on: (1) individual lots or parcels, (2) in new and/or substantially improved manufactured home parks or subdivisions, (3) in expansions to existing manufactured home parks or subdivisions, or
(4) on a site in an existing manufactured home park or subdivision where a manufactured home has incurred “substantial damage” as the result of a flood, must have the lowest floor including basement, elevated no lower than three feet above the base flood elevation.
(b) Manufactured homes placed and/or substantially improved in an existing manufactured home park or subdivision may be elevated so that either: the lowest floor of the manufactured home is elevated no lower than three feet above the level of the base flood elevation; or the manufactured home chassis is elevated and supported by reinforced piers (or other foundation elements of at least an equivalent strength) of no less than 36 inches in height above grade.
(c) All manufactured homes must be securely anchored to an adequately anchored foundation system to resist flotation, collapse and lateral movement.
Sec. 11-306. Recreational vehicles.
All recreational vehicles placed on sites must either:
(a) Be on the site for fewer than 180 consecutive days;
(b) Be fully licensed and ready for highway use, (a recreational vehicle is ready for highway use if it is licensed, on its wheels or jacking system, attached to the site only by quick disconnect type utilities and security devices, and has no permanently attached structures or additions); or
(c) The recreational vehicle must meet all the requirements for “new construction,” including the anchoring and elevation requirements of this Article.
Sec. 11-307. Floodway.
Located within areas of special flood hazard established in this Article are areas designated as floodway. A floodway may be an extremely hazardous area due to velocity floodwaters, debris or erosion potential. In addition, the area must remain free of encroachment in order to allow for the discharge of the base flood without increased flood heights. Therefore, the following provisions shall apply:
Encroachments are prohibited, including earthen fill, new construction, substantial improvements or other development within the regulatory floodway. Development may be permitted however, provided it is demonstrated through hydrologic and hydraulic analyses performed in accordance with standard engineering practice that the encroachment shall not result in any increase in flood levels or floodway widths during a base flood discharge. A registered professional engineer must provide supporting technical data and certification thereof.
Sec. 11-308. Building standards for streams without established base flood elevations and/or floodway (A-zones).
Located within the areas of special flood hazard established in this Article, are streams for which no base flood data have been provided (A-Zones), or where base flood data have been provided but a floodway has not been delineated. When base flood elevation data or floodway data have not been provided in accordance with this Article, then the administrator shall obtain, review, and reasonably utilize any scientific or historic base flood elevation and floodway data available from a Federal, State, or other source, in order to administer the provisions of this Article. Only if data are not available from these sources, then the following provisions apply:
(a) No encroachments, including structures or fill material, shall be located within an area equal to the width of the stream or twenty feet, whichever is greater, measured from the top of the stream bank, unless certification by a registered professional engineer is provided demonstrating that such encroachment shall not result in more than a one foot increase in flood levels during the occurrence of the base flood discharge.
(b) In special flood hazard areas without base flood elevation data, new construction and substantial improvements of existing structures shall have the lowest floor of the lowest enclosed area (including basement) elevated no less than three feet above the highest adjacent grade at the building site. (NOTE: Require the lowest floor to be elevated one foot above the estimated base flood elevation in A-Zone areas where a limited detail study has been completed). Openings sufficient to facilitate the unimpeded movements of floodwaters shall be provided in accordance with standards of this Article for “elevated buildings.”
(c) All heating and air conditioning equipment and components (including ductwork), all electrical, ventilation, plumbing, and other service facilities shall be elevated no less than three feet above the highest adjacent grade at the building site.
(d) The administrator shall certify the lowest floor elevation level and the record shall become a permanent part of the permit file.
Sec. 11-309. Standards for areas of special flood hazard (Zones AE) with established base flood elevations without designated floodways.
Located within the areas of special flood hazard established in this Article, where streams with base flood elevations are provided but no floodways have been designated (Zones AE), the following provisions apply:
(a) No encroachments, including fill material, new structures or substantial improvements shall be located within areas of special flood hazard, unless certification by a registered professional engineer is provided demonstrating that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the water surface elevation of the base flood more than one foot at any point within the community. The engineering certification should be supported by technical data that conforms to standard hydraulic engineering principles.
(b) New construction or substantial improvements of buildings shall be elevated or floodproofed to elevations established in accordance with this Article.
Sec. 11-310. Standards for areas of shallow flooding (AO Zones).
Areas of special flood hazard established in this Article may include designated “AO” shallow flooding areas. These areas have base flood depths of one to three feet above ground, with no clearly defined channel. The following provisions apply:
(a) All new construction and substantial improvements of residential and non-residential structures shall have the lowest floor, including basement, elevated to the flood depth number specified on the Flood Insurance Rate Map (FIRM), above the highest adjacent grade. If no flood depth number is specified, the lowest floor, including basement, shall be elevated at least three feet above the highest adjacent grade. Openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of this Article for “elevated buildings.” The administrator shall certify the lowest floor elevation level and the record shall become a permanent part of the permit file.
(b) New construction or the substantial improvement of a non-residential structure may be flood-proofed in lieu of elevation. The structure, together with attendant utility and sanitary facilities, must be designed to be water tight to the specified FIRM flood level plus two feet, above highest adjacent grade, with walls substantially impermeable to the passage of water, and structural components having the capability of resisting hydrostatic and hydrodynamic loads and the effect of buoyancy. A registered professional engineer or architect shall certify that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions above, and shall provide such certification to the official as set forth in this paragraph and as required in this Article.
(c) Drainage paths shall be provided to guide floodwater around and away from any proposed structure.
Sec. 11-311. Subdivisions.
(a) All subdivision and/or development proposals shall be consistent with the need to minimize flood damage.
(b) All subdivision and/or development proposals shall have public utilities and facilities such as sewer, gas, electrical and water systems located and constructed to minimize flood damage.
(c) All subdivision and/or development proposals shall have adequate drainage provided to reduce exposure to flood hazards.
(d) For subdivisions and/or developments greater than fifty lots or five acres, whichever is less, base flood elevation data shall be provided for subdivision and all other proposed development, including manufactured home parks and subdivisions. Any changes or revisions to the flood data adopted herein and shown on the FIRM shall be submitted to FEMA for review as a Conditional Letter of Map Revision (CLOMR) or Conditional Letter of Map Amendment (CLOMA), whichever is applicable. Upon completion of the project, the developer is responsible for submitting the “as-built” data to FEMA in order to obtain the final LOMR.
Sec. 11-312. Critical facilities.
Critical facilities shall not be located in the 100-year floodplain or the 500-year floodplain. All ingress and egress from any critical facility must be protected to the 500-year flood elevation.
Sec. 11-402. Criteria and conditions for variances.
Sec. 11-401. Variance procedures.
(a) The Commerce City Council shall hear and decide requests for appeals or variance from the requirements of this Article. Procedures for consideration of variances to the requirements of this Article shall be the same as provided in this UDC for variances generally.
(b) The Commerce City Council shall hear and decide appeals when it is alleged an error in any requirement, decision, or determination is made by the zoning administrator, in the enforcement or administration of this Article. Procedures for consideration of appeals shall be the same as provided in this UDC for appeals of administrative decisions, generally.
(c) Any person aggrieved by the decision of the Commerce City Council may appeal such decision to the Superior Court of Jackson County, as provided by law.
Sec. 11-02. Criteria and conditions for variances.
The provisions of this Article are minimum standards for flood loss reduction; therefore, any deviation from the standards must be weighed carefully. In reviewing requests for variances, the Commerce City Council shall consider all technical evaluations, relevant factors, and the following standards in addition to others in this Article. A variance shall be issued only when consistent with the following criteria and conditions:
(a) A finding of good and sufficient cause is made.
(b) A determination is made that failure to grant the variance would result in exceptional hardship.
(c) A determination is made that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisance, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances.
(d) Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.
(e) Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.
(f) Variances may be issued for the repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum to preserve the historic character and design of the structure. In the instance of an historic structure, a determination that the variance is the minimum necessary so as not to destroy the historic character and design of the building.
(g) Variances may be issued for development necessary for the conduct of a functionally dependent use, provided the criteria of this Article are met, no reasonable alternative exists, and the development is protected by methods that minimize flood damage during the base flood and create no additional threats to public safety.
Sec. 11-403. Conditional approval permitted.
Upon consideration of the factors listed above and the purposes of this ordinance, the Commerce City Council may attach such conditions to the granting of variances as it deems necessary to further the purposes of this Article.
Sec. 11-404. Actions following variance approval.
(a) Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation and the elevation of the proposed lowest floor and stating that the cost of flood insurance will be commensurate with the increased risk to life and property resulting from the reduced lowest floor elevation.
(b) The Zoning Administrator shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency upon request.
Sec. 11-501. Administration.
The Zoning Administrator is hereby appointed to administer and implement the provisions of this Article. Duties of the Zoning Administrator shall include, but shall not be limited to the following:
(a) Review proposed development to assure that the permit requirements of this Article have been satisfied.
(b) Review proposed development to assure that all necessary permits have been received from governmental agencies from which approval is required by Federal or State law, including section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334. Require that copies of such permits be provided and maintained on file.
(c) Review all permit applications to determine whether proposed building sites will be reasonably safe from flooding.
(d) When base flood elevation data or floodway data have not been provided in accordance with this Article, then the Administrator shall obtain, review and reasonably utilize any base flood elevation and floodway data available from a Federal, State or other sources in order to administer the provisions of this Article.
(e) Review and record the actual elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all new or substantially improved structures in accordance with this section.
(f) Review and record the actual elevation, in relation to mean sea level to which any new or substantially improved structures have been flood-proofed, in accordance with this Article.
(g) When flood-proofing is utilized for a structure, the administrator shall obtain certification of design criteria from a registered professional engineer or architect in accordance with this Article.
(h) Make substantial damage determinations following a flood event or any other event that causes damage to structures in flood hazard areas.
(i) Notify adjacent communities and the Georgia Department of Natural Resources prior to any alteration or relocation of a watercourse and submit evidence of such notification to the Federal Emergency Management Agency (FEMA).
(j) For any altered or relocated watercourse, submit engineering data/analysis within six (6) months to the FEMA to ensure accuracy of community flood maps through the letter of map revision process. Assure flood carrying capacity of any altered or relocated watercourse is maintained.
(k) Make interpretations of this Article. In the interpretation and application of this Article all provisions shall be: considered as minimum requirements; liberally construed in favor of the city, and; deemed neither to limit nor repeal any other powers granted under state statutes. Where interpretation is needed as to the exact location of boundaries of the areas of special flood hazard (for example, where there appears to be a conflict between a mapped boundary and actual field conditions) the administrator shall make the necessary interpretation. Any person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this Article. In the interpretation and application of this ordinance all provisions shall be: (1) considered as minimum requirements; (2) liberally construed in favor of the city, and; (3) deemed neither to limit nor repeal any other powers granted under state statutes.
(l) All records pertaining to the provisions of this Article shall be maintained in the office of the City Clerk and shall be open for public inspection.
Sec. 11-502. Abrogation and greater restrictions.
This Article is not intended to repeal, abrogate, or impair any existing ordinance, easements, covenants, or deed restrictions. However, where this Article and another conflict or overlap, whichever imposes the more stringent restrictions shall prevail.
Sec. 11-503. Warning and disclaimer of liability.
The degree of flood protection required by this Article is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur; flood heights may be increased by man-made or natural causes. This Article does not imply that land outside the areas of special flood hazard or uses permitted within such areas will be free from flooding or flood damages. This Article shall not create liability on the part of the City of Commerce, or by any officer or employee thereof for any flood damages that result from reliance on this Article or any administrative decision lawfully made hereunder.
Sec. 11-504. Penalties for violation.
Failure to comply with the provisions of this Article or with any of its requirements, including conditions and safeguards established in connection with grants of variance shall constitute a violation. Any person who violates this Article or fails to comply with any of its requirements shall be subject to the provisions of the Code of the City of Commerce and this UDC relative to violations. Nothing herein contained shall prevent the City of Commerce from taking such other lawful actions as is necessary to prevent or remedy any violation.
Article 12 Land Development Involving Cemeteries and Burial Grounds
ARTICLE 12
LAND DEVELOPMENT INVOLVING CEMETERIES AND BURIAL GROUNDS
(Adopted 01/16/2023)
DIVISION I LAND DEVELOPMENT INVOLVING CEMETERIES AND BURIAL
GROUNDS
be developed.
be developed.
Sec. 12.118. Enforcement and penalties.
Sec. 12-101. Authority.
This Division is adopted to implement the requirements of O.C.G.A. § 36-72-4, “Permit Required for Developing Land on Which a Cemetery Located.”
Sec. 12-102. Definitions.
Unless otherwise defined in this UDC, terms used in this Division shall have the meanings given them in O.C.G.A. § 36-72-2.
Sec. 12-103. Permit required.
No known cemetery, burial ground, human remains, or burial object shall be knowingly disturbed by the owner or occupier of the land on which the cemetery or burial ground is located for the purposes of developing or changing the use of any part of such land unless a permit is first obtained from the Commerce City Council, which shall have authority to permit such activity except as provided in O.C.G.A. § 36-72-14.
(a) Exceptions. Minimally invasive investigation techniques, including remote sensing methods and the use of metal probes, used in effort to determine the presence and location(s) of graves shall not require a permit pursuant to O.C.G.A. § 36-72-5(2).
Sec. 12-104. Permit application requirements.
To obtain a permit for developing land on which a cemetery or burial ground is located, submittal of an application meeting the requirements specified in this section is required as follows:
(a) Application fee as established by the Commerce City Council not to exceed the maximum allowed by State law;
(b) Application form furnished by the Zoning Administrator, including signed and notarized signature of property owner;
(c) Evidence of ownership of the land on which the cemetery or burial ground is located in the form of a legal opinion based upon a title search;
(d) Campaign contribution disclosure;
(e) Metes and bounds legal description of the property;
(f) Copy of current survey plat of the property on record;
(g) Letter of intent describing the reason for development, proposed use of the property, and an analysis of how the proposed action compares to decision criteria specified for rezoning decisions in this Division to include a description of any special conditions voluntarily made by the applicant as a part of the request;
(h) A report prepared by an archeologist stating the number of graves believed to be present and their locations as can be determined from the use of minimally invasive investigation techniques, including remote sensing methods and the use of metal probes, which activities shall not require a permit;
(i) A survey prepared by or under the direction of a registered surveyor showing the location and boundaries of the cemetery or burial ground based on an archeologist's report;
(j) A sketch plan of the property(-ies) the cemetery or burial ground is located upon at an appropriate engineering scale prepared under the direction of a registered surveyor showing the following information:
1. Name, address, telephone number and e-mail address of the property owner(s), and of the applicant if different from the property owner(s);
2. If drawn on a boundary survey, the date of survey and source of data;
3. Date of sketch plan drawing, and revision dates, if applicable;
4. North arrow and graphic engineering scale
5. Location (land district, address, and tax map and parcel number) and size of the property in acres (or in square feet if less than an acre);
6. Vicinity map, showing the property in relation to the surrounding area with regard to well-known landmarks such as arterial streets or railroads. Vicinity maps may be drawn in freehand and at a scale sufficient to show clearly the information required.
U.S. Geological Survey maps at a scale of 1 inch equals 2,000 feet may be used for vicinity maps.
7. Zoning district classification of the subject property and all adjacent properties;
8. Man-made features within and adjacent to the property, including existing streets and names, city and city limit lines, and other significant information such as location of bridges, major utility lines, existing buildings and structures to remain, and other features as appropriate to the nature of the request;
9. The location and boundaries of the cemetery or burial ground based on an archeologist's report and survey as required above;
10. The proposed project layout, including the approximate location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas, driveways, and approximate location of proposed storm water detention facilities;
11. Proposed use(s) of the property;
12. A statement from the utility provider(s) as to the source of water supply and the provision for sanitary sewage disposal;
13. Statistics regarding the proposed development, such as but not limited to maximum building height, minimum lot size, minimum lot width, building coverage, percentage of landscaped open space, stream and zoning buffers required, and other information demonstrating compliance with the proposed zoning district’s dimensional requirements as determined by the zoning administrator;
(k) A plan prepared by a genealogist for identifying and notifying the descendants of those buried or believed to be buried in such cemetery. If those buried or believed to be buried are of aboriginal or American Indian descent, the genealogist, in preparing the notification plan, shall consult with the Council on American Indian Concerns created pursuant to O.C.G.A. § 44-12-280 and shall include in the notification plan not only any known descendants of those presumed buried but also any American Indian tribes as defined in paragraph (2) of O.C.G.A. § 44-12-260 that are culturally affiliated; and
(l) A proposal for mitigation or avoidance of the effects of the planned activity on the cemetery or burial ground. If the proposal includes relocation of any human remains or burial objects, the proposal shall specify the method of disinterment, the location and method of disposition of the remains, the approximate cost of the process, and the approximate number of graves affected; and
(m) A traffic impact study prepared by a professional engineer registered in Georgia shall be required to be submitted for applications for proposed developments that generate 1,000 or more average daily vehicle trips based upon the latest edition of Trip Generation published by the Institute of Transportation Engineers. If a traffic study calls for certain improvements the owner/developer shall provide all recommended improvements unless the project is located on a state route in which case the Georgia Department of Transportation must approve the project’s transportation improvements. A traffic study, a hydrology study, and/or other studies of the impact of the proposed development implied in the permit application may be recommended by the Zoning Administrator or required by the Commerce City Council as they may deem necessary for adequate consideration and a fully informed decision on the application.
Sec. 12-105. Review for completeness.
The Zoning Administrator shall review the application for completeness within ten (10) business days of receipt of the application packet. Incomplete applications will be returned to the applicant and shall not be processed.
Sec. 12-106. Identification and notification of descendants of person in cemetery sought to be developed.
(a) Applicant Requirements. The applicant shall implement its plan for identifying and locating descendants no later than the date the application is submitted to the City. Notice to possible descendants shall include information on how to contact the City and a summary of the rights of descendants under State law.
(b) Consideration by City Council. The City Council shall review the applicant’s plan for identifying and notifying the descendants of the deceased persons and may require as a condition for issuing a permit that the applicant implement additional reasonable attempts to identify and locate descendants.
(c) City Requirements. The governing authority shall promptly inform any descendant who indicates an interest in the disposition of the human remains and burial objects regarding any proposals for mitigation, the terms of any permit issued, the time and place of any scheduled public hearings, and appeal procedures and events.
Sec. 12-107. Investigations and recommendation.
(a) The Zoning Administrator may send the application out for review by internal city departments, external agencies and parties as may be appropriate. Any written comments received in a timely manner shall be submitted to the applicant and Commerce City Council for consideration, and any such comments shall become an official public record.
(b) The Zoning Administrator shall investigate and may make a recommendation regarding any or all of the relevant matters concerning the application. Any such investigation and recommendation shall, if in writing, be made available to the applicant and Commerce City Council prior to public hearings and shall become an official public record.
Sec. 12-108. Published notice of public hearings.
Within fifteen (15) days after it is satisfied that all reasonable effort has been made to notify descendants as provided per this Division, a public hearing shall be scheduled and the city shall cause to be published within a newspaper of general circulation within the City a notice of public hearing to be published one time per week for two consecutive weeks immediately preceding the week of the public hearing. The notice shall state the time, place, purpose of the public hearing, and location of the property.
Sec. 12-109. Public hearing notices – sign on property.
(a) Requirement and locations. The applicant shall be required to post and maintain signs supplied by the City near the right-of-way of the nearest public street, so as to be visible from the street and to coincide with the timeframe of the published public notice outlined in this Division. One such sign shall be placed in a conspicuous location along each street frontage of the property for which the rezoning has been requested. If the property has no street frontage, the sign shall be placed on each street where access to the property will be gained. The applicant shall be required to pay for the cost of each sign as required per this Division.
(b) Content. The sign providing notice shall state the time, place, and purpose of the public hearing and shall include the location of the property.
(c) Time period. It is the responsibility of the applicant to post the signs and to maintain the signs during the posting period. Said signs pertaining to the Commerce City Council’s consideration shall remain posted until a final decision by the Commerce City Council has been rendered.
(d) Consequences of non-maintenance. Failure to post and maintain the signs continuously may prohibit consideration of the application at any scheduled public hearing. In the event the signs are not posted continuously, the city, in its sole discretion, may require the reposting and readvertising prior to any future public hearing, for which the applicant shall pay an additional readvertising fee. The city may also in its sole discretion, continue, hold, or dismiss the application if public notice requirements are not met due to applicant non-maintenance of the required public notice sign(s) on the property.
Sec. 12-110. Public hearings.
The City Council shall hold a public hearing on the applications in accordance with the public hearing procedures specified in this UDC.
Sec. 12-111. Issues considered in decision on application for permit.
The Commerce City Council shall consider the following standards in making its determination:
(a) The presumption in favor of leaving the cemetery or burial ground in place;
(b) The concerns and comments of any descendants of those buried in the burial ground or cemetery and any other interested parties;
(c) The economic and other costs of mitigation;
(d) The adequacy of the applicant’s plans for disinterment and proper disposition of any human remains or burial objects;
(e) The balancing of the applicant’s interests in disinterment with the public’s and any descendant’s interest in the value of the undisturbed cultural and natural environment;
and
(f) Any other compelling factors which the City Council deems relevant.
Sec. 12-112. Commerce City Council decision.
(a) Decision. The City Council may (1) deny the application with written reasons therefor, or
(2) issue a permit adopting the application in whole or in part, or (3) issue a permit which may include additional requirements to mitigate the proposed activity’s adverse effects on the cemetery or burial ground, including but not limited to relocation of the proposed project, reservation of the cemetery or burial ground as an undeveloped area within the proposed development or use of land, and respectful disinterment and proper disposition of the human remains. The governing authority may adopt the applicant’s proposal for mitigation.
(b) Consideration of information. In rendering a decision on any such application, the Commerce City Council shall consider information supplied by the applicant and the Zoning Administrator as well as testimony and information accepted during public hearings.
(c) Timeframe for decision. Within 30 days after the conclusion of the public hearing, the Zoning Administrator shall notify the applicant in writing of the decision made by the City Council.
Sec. 12-113. Withdrawal of application.
(a) No refund. There shall be no refund by the city of an application fee if an application is withdrawn.
(b) Prior to public notice. If a request for withdrawal is received prior to the publication of a notice for a public hearing, the application shall be withdrawn administratively by the Zoning Administrator without restriction on the refiling of a rezoning application on the property in the future, as described in this division.
(c) After public notice. Should any request for withdrawal be made by the applicant after the Planning Commission’s public hearing but before or at the Commerce City Council’s consideration of the application, the application shall remain on the Commerce City Council’s agenda and the withdrawal request shall be considered for approval or denial, with or without prejudice, by the Commerce City Council. If withdrawal is not allowed, the Councils’ consideration of the application will proceed.
Sec. 12-114. Appeals.
Any person dissatisfied with a decision of the city council on an application for a permit to develop land on which a cemetery is located, may file an appeal in Jackson County Superior Court in addition to the superior courts enumerated in O.C.G.A. § 50-13-19, within thirty (30) days of such decision by the City Council.
Sec. 12-115. Development Activities Pending Appeal.
Until the expiration of the time for appeal as set forth in Section 12-114 or O.C.G.A. § 36-72-11, the applicant shall not begin or resume activities which comply with the permit issued by the City Council. If an appeal is filed, the applicant may begin or resume activities which comply with the permit only upon consent of the City Council and the party seeking judicial review or upon order of the reviewing court for good cause shown.
Sec. 12-116. Inspection to ensure applicant compliance.
The Zoning Administrator, Building Official, their designee, or local law enforcement agency shall inspect as necessary to determine whether the applicant has complied with the provisions of this Division requiring cessation or limitation of activity and with the terms of the permit as issued by the City Council or as modified by the superior court or reviewing court.
Sec. 12-117. Disinterment and disposition of human remains or burial objects.
Any disinterment and disposition of human remains or burial objects permitted under this Division shall be supervised, monitored, or carried out by the applicant’s archeologist and shall be done at the expense of the person or entity to whom the permit is issued.
Sec. 12-118. Enforcement and penalties.
Any action or inaction that violations the provisions of this Division are subject to the enforcement actions and penalties as outlined in this UDC up to and including criminal penalties as provided by applicable state law.
Article 13 Zoning Amendments and Procedures
ARTICLE 13
ZONING AMENDMENTS AND PROCEDURES
DIVISION I TEXT AMENDMENT
DIVISION II AMENDMENT TO THE OFFICIAL ZONING MAP (REZONING) AND
CHANGE OF CONDITIONS
DIVISION III APPLICATION FOR CONDITIONAL USE
DIVISION IV PROCEDURES FOR CALLING AND CONDUCTING PUBLIC HEARINGS
DIVISION V DEVELOPMENT OF REGIONAL IMPACT
Sec. 13-101. Authority to amend.
The Commerce City Council may from time to time amend any regulation pertaining to any zoning district; or may amend any other article or section of this UDC.
Sec. 13-102. Initiation of proposals for text amendments.
The Commerce City Council, Planning Commission or the Zoning Administrator may propose a change to the text of this UDC when public necessity, general welfare or good zoning practice justify such action.
Sec. 13-103. Notice of public hearings.
(a) Planning Commission. At least 15 but not more than 45 days prior to the date of the public hearing before the Planning Commission, the city shall cause to be published within a newspaper of general circulation within the city a notice of the public hearing to be published before the Planning Commission public hearing. The notice shall state the time, place, and purpose of the public hearing.
Sec. 13-104. Public hearings.
(a) Planning Commission. The Planning Commission shall hold a public hearing on text amendments in accordance with the public hearing procedures specified in this Article.
For any text amendment, the Commerce City Council may waive the requirement for public hearing, consideration, and action by the Planning Commission.
Sec. 13-105. Recommendation and decision.
(a) Planning Commission recommendation. Unless review and recommendation by the Planning Commission is waived by the Commerce City Council, within a period of 32 calendar days from the date of the Planning Commission’s scheduled public hearing on any such application for the text amendment, the Planning Commission shall provide a recommendation on the proposed text amendment or elect to make no recommendation.
The Planning Commission may recommend approval or disapproval of the proposed text amendment, or it may recommend modifications of the text amendment originally proposed, or it may elect to make no recommendation.
(b) Commerce City Council decision. The Commerce City Council shall, following a public hearing or thereafter, render a decision on the text amendment. The Commerce City Council may approve or disapprove the proposed text amendment as written, or it may approve modifications of the text amendment originally proposed.
(c) Information. In rendering a recommendation on any text amendment, the Planning Commission shall consider all information supplied by the zoning administrator, as well as any testimony and information accepted during public hearings. In rendering a decision on any text amendment, the Commerce City Council shall consider all information supplied by the Zoning Administrator and the recommendation of the Planning Commission, as well as any testimony and information accepted during public hearings.
Sec. 13-106. Withdrawal of text amendment.
Any application for an amendment to the text of this UDC may be withdrawn at any time at the discretion of the initiator of such a request.
AND CHANGE OF CONDITIONS
Sec. 13-201. Generally.
Any zoning district established by Article 2 of this UDC, any overlay district established by Article 4 of this UDC, or any environmental overlay district map established by Article 5 of this UDC, may be amended from time to time by the Commerce City Council following the procedures in this division. In addition, changes to conditions of approval pertaining to any rezoning approval may also be approved by the Commerce City Council following the procedures in this division.
Sec. 13-202. Initiation of rezoning application.
(a) An application to amend the official zoning map, overlay district map or environmental overlay district map, or a condition of zoning approval may be initiated by the Commerce City Council.
(b) A private property owner may file an application to amend the official zoning map or to change conditions of zoning approval, as it pertains to the property owned, in accordance with the requirements of this division.
Sec. 13-203. Rezoning application requirements.
Applications to amend the official zoning map or to change conditions of zoning shall require submittal of an application meeting requirements specified in this section. The Zoning Administrator may waive the application fee and certain application requirements specified in this Section when an application for amendment of the official zoning map or change of zoning conditions is initiated by the Commerce City Council. The following are required:
(n) Application fee as established by resolution of the Commerce City Council;
(o) Application form furnished by the Zoning administrator, including signed and notarized signature of property owner;
(p) Campaign contribution disclosure;
(q) Metes and bounds legal description of the property;
(r) Survey plat of the property;
(s) Letter of intent describing the proposed use of the property, and including an analysis of how the proposed action compares to decision criteria specified for rezoning decisions in this division and a description of any special conditions voluntarily made a part of the request;
(t) Sketch plan of the property at an appropriate engineering scale prepared by the applicant, a professional engineer, a registered land surveyor, a landscape architect, a land planner or any other person familiar with land development activities showing the following information:
14. Name, address, telephone number and e-mail address of the property owner, and of the applicant if different from the property owner;
15. If drawn on a boundary survey, the date of survey and source of data;
16. Date of sketch plan drawing, and revision dates, if applicable;
17. North arrow and graphic engineering scale;
18. Location (land district, address, and tax map and parcel number) and size of the property in acres (or in square feet if less than an acre);
19. Vicinity map, showing the property in relation to the surrounding area with regard to well-known landmarks such as arterial streets or railroads. Vicinity maps may be drawn in freehand and at a scale sufficient to show clearly the information required.
U.S. Geological Survey maps at a scale of 1 inch equals 2,000 feet may be used for vicinity maps.
20. Zoning district classification of the subject property and all adjacent properties;
21. Man-made features within and adjacent to the property, including existing streets and names, city and city limit lines, and other significant information such as location of bridges, major utility lines, existing buildings and structures to remain, and other features as appropriate to the nature of the request;
22. The proposed project layout, including the approximate location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas, driveways, and approximate location of proposed storm water detention facilities;
23. Proposed use or uses of the property;
24. A statement from the utility provider(s) as to the source of water supply and the provision for sanitary sewage disposal;
25. Statistics regarding the proposed development, such as but not limited to maximum building height, minimum lot size, minimum lot width, building coverage, percentage of landscaped open space, stream and zoning buffers required, and other information demonstrating compliance with the proposed zoning district’s dimensional requirements as determined by the zoning administrator;
(u) A traffic impact study prepared by a professional engineer registered in Georgia shall be required to be submitted for applications for proposed developments that generate 1,000 or more average daily vehicle trips based upon the latest edition of Trip Generation published by the Institute of Transportation Engineers. If a traffic study calls for certain improvements the owner/developer shall provide all recommended improvements unless the project is located on a state route in which case the Georgia Department of Transportation must approve the project’s transportation improvements. A traffic study, a hydrology study, and/or other studies of the impact of the proposed zoning district or development implied in the rezoning application may be recommended by the Zoning Administrator or required by the Planning Commission or the Commerce City Council as they may deem necessary for adequate consideration and a fully informed decision on an application for rezoning; and
(v) Other information as may be required by the zoning administrator.
Sec. 13-204. Review for completeness.
The Zoning Administrator shall review the application for completeness within 10 working days of the posted application submission deadline. Incomplete applications will be returned to the applicant and shall not be processed.
Sec. 13-205. Published notice of public hearings.
Planning Commission. At least 15 but not more than 45 days prior to the date of the public hearing before the Planning Commission, the city shall cause to be published within a newspaper of general circulation within the city a notice of the public hearing to be published before the Planning Commission public hearing. The notice shall state the time, place, and purpose of the public hearing. The published notice, in addition to the requirements above, shall include the location of the property, the present zoning classification of the property, and the proposed zoning classification of the property requested.
Sec. 13-206. Public hearing notices – sign on property.
(e) Requirement and locations. The applicant shall be required to post and maintain signs supplied by the city near the right-of-way of the nearest public street, so as to be visible from the street for at least 15 but not more than 45 days preceding the date of the Planning Commission’s public hearing and for at least 15 days and not more than 45 days immediately preceding the date for the Commerce City Council’s consideration of the rezoning application. One such sign shall be placed in a conspicuous location along each street frontage of the property for which the rezoning has been requested. If the property has no street frontage, the sign shall be placed on each street where access to the property will be gained. The applicant shall be required to pay for the cost of each sign as required per this Article.
(f) Content. The sign providing notice shall state the time, place, and purpose of the public hearing and shall include the location of the property. In addition, the notice shall include the existing zoning classification and the proposed zoning classification of the property.
(g) Time period. It is the responsibility of the applicant to post the signs and to maintain the signs during the posting period. Said signs pertaining to the Commerce City Council’s consideration shall remain posted until a final decision by the Commerce City Council has been rendered.
(h) Consequences of non-maintenance. Failure to post and maintain the signs continuously may prohibit consideration of the application at any scheduled public hearing. In the event the signs are not posted continuously, the city, in its sole discretion, may require the reposting and readvertising prior to any future public hearing, for which the applicant shall pay an additional readvertising fee. The city may also in its sole discretion, continue, hold, or dismiss the application if public notice requirements are not met due to applicant non-maintenance of the required public notice sign(s) on the property.
Sec. 13-207. Special notice requirements for halfway houses and related uses.
This section is adopted pursuant to the specific requirements of the state zoning procedures law.
When a proposed zoning map amendment relates to or will allow the location or relocation of a halfway house, drug rehabilitation center, or other facility for treatment of drug dependency, a duly noticed public hearing shall be held on the proposed action in accordance with the procedures and requirements established in this Article. In addition, the following requirements shall apply.
(a) Such public hearing shall be held at least six months but not more than nine months prior to the date of final action on the application.
(b) All published or posted notices of the public hearing shall include a prominent statement that the proposed zoning map amendment relates to or will allow the location or relocation of a halfway house, drug rehabilitation center, or other facility for treatment of drug dependency.
(c) The published notice shall be at least six column inches in size and shall not be located in the classified advertising section of the newspaper.
Sec. 13-208. Investigations and recommendation.
(c) The Zoning Administrator may send the application out for review by internal city departments and external agencies as may be appropriate (i.e., inter-agency review). Any written comments received in a timely manner shall be submitted to the applicant, Planning Commission and Commerce City Council for consideration, and any such comments shall become an official public record.
(d) The Zoning Administrator shall investigate and make a recommendation regarding any or all of the relevant matters concerning the application. Any such investigation and recommendation shall, if in writing, be made available to the applicant, Planning Commission, and Commerce City Council prior to public hearings and shall become an official public record.
Sec. 13-209. Public hearings.
Planning Commission. The Planning Commission shall hold a public hearing on rezoning applications in accordance with the public hearing procedures specified in this Article. For any rezoning application initiated by the Commerce City Council, the Commerce City Council may waive the requirement for public hearing, consideration, and action by the Planning Commission.
Sec. 13-210. Standards for rezoning decisions.
The Planning Commission and the Commerce City Council should consider the following standards for any rezoning proposal, giving due weight or priority to those factors that are appropriate to the circumstances of each proposal:
(g) The existing land use pattern;
(h) The possible creation of an isolated district unrelated to adjacent and nearby districts;
(i) The population density pattern and possible increase or overtaxing of the load on public facilities including, but not limited to, schools, utilities, and streets, and the cost to the city and other governmental entities in providing, improving, increasing or maintaining public utilities, schools, streets and other public safety measures;
(j) The possible impact on the environment, including but not limited to, drainage, soil erosion and sedimentation, flooding, air quality and water quality;
(k) Whether the proposed zoning map amendment will be a deterrent to the value or improvement or development of adjacent property in accordance with existing regulations;
(l) Whether there are substantial reasons why the property cannot be used in accordance with existing regulations;
(m)The aesthetic effect of existing and future use of the property as it relates to the surrounding area;
(n) The extent to which the proposed zoning map amendment is consistent with the comprehensive plan;
(o) The possible effect of the proposed zoning map amendment on the character of a zoning district, a particular piece of property, neighborhood, a particular area, or the community;
(p) The relation that the proposed zoning map amendment bears to the purpose of the overall zoning scheme, with due consideration given to whether or not the proposed change will help carry out the purposes of these zoning regulations;
(q) The consideration of the preservation of the integrity of residential neighborhoods shall be considered to carry great weight;
(r) In those instances in which property fronts on a major thoroughfare and also adjoins an established residential neighborhood, the factor of preservation of the residential area shall be considered to carry great weight.
Sec. 13-211. Planning Commission recommendation.
(a) Time frame for recommendation. Within 35 calendar days of the date of the public hearing held by the Planning Commission on the application, the Planning Commission shall provide a recommendation on all applications for rezoning or elect to make no recommendation. This time limit may be extended if the applicant consents to extend the time frame, or if the project is a Development of Regional Impact (DRI) in which case the time limit will extend to accommodate the DRI process.
(b) Recommendation. The Planning Commission may recommend approval or disapproval of the proposed rezoning applied for, or it may recommend conditions of approval on the application, or it may elect to make no recommendation. The Planning Commission may also recommend rezoning the property to a more restrictive zoning classification than requested by the applicant. The Planning Commission may also recommend a reduction of the boundaries of the area rezoned that is less than that requested by the applicant.
(c) Consideration of information. In rendering a recommendation on any such application, the Planning Commission shall consider information supplied by the applicant, any report and/or recommendation from the zoning administrator, and any testimony and information accepted during the public hearing.
Sec. 13-212. Commerce City Council decision.
(d) Time frame for decision. Within 65 calendar days of the date of Planning Commission’s recommendation, the Commerce City Council shall render a decision on the application for rezoning. This time limit may be extended if the applicant consents to extend the time frame.
(e) Decision. The Commerce City Council may approve or disapprove the proposed rezoning as applied for, return the application to the Planning Commission for further study, or may approve the application with conditions. The Commerce City Council may also rezone the property to a more restrictive zoning classification than requested by the applicant. The Commerce City Council may also reduce the boundaries of the area rezoned to an area that is less than that requested by the applicant.
(f) Consideration of information. In rendering a decision on any such application, the Commerce City Council shall consider information supplied by the applicant, the zoning administrator, and the Planning Commission, as well as testimony and information accepted during public hearings.
Sec. 13-213. Withdrawal of application.
(d) No refund. There shall be no refund by the city of an application fee if an application is withdrawn.
(e) Prior to public notice. If a request for withdrawal is received prior to the publication of a notice for a public hearing, the application shall be withdrawn administratively by the Zoning Administrator without restriction on the refiling of a rezoning application on the property in the future, as described in this division.
(f) After public notice. If a request for withdrawal is received after publication of a public notice has been published or when such public notice is irretrievably set for publication but the rezoning application has not been heard by the Planning Commission, the application shall be withdrawn administratively by the zoning administrator, provided that an application for a rezoning of the property shall not be resubmitted for six months from the date of withdrawal.
(g) After Planning Commission public hearing. Should any request for withdrawal be made by the applicant after the Planning Commission’s public hearing but before or at the Commerce City Council’s consideration of the application, the application shall remain on the Commerce City Council’s agenda and the withdrawal request shall be considered for approval or denial, with or without prejudice, by the Commerce City Council. If withdrawal is not allowed, the Councils’ consideration of the application will proceed.
Sec. 13-214. Limitations on the frequency of filing applications.
(a) No rezoning application affecting the same or any portion of property which was denied by the Commerce City Council shall be accepted for filing by a property owner until twelve months shall have elapsed from the date said application was denied by the Commerce City Council, unless the Commerce City Council reduces the twelve-month time period to no less than six months.
(b) The same or any portion of property previously considered in a rezoning application which was denied by the Commerce City Council may not be initiated again by the Commerce City Council until the expiration of at least six months immediately following the final decision rendered on the application by the Commerce City Council.
(c) After approval of a rezoning, no rezoning application affecting the same or any portion of property which was approved by the Commerce City Council shall be accepted for filing by a property owner until twelve months shall have elapsed from the date said application for rezoning was approved by the Commerce City Council, unless there are extenuating circumstances determined by the Zoning Administrator in which case the Zoning Administrator may authorize the filing of such application.
(d) After approval of conditional zoning by the Commerce City Council, no application to modify conditions of zoning affecting the same or any portion of property which was approved shall be accepted for filing by a property owner until twelve months have elapsed from the date the conditions of zoning were approved, unless there are extenuating circumstances determined by the Zoning Administrator in which case the Zoning Administrator may authorize the filing of such application.
Sec. 13-215. Concurrent consideration of applications.
In cases where an applicant is proposing a rezoning (i.e., amendment to the official zoning map), and where the applicant files an application to obtain a conditional use at the same time of filing a rezoning application, the two applications may be processed simultaneously, but the conditional use application shall not be voted on until the rezoning application is voted on (which may be the same public hearing or meeting), since the conditional use would not otherwise be permitted without the rezoning.
Sec. 13-216. Appeals Any person aggrieved by a decision of the city council on an application for a zoning amendment may petition the Jackson County Superior Court in accordance with the law within ten (10) days of the written decision of the city council.
Sec. 13-301. Generally.
The Commerce City Council following the procedures in this Division may approve conditional uses authorized in Table 2-1A and Table 2-1B of this UDC. In addition, changes to the conditions of approval, pertaining to any conditions of conditional use approval, may also be approved by the Commerce City Council following the procedures in this division.
Sec. 13-302. Initiation of conditional use application.
A private property owner may file an application for conditional use approval, as it pertains to the property owned, in accordance with the requirements of this Division.
Sec. 13-303. Conditional use application requirements.
Applications for conditional use shall require submittal of an application meeting the requirements specified in this Section.
(a) Application fee as established by resolution of the Commerce City Council;
(b) Application form furnished by the zoning administrator, including signed and notarized signature of property owner;
(c) Campaign contribution disclosure;
(d) Metes and bounds legal description of the property;
(e) Survey plat of the property;
(f) Letter of intent describing the proposed use of the property, and including an analysis of how the proposed action compares to decision criteria specified in this division for conditional uses and a description of any special conditions voluntarily made a part of the request;
(g) Sketch plan of the property at an appropriate engineering scale prepared by the applicant, a professional engineer, a registered land surveyor, a landscape architect, a land planner or any other person familiar with land development activities showing the following information:
1. Name, address, telephone number and e-mail address of the property owner, and of the applicant if different from the property owner;
2. If drawn on a boundary survey, the date of survey and source of data;
3. Date of sketch plan drawing, and revision dates, if applicable;
4. North arrow and graphic engineering scale;
5. Location (land district, address, and tax map and parcel number) and size of the property in acres (or in square feet if less than an acre);
6. Vicinity map, showing the property in relation to the surrounding area with regard to well-known landmarks such as arterial streets or railroads. Vicinity maps may be drawn in freehand and at a scale sufficient to show clearly the information required.
U.S. Geological Survey maps at a scale of 1 inch equals 2,000 feet may be used for vicinity maps.
7. Zoning district classification of the subject property and all adjacent properties;
8. Man-made features within and adjacent to the property, including existing streets and names, city and city limit lines, and other significant information such as location of bridges, major utility lines, existing buildings and structures to remain, and other features as appropriate to the nature of the request;
9. The proposed project layout, including the approximate location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas, driveways, and approximate location of proposed storm water detention facilities;
10. Proposed conditional use and uses of the property;
11. A statement as to the source of water supply and the provision for sanitary sewage disposal;
12. Statistics regarding the proposed development, such as but not limited to maximum building height, minimum lot size, minimum lot width, building coverage, percentage of landscaped open space, stream and zoning buffers required, and other information demonstrating compliance with the zoning district’s dimensional requirements and specific regulations for the conditional use as required by Article III of this UDC, as determined by the zoning administrator;
(h) A traffic impact study prepared by a professional engineer registered in Georgia shall be required to be submitted for applications for proposed developments that generate 1,000 or more average daily vehicle trips based upon the latest edition of Trip Generation published by the Institute of Transportation Engineers. A traffic study, a hydrology study, and/or other studies of the impact of the proposed conditional use may be recommended by the Zoning Administrator or required by the Planning Commission or the Commerce City Council as they may deem necessary for adequate consideration and a fully informed decision on an application for conditional use; and
(i) Other information as may be required by the zoning administrator.
Sec. 13-304. Review for completeness.
The Zoning Administrator shall review the application for completeness within 10 working days of the posted application submission deadline. Incomplete applications will be returned to the applicant and shall not be processed.
Sec. 13-305. Published notice of public hearings.
Planning Commission. At least 15 but not more than 45 days prior to the date of the public hearing before the Planning Commission, the City shall cause to be published within a newspaper of general circulation within the city a notice of the public hearing before the Planning Commission. The notice shall state the time, place, and purpose of the public hearing.
The published notice, in addition to the requirements above, shall include the location of the property and the proposed conditional use of the property requested.
Sec. 13-306. Public hearing notices – sign on property.
(i) Requirement and locations. The applicant shall be required to post and maintain signs supplied by the city near the right-of-way of the nearest public street, so as to be visible from the street at least 15 but not more than 45 days preceding the date of the Planning Commission’s public hearing and for at least 15 days and not more than 45 days immediately preceding the date for the Commerce City Council’s consideration of the conditional use application. One such sign shall be placed in a conspicuous location along each street frontage of the property for which the rezoning approval has been requested.
If the property has no street frontage, the sign shall be placed on each street where access to the property will be gained. The applicant shall be required to pay for the cost of each sign as required per this Article.
(j) Content. The sign providing notice shall state the time, place, and purpose of the public hearing and the Council’s consideration of the application and shall include the location of the property. In addition, the notice shall include the proposed conditional use of the property.
(k) Time period. It is the responsibility of the applicant to post the signs and to maintain the signs during the posting period. Said signs pertaining to the Commerce City Council’s consideration of the application shall remain posted until a final decision by the Commerce City Council has been rendered.
(l) Consequences of non-maintenance. Failure to post and maintain the signs continuously may prohibit consideration of the application at any scheduled public hearing. In the event the signs are not posted continuously, the city, in its sole discretion, may require the reposting and readvertising prior to any future public hearing, for which the applicant shall pay an additional readvertising fee. The city may also in its sole discretion, continue, hold, or dismiss the application if public notice requirements are not met due to applicant non-maintenance of the required public notice sign(s) on the property.
Sec. 13-307. Special notice requirements for halfway houses and related uses.
This section is adopted pursuant to the specific requirements of the state zoning procedures law.
When a proposed conditional use relates to or will allow the location or relocation of a halfway house, drug rehabilitation center, or other facility for treatment of drug dependency, a duly noticed public hearing shall be held on the proposed action in accordance with the procedures and requirements established in this Article. In addition, the following requirements shall apply.
(d) Such public hearing shall be held at least six months but not more than nine months prior to the date of final action on the application.
(e) All published or posted notices of the public hearing shall include a prominent statement that the proposed conditional use relates to or will allow the location or relocation of a halfway house, drug rehabilitation center, or other facility for treatment of drug dependency.
(f) The published notice shall be at least six column inches in size and shall not be located in the classified advertising section of the newspaper.
Sec. 13-308. Investigations and recommendation.
(e) The Zoning Administrator may send the application out for review by internal city departments and external agencies as may be appropriate (i.e., inter-agency review). Any written comments received in a timely manner shall be submitted to the applicant, Planning Commission and Commerce City Council for consideration, and any such comments shall become an official public record.
(f) The Zoning Administrator shall investigate and make a recommendation regarding any or all of the relevant matters concerning the application. Any such investigation and recommendation shall if in writing be made available to the applicant, Planning Commission, and Commerce City Council prior to public hearings and shall become an official public record.
Sec. 13-309. Public hearings.
Planning Commission. The Planning Commission shall hold a public hearing on conditional use applications in accordance with the public hearing procedures specified in this Article.
Sec. 13-310. Standards for conditional use application decisions.
The Planning Commission and the Commerce City Council should consider the following standards for any conditional use application, giving due weight or priority to those factors that are appropriate to the circumstances of each proposal:
(a) Will the proposed conditional use be consistent with the stated purpose of the zoning district in which it will be located?
(b) Is the proposed conditional use compatible with the goals, objectives, purpose and intent of the comprehensive plan?
(c) Will the establishment of the conditional use impede the normal and orderly development of surrounding property for uses predominant in the area?
(d) Is the location and character of the proposed conditional use consistent with a desirable pattern of development for the locality in general?
(e) Is or will the type or functional classification of street providing access to the use be adequate to serve the proposed conditional use?
(f) Is or will access into and out of the property be adequate to provide for traffic and pedestrian safety, the anticipated volume of traffic flow, and access by emergency vehicles?
(g) Are or will public facilities such as schools, water or sewer utilities, and police or fire protection be adequate to serve the conditional use?
(h) Are or will refuse service, parking and loading areas on the property be located or screened to protect other properties in the area from such adverse effects as noise, light, glare or odor?
(i) Will the hours and manner of operation of the conditional use have one or more adverse effects on other properties in the area?
(j) Will the height, size or location of the buildings or other structures on the property be compatible with the height, size or location of buildings or other structures on neighboring properties?
Sec. 13-311. Planning Commission recommendation.
(a) Time frame for recommendation. Within 35 calendar days of the date of the public hearing held by the Planning Commission on the application, the Planning Commission shall provide a recommendation on all applications for conditional use or elect to make no recommendation. This time limit may be extended if the applicant consents to extend the time frame. In the event a conditional use application triggers a Development of Regional Impact (DRI) review, the time frame shall be extended to accommodate the DRI review process.
(b) Recommendation. The Planning Commission may recommend approval or disapproval of the proposed conditional use applied for, may recommend conditions of approval, or it may elect to provide no recommendation. The Planning Commission may also recommend a reduction of the boundaries of the area devoted to the conditional use that is less than that requested by the applicant.
(c) Consideration of information. In rendering a recommendation on any such application, the Planning Commission shall consider information supplied by the applicant and any report and/or recommendation from the zoning administrator.
Sec. 13-312. Commerce City Council decision.
(a) Time frame for decision. Within 65 calendar days of the date of recommendation of the Planning Commission, the Commerce City Council shall render a decision on the application for conditional use. This time limit may be extended if the applicant consents to extend the time frame.
(b) Decision. The Commerce City Council may approve or disapprove the proposed conditional use as applied for, return the application to the Planning Commission for further study, or may approve the application with conditions. The Commerce City Council may also reduce the boundaries of the area applicable to the conditional use to an area that is less than that requested by the applicant.
(c) Consideration of information. In rendering a decision on any such application, the Commerce City Council shall consider information supplied by the applicant, the zoning administrator, and the Planning Commission, as well as testimony and information accepted during public hearings.
Sec. 13-313. Withdrawal of application.
(a) No refund. There shall be no refund by the city of an application fee if an application is withdrawn.
(b) Prior to public notice. If a request for withdrawal is received prior to the publication of a notice for a public hearing, the application shall be withdrawn administratively by the Zoning Administrator without restriction on the refiling of a conditional use application on the property in the future, as described in this division.
(c) After public notice. If a request for withdrawal is received after publication of a public notice has been published or when such public notice has been irretrievably set for publication but the conditional use application has not been heard by the Planning Commission, the application shall be withdrawn administratively by the zoning administrator, provided that an application for conditional use on the property shall not be resubmitted for six months from the date of withdrawal.
(d) After Planning Commission public hearing. Should any request for withdrawal be made by the applicant after the Planning Commission’s public hearing but before or at the Commerce City Council’s consideration of the application, the application shall remain on the Commerce City Council’s agenda and the withdrawal request shall be considered for approval or denial, with or without prejudice, by the Commerce City Council. If withdrawal is not allowed, the Council’s consideration of the conditional use will proceed.
Sec. 13-314. Limitations on the frequency of filing applications.
(a) No conditional use application affecting the same or any portion of property which was denied by the Commerce City Council shall be accepted for filing by a property owner until twelve months shall have elapsed from the date said application was denied by the Commerce City Council, unless the Commerce City Council reduces the twelve-month time period to no less than six months.
(b) The same or any portion of property previously considered in a conditional use application which was denied by the Commerce City Council may not be initiated again by the Commerce City Council until the expiration of at least six months immediately following the final decision rendered on the application by the Commerce City Council.
(c) After approval of a conditional use by the Commerce City Council, no application to modify conditions placed on an approved conditional use application affecting the same or any portion of property shall be accepted for filing by a property owner until twelve months have elapsed from the date the conditions of zoning were approved, unless there are extenuating circumstances determined by the Zoning Administrator in which case the Zoning Administrator may authorize the filing of such application.
Sec. 13-315. Concurrent consideration of applications.
In cases where an applicant is proposing a rezoning (i.e., amendment to the official zoning map), and where the applicant files an application to obtain a conditional use at the same time of filing a rezoning application, the two applications may be processed simultaneously, but the conditional use application shall not be voted on until the rezoning application is voted on (which may be the same public hearing or meeting), since the conditional use would not otherwise be permitted without the rezoning.
Sec. 13-316. Appeals.
Any person aggrieved by a decision of the city council on an application for a conditional use may petition the Jackson County Superior Court in accordance with the law within ten (10) days of the written decision of the city council.
Sec. 13-401. Generally.
Public hearings held by the Planning Commission (or if a public hearing is held by the Commerce City Council in its discretion) for rezoning and conditional use applications shall be conducted in accordance with this division.
Sec. 13-402. Convening a hearing.
(a) The public hearing will be convened at the scheduled time and place by the Planning Commission chair, the chairman of the Commerce City Council or an appointed designee, as appropriate, who will act as the presiding official. The presiding official shall indicate that a public hearing has been called on one or more applications made and shall summarize the procedures of this division or call on the Zoning Administrator staff to summarize the procedures. The presiding official shall then open the public hearing.
(b) Upon opening the public hearing, the presiding official shall call the first case and the hearing body shall consider each application on an individual basis in succession as printed on the published agenda or as otherwise approved by the hearing body; provided, however, that the presiding official may at his or her discretion call and consider more than one application simultaneously if more than one application involves the same piece of property, or if proceedings would be efficiently completed by combining separately required public hearings and discussing more than one scheduled matter as a single group of applications.
Sec. 13-403. Call for presentation.
The presiding official will call for each application to be presented by the zoning administrator.
Sec. 13-404. Requirements to speak.
Time permitting, any member of the general public may speak at the public hearing; however, no person in attendance shall speak unless first formally recognized by the presiding official. Upon rising to speak, each person recognized except staff members shall state their name and home address.
Sec. 13-405. Sequence and limits.
(a) When an individual application comes up for hearing, the presiding official may ask for a show of hands of those persons who wish to appear in support of and in opposition to the application. If it appears that the number of persons wishing to appear in support of or in opposition to the application is in excess of that which may reasonably be heard, the presiding official may request that a spokesperson for the group be chosen to make presentations. The presiding official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed zoning change or conditional use application.
(b) No less than 10 minutes will be provided for all of those speaking in support of a zoning change or conditional use application, and no less than 10 minutes will be provided for all of those speaking against; provided, however, that proponents or opponents may take less time than the minimum required in which case the full 10 minutes shall not be required to be allotted.
(c) After any staff presentation on the application, the applicant will be allowed to speak first in order to present the application. The hearing shall be attended by the applicant or representative thereof with authority to make binding commitments to the city with respect to any stipulations that may be offered in connection with such application.
Failure to attend the hearing by the applicant or his or her authorized representative may result in the application being continued.
(d) Each speaker may speak only to the proposed application under consideration and shall address his or her remarks only to the hearing body. Each speaker shall refrain from personal attacks on any other speaker or the discussion of facts or opinions irrelevant to the proposed application under consideration. The presiding official may limit or refuse a speaker the right to continue if, after first being cautioned, the speaker continues to violate this procedure.
(e) Upon conclusion of the applicant’s presentation, others in support of the application may then speak, followed by those in opposition to the application. Those present who are neither opposed or in favor of the application but who have questions will speak during the time afforded the opposition.
(f) Following the conclusion of speakers in opposition, if some of the 10 minutes of applicant’s time has reserved for rebuttal, the applicant will then be allowed to use the reserved time for rebuttal, which must be limited to points or issues raised by opponents to the application during the public hearing.
(g) During the public hearing, any member of the Planning Commission or Commerce City Council as appropriate may upon recognition by the presiding official ask questions of the applicant, staff, or a member speaking at the public hearing. Time devoted to questions and answers will not be counted against any time limitations that have been imposed on presentations.
Sec. 13-406. Close of hearing.
(a) After the foregoing procedures have been completed, the presiding official will indicate that the public hearing is closed.
(b) Upon the closing of the public hearing, the applicant or his agent and any member of the public shall no longer address the hearing body in any way, including hand waving or motions for attention; provided, however, the presiding officer may, in his or her discretion, reopen the public hearing for a limited time and purpose.
(c) After the close of public hearing, the hearing body may act on the application.
Sec. 13-501. Definitions.
Initial DRI information form: A form intended to identify basic information about a proposed development of regional impact on which a local government is being requested to take action, and which provides information to the regional commission. This form notifies the regional commission of a potential development of regional impact in order for the commission to meet its responsibilities within the DRI review process.
DRI Review initiation request form: A form intended to provide additional information about the proposed project to the regional commission, the submission of which serves as an official request that the DRI review process be started by the commission.
Regional commission: The Northeast Georgia Regional Commission, or any successor or subsequent agency with jurisdiction for development of regional impact applications.
Sec. 13-502. Applicability.
This division shall apply when an applicant (industry, business, or developer) requests some type of local government action related to a project, such as, but not limited to, a request for rezoning, conditional use, variance, permit, hookup to a water or sewer system, master or site plan approval, or entering into a contract, and it appears that the proposed development (or, for multiphased projects, the complete development) meets the threshold(s) of a development of regional impact, according to “Rules of Georgia Department of Community Affairs, Chapter 110-12-3, Developments of Regional Impact, effective March 1, 2014, as may be amended from time to time.
Sec. 13-503. Jurisdiction.
If a proposed development project is to be located in more than one jurisdiction and, in total, the proposed development meets or exceeds a DRI threshold, the local government in which the largest portion of the project is to be located is responsible for initiating the DRI review process.
Sec. 13-504. Procedures.
The application procedures established in this UDC will be modified by this Division in cases where a rezoning request, conditional use application or variance application fits the definition of a “development of regional impact.” Developments of regional impact will be processed according to procedures of the Georgia Department of Community Affairs as described in “Rules of Georgia Department of Community Affairs, Chapter 110-12-3, Developments of Regional Impact, effective March 1, 2014, as may be amended from time to time.
When an application is received for development that meets or exceeds the thresholds established for that development type and thus constitutes a “development of regional impact” according to the aforementioned Rules of the Georgia Department of Community Affairs, the city will follow the procedures identified in said administrative rules which are summarized here.
(a) When an application for a development of regional impact is received, the Zoning Administrator will complete an “Initial DRI Information” form and a “DRI Review Initiation Request” form. Each of these two forms may be submitted to the regional commission simultaneously, provided the city has all necessary project-related information.
(b) The city shall not take any official legislative or administrative action to advance or further a DRI project until the review process identified under the DRI review procedure specified in “Rules of Georgia Department of Community Affairs, Chapter 110-12-3, Developments of Regional Impact,” effective March 1, 2014, as may be amended from time to time, is completed. The city may undertake preliminary staff administrative functions associated with a proposed DRI including, but not limited to, project evaluation/assessment, site visits, and placing consideration of the application on a future agenda for formal action, if required. The city shall not take any official action related to such a project until the DRI review process is completed and the city has had adequate time to consider the DRI review comments.
(c) After the DRI review process is completed, the city may proceed with whatever action it deems appropriate regarding the proposed project, although it is encouraged to take the public finding and additional comments into consideration as it makes its decision.
(d) If the project receives a negative public finding from the Regional Commission and the city approves said project or takes action to advance said project, the city shall notify the regional commission and the Georgia Department of Community Affairs of its action and identify all local requirements it has placed on the development that could mitigate any negative findings identified in the DRI review process.
Article 14 Variance and Appeals
ARTICLE 14
VARIANCES AND APPEALS
DIVISION I VARIANCES
DIVISION II ADMINISTRATIVE VARIANCES
DIVISION III APPEALS OF ADMINISTRATION DECISIONS
Sec. 14-101. Authority to grant variances.
(a) The Commerce City Council shall have the power to authorize upon application in specific cases such variances from the terms of this UDC as will not be contrary to the public interest where, owing to special conditions, a literal enforcement of the provisions of this UDC will in an individual case result in unnecessary hardship or practical difficulty, so that the spirit of this UDC shall be observed, public safety and welfare secured, and substantial justice done.
(b) The Commerce City Council may upon application approve, conditionally approve, or deny variances, subject to the requirements of this division. In granting a variance, the Commerce City Council may impose such requirements and conditions with respect to the location, construction, maintenance and operation of any use or building, in addition to those expressly set forth in this UDC, as may be deemed necessary for the protection of adjacent properties and the public interest.
Sec. 14-102. Initiation of variance applications.
An application for variance may be initiated by any person, firm, corporation or agency, provided said individual, firm, corporation or agency is the owner or owner's agent of the property for which the variance is sought. The Commerce City Council may also initiate a variance application.
Sec. 14-103. Application requirements.
Applications for variance shall require submittal of the following items:
(a) Application fee as specified by resolution of the City Council;
(b) Application form furnished by the zoning administrator, including signed and notarized signature of property owner;
(c) Campaign contribution disclosure;
(d) Legal description of the property;
(e) Survey plat of the property;
(f) Letter of intent describing the proposed use of the property or other action requested;
(g) Site plan of the property at an appropriate engineering scale showing existing and proposed buildings and structures and other information as may be required by the Zoning Administrator to describe and/or graphically depict the requested variance;
(h) Written analysis of how the proposed action compares to decision criteria specified for the granting of variances pursuant to this division; and
(i) Other information as may be required by the zoning administrator.
Sec. 14-104. Criteria for granting variances.
Any applicant requesting consideration of a variance to any provision of this UDC shall provide a written justification that one or more of the condition(s) described in this section exist. The Commerce City Council shall not approve a variance application unless it shall have adopted findings that all the following conditions exist:
(a) There are extraordinary and exceptional conditions pertaining to the particular piece of property in question because of its size, shape or topography, and such conditions are peculiar to the particular piece of property;
(b) The application of this UDC to the particular piece of property would create an unnecessary hardship;
(c) Relief, if granted, would not cause substantial detriment to the public good or impair the purpose and intent of this UDC;
(d) The special circumstances surrounding the request for a variance are not the result of acts by the applicant; and
(e) The variance is not a request to permit a use of land, buildings, or structures, which is not permitted by right or by conditional use permit in the zoning district involved. For any variance to the flood damage prevention requirements of Article 10 of this UDC, the specific requirements, procedures, and criteria in Article 10 of this UDC shall apply in addition to the requirements of this division.
Sec. 14-105. Application compliance and completeness.
(a) A separate application (and fee) is required for each section of this UDC proposed to be varied. In cases where more than one application for variance pertaining to a particular piece of property is filed, said applications may be processed simultaneously.
(b) No variance application shall be processed by the Zoning Administrator unless it complies with the procedural requirements of this division and is found to be complete with regard to application materials, payment of fees, supportive materials, and any other application requirements specified by this division.
(c) The Zoning Administrator shall not accept for processing, or process, a variance application that does not comply with all application submittal requirements of this division.
Sec. 14-106. Administrative processing of applications.
The Zoning Administrator shall review the application for completeness within 10 working days of the posted application submission deadline. Upon a finding by the Zoning Administrator that a variance application is complete and complies with the requirements of this division, including deadlines, the application shall be marked received and approved for initiation, and the date of such consideration shall be indicated in the file of the application.
Sec. 14-107. Concurrent variance application.
In cases where an applicant is proposing a rezoning (i.e., amendment to the official zoning map) or conditional use, or both, and where the applicant files an application to obtain a variance related to the same property as involved in the filing a rezoning or conditional use application, the applications may be administratively processed simultaneously, but no action shall be taken by the Commerce City Council on the variance application until the rezoning or conditional use application, or both as appropriate, is approved by the City Council.
Sec. 14-108. Investigation and recommendation.
(g) The Zoning Administrator may send the application out for review by internal city departments and external agencies as may be appropriate (i.e., inter-agency review). Any written comments received in a timely manner shall be submitted to the applicant, the Planning Commission and Commerce City Council, and any such comments shall become an official public record.
(h) The Zoning Administrator shall investigate and make a recommendation regarding any or all of the relevant matters concerning the application. Any such investigation and recommendation shall if in writing be made available to the applicant, the Planning Commission and Commerce City Council prior to public hearings and shall become an official public record.
(i) The variance application shall be submitted to the Planning Commission for review and recommendation. The Planning Commission shall also hold a public hearing on the matter prior to providing a recommendation. The Planning Commission may recommend, approval, conditional approval, or denial.
Sec. 14-109. Published notice of public hearings.
(a) At least 15 but not more than 45 days preceding the date of the Commerce Planning Commission’s public hearing, the Zoning Administrator shall cause to be published within a newspaper of general circulation within the city a notice of a public hearing on the matter before the Commerce Planning Commission. The notice shall state the time, place, and purpose of the public hearing and shall include the location of the property.
The notice shall also include the nature of the variance request, including the section of this UDC requested to be varied.
Sec. 14-110. Public hearing notice – sign on property.
(m)Requirement and locations. The applicant shall be required to post and maintain signs supplied by the city near the right-of-way of the nearest public street, so as to be visible from the street at least 15 but not more than 45 days prior to the date of the public hearing held by the Planning Commission and at least 15 days and not more than 45 days immediately preceding the date of the Commerce City Council’s consideration of the rezoning application. One such sign shall be placed in a conspicuous location along each street frontage of the property for which the variance has been requested. If the property has no street frontage, the sign shall be placed on each street where access to the property will be gained.
(n) Content. The sign providing notice shall state the time, place, and purpose of the public hearing and shall include the location of the property. The notice shall also include the nature of the variance request, including the section of this UDC requested to be varied.
(o) Time period. It is the responsibility of the applicant to post the signs and to maintain the signs during the posting period. Said signs pertaining to the Commerce City Council’s consideration shall remain posted until a final decision by the Commerce City Council has been rendered.
(p) Consequences of non-maintenance. Failure to post and maintain the signs continuously may prohibit consideration of the application at any scheduled public hearing. In the event the signs are not posted continuously, the city, in its sole discretion, may require the reposting and readvertising prior to any future public hearing, for which the applicant shall pay an additional readvertising fee. The city may also in its sole discretion, continue, hold, or dismiss the application if public notice requirements are not met due to applicant non-maintenance of the required public notice sign(s) on the property.
Sec. 14-111. Public hearing and procedures.
(a) The Commerce Planning Commission shall hold a public hearing on all variance applications.
(b) Procedures for calling and conducting a public hearing with regard to variances shall be the same as those procedures established in Article 13 of this UDC.
Sec. 14-112. Decision.
(g) Time frame. Within 35 days of the date of its public hearing, the Planning Commission shall make a recommendation on the application for variance. Within 65 calendar days of the date of recommendation of the Planning Commission, the Commerce City Council shall render a decision on the application for variance. This time limit may be extended if the applicant consents to extend the time frame.
(h) Decision.
1. The Commerce City Council may approve or disapprove the proposed variance, or it may approve the application with conditions.
2. The Commerce City Council shall consider information supplied by the applicant, the Planning Commission and the Zoning Administrator prior to making a decision.
3. The recommendation of the Planning Commission and the decision of the Commerce City Council shall be based on findings.
4. If the Commerce City Council’s proposed action on the variance is consistent with the findings in the staff report prepared by the zoning administrator, the Commerce City Council may rely on the findings in the staff report, without the need to adopt any additional findings. In such instance, the motion shall be worded as follows: “I make a motion to approve [or deny] the application for variance based on the findings adopted in the staff report for the application.”
5. If the Commerce City Council’s proposed action on the variance is contrary to the findings in the staff report prepared by the zoning administrator, the Commerce City Council shall adopt its own findings to support its decision. In such instance, the Commerce City Council shall take one of the following actions prior to acting on a motion: adopt its own findings of fact; or request that the Zoning Administrator articulate findings to support the proposed action; or recess to allow the Board members or the Zoning Administrator to articulate findings to support the proposed action; or continue the meeting to a later date certain to give the City Council and/or Zoning Administrator time to articulate findings to support the proposed action.
Sec. 14-113. Withdrawal of application.
(h) No refund. There shall be no refund by the city of an application fee if an application is withdrawn.
(i) Prior to public notice. If a request for withdrawal is received prior to the publication of a notice for a public hearing, the application shall be withdrawn administratively by the Zoning Administrator without restriction on the refiling of a variance application on the property in the future, as described in this division.
(j) After public notice. If a request for withdrawal is received after publication of a public notice has been published or when such public notice has been irretrievably set for publication but the variance application has not been heard by the Planning Commission or the Commerce City Council, the application shall be withdrawn administratively by the zoning administrator, provided that an application for a variance relating to the property shall not be resubmitted for twelve months from the date of withdrawal.
(k) After Planning Commission public hearing. No withdrawal of a variance application shall be permitted after the Planning Commission public hearing on said application has been convened.
Sec. 14-114. Notice of action.
The Zoning Administrator shall notify the applicant in writing of the decision on the variance application by the Commerce City Council.
Sec. 14-115. Finality and appeal.
A decision of the Commerce City Council with regard to a variance application shall be final and may be appealed to the Jackson County Superior Court in accordance with law. Such appeal must be taken within ten (10) days of the written decision of the Commerce City Council.
Sec. 14-116. Limitations on the frequency of filing applications.
(a) No variance application requesting variance to the same section of the UDC and affecting the same or any portion of property which was denied by the Commerce City Council shall be accepted for filing by a property owner until twelve months shall have elapsed from the date said application for variance to the same section of the UDC was denied by the Commerce City Council.
(b) After approval of a variance, no variance application requesting variance affecting the same or any portion of property which was approved by the Commerce City Council shall be accepted for filing by a property owner until twelve months shall have elapsed from the date said application for variance was approved by the Commerce City Council.
Sec. 14-201. Authority.
(a) The Zoning Administrator shall have the power to authorize upon application in specific cases such variances from the terms of this UDC as will not be contrary to the public interest where, owing to special conditions, a literal enforcement of the provisions of this UDC will in an individual case result in unnecessary hardship or practical difficulty, so that the spirit of this UDC shall be observed, public safety and welfare secured, and substantial justice done. Administrative variances will only be considered at the discretion of the Planning Administrator and variance requests cannot exceed a 20% modification to each standard set in this UDC.
(b) The Zoning Administrator may upon application approve, conditionally approve, or deny variances, subject to the requirements of this division. In granting a variance, the Zoning Administrator may impose such requirements and conditions with respect to the location, construction, maintenance and operation of any use or building, in addition to those expressly set forth in this UDC, as may be deemed necessary for the protection of adjacent properties and the public interest.
Sec. 14-202. Initiation of administrative variance applications.
An application for administrative variance may be initiated by any person, firm, corporation or agency, provided said individual, firm, corporation or agency is the owner or owner's agent of the property for which the administrative variance is sought.
Sec. 14-203. Application requirements.
Applications for administrative variance shall require submittal of the following items:
(a) Application fee for each variance requested as specified by resolution of the City Council;
(b) Application form furnished by the zoning administrator, including signed and notarized signature of property owner;
(c) Campaign contribution disclosure;
(d) Legal description of the property;
(e) Survey plat of the property;
(f) Letter of intent describing the proposed use of the property or other action requested;
(g) Site plan of the property at an appropriate engineering scale showing existing and proposed buildings and structures and other information as may be required by the Zoning Administrator to describe and/or graphically depict the requested variance;
(h) Written analysis of how the proposed action compares to decision criteria specified for the granting of variances pursuant to this division; and
(i) Other information as may be required by the zoning administrator.
Sec. 14-204. Criteria for granting administrative variances.
Any applicant requesting consideration of an administrative variance shall provide a written justification that one or more of the condition(s) described in this section exist. The Zoning Administrator shall not approve an administrative variance application unless he or she shall have adopted findings that one or more of the following conditions exist:
(a) There are extraordinary, exceptional, or peculiar conditions pertaining to the particular piece of property in question, because of its size, shape, topography or other physical condition that are not applicable to other lands or structures in the same district; and that such conditions cause unnecessary hardship, practical difficulty or adversely affect the reasonable use or usability of property as currently zoned and regulated;
(b) The requested variance will be in harmony with the purpose and intent of this UDC and will not be injurious to the neighborhood or to the general welfare;
(c) The special circumstances are not the result of the actions of the applicant; and/or
(d) The variance requested is the minimum variance that will make possible the proposed use of the land, building, or structure in the use district proposed.
Sec. 14-205. Application compliance and completeness.
(a) A separate application (and fee) is required for each section of this UDC proposed to be administratively varied. In cases where more than one application for administrative variance pertaining to a particular piece of property is filed, said applications may be processed simultaneously.
(b) No administrative variance application shall be processed by the Zoning Administrator unless it complies with the procedural requirements of this division and is found to be complete with regard to application materials, payment of fees, supportive materials, and any other application requirements specified by this division.
(c) The Zoning Administrator shall not accept for processing, or process, an administrative variance application that does not comply with all application submittal requirements of this division.
Sec. 14-206. Decision.
Within no more than thirty (30) calendar days of the date an administrative variance application is determined complete, the Zoning Administrator shall render a decision on the application which shall be based on findings. The Zoning Administrator shall forward the decision and findings to the City Manager or his designee for review. Within no more than ten (10) calendar days of the date the Zoning Administrator forwards his decision to the City Manager or designee, the City Manager or designee shall render a decision in writing on the application and return said decision to the zoning administrator. The application will be denied if either the Zoning Administrator or the City Manager or designee determine that the administrative variance application should be denied based on findings.
Sec. 14-207. Recourse if denied.
An applicant who applies for an administrative variance that is denied by the Zoning Administrator or City Manager or his designee may file a variance application to be considered by the Commerce City Council, as provided in Division I of this Article.
Sec. 14-301. Appeal as a remedy.
It is the intent of this UDC that all questions arising in connection with the administration and enforcement of this UDC shall be presented first to the Zoning Administrator for potential resolution. Persons may appeal to the Commerce City Council for relief when aggrieved by an action or an interpretation of the Zoning Administrator made under this UDC. All such requests for relief shall be taken as an appeal to the Commerce City Council, as provided in this Division.
Sec. 14-302. Initiation of an appeal.
Any person aggrieved by a decision of the Zoning Administrator or by an act of any person acting administratively under authority of this UDC may initiate, by application, an appeal of an administrative action or interpretation to the Commerce City Council. An application for an appeal for any property or properties may be initiated by the owner of a majority interest in the property affected, or his or her authorized representative.
Sec. 14-303. Bases for an appeal.
(a) An appeal may be filed where it is alleged that the Zoning Administrator has misinterpreted or misapplied one or more requirements or other provisions of this UDC.
(b) An appeal may be filed where it is alleged that an enforcement officer erred in finding the person or property in violation of any provision of this UDC or in violation of permit conditions.
Sec. 14-304. Application requirements.
(a) All appeal applications shall be submitted to the Zoning Administrator on forms provided by the zoning administrator. The applicant shall be required to submit all documentation necessary to support the appeal application, which shall be transmitted by the Zoning Administrator to the Commerce City Council.
(b) All appeal applications shall be accompanied by a non-refundable fee, as set by resolution of the governing body from time to time.
(c) An application for an appeal shall include such descriptions, maps or drawings as needed to clearly illustrate or explain the action requested. The city may request such additional information from the appellant as necessary to provide a full understanding of the appeal.
(d) Such appeal application must be filed within thirty days of the action or interpretation that is the subject of the appeal. If the person aggrieved by an action by an administrative official with regard to this UDC does not file a complete appeal application within thirty
Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.