Appendix C - ROADWAY AND SUBDIVISION SPECIFICATIONS

15.03. Construction.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. General requirements. Structures shall be installed in accordance with the specifications and in reasonably close conformance with the details shown on the plans or as

directed. Structure excavation and foundation preparation shall be as set forth in section 5. Before pipe and pipe-arches are

installed the foundation material shall be shaped as shown on plans.

The contractor shall provide necessary temporary drainage.

Before any traffic over a culvert is allowed, the contractor shall provide an adequate depth and width of compacted backfill to protect the structure from damage or displacement. Any damage or traffic or erosion shall be repaired or corrected at the contractor's expense. Any debris or silt that constricts the flow

through a pipe shall be removed by the contractor as often as necessary to maintain drainage throughout the life of the contract. All pipes and pipe-arch culverts

shall be cleaned before the work is accepted.

B. Installation.

1. Concrete pipe. Flat bottom and circular sections shall be laid in a prepared trench with the socket ends pointing upstream. Sections may be

joined by mortar joints, bituminous plastic cement joints, rubber-type gasket joints, O-ringed gasket joints, or preformed plastic gasket joints. In

mortar and bituminous plastic cement joints the annular space shall be filled with the joint material, and

the inside of each joint wiped smooth.

Mortar joints shall be made in the same manner except that the annular space shall be thoroughly wetted before filling with joint material. fter

the initial set, the mortar on the outside shall be protected from the air and sun with thoroughly wet earth or burlap cover. Rubber-type, O-ring, and preformed plastic gasket joints shall be installed in accordance with the manufacturer's recommendations.

2. Cast iron pipe. Pipe sections shall be laid in a prepared trench with bells pointing upstream. The annular space in each joint shall be filled with mortar or bituminous plastic cement as specified of concrete pipe, and each joint wiped smooth. Rubber gasket joints shall be in accordance with manufacturer's requirements.

3. Corrugated aluminum or steel pipe and pipe arches. Pipe sections shall be laid in a prepared trench with outside laps of circumferential joints pointing upstream and with longitudinal joints at the sides. Helical coupling bands, fastened by two or more bolts, shall join the sections. The

space between adjoining sections shall be not more than the width of one corrugation.

All damaged spots in galvanized coating that expose the base metal shall be repaired before the structure is backfilled. All damaged spots in bituminous coating that expose

the base metal shall be recoated with asphalt before the structure is backfilled.

Joints for smooth lines asbestos bonded, corrugated steel pipe shall be formed with and "O" ring type mechanical seal assembly when son detailed on the plans. Seal assembly should be burnished by the same manufacturer that supplies the pipe.

4. Specials (wyes, tees, and bends). The location and manner of installation of all wyes, tees and bends shall be shown on the plans or as directed.

5. Tapered pipe inlets. Tapered pipe inlet end sections will be installed where shown on the plans or as directed.

6. Elongation. Elongation of metal pipe shall be as shown on the plans. The contractor shall order the elongation of the vertical axis of the pipe to be done in the shop.

Metal pipe shall be shipped with wire-tie in the pipe ends. Wire ties shall be removed as soon as possible after the fill is completed.

7. [Flared end sections.] Flared end sections may be specified for use either on the inlet or outlet or both ends of

storm drain pipe according to plan details.

Sec. 16. Rip rap.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cusseta-chattahoochee/zoning/appendix-c-15.03@2026-11-11-d845619195

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Cusseta-Chattahoochee County unified government Zoning Ordinance, 15.03 (Appendix C). Construction | Georgia Commons