Sec. 104-562. Construction inspections of post-construction stormwater management system.

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Inspections to ensure plan compliance during construction; storm sewer installation report. A third-party pipe installation inspection report shall be required for all pipes placed in the ground and shall include the following information:

(1) Description of subgrade and bedding used in installation;

(2) Pipe material certifications;

(3) Description of backfill methods used;

(4) A summary of all field inspections, including the name and affiliation of the inspector, date and time of visits, and summary of activities observed; and

(5) Certification from a registered professional engineer that the pipe was installed in accordance to the approved construction plans and any applicable Georgia DOT, AASHTO or American Concrete Pipe Association Standards.

(b) Periodic inspections. Periodic inspections of the stormwater management system construction shall be conducted and certified by a professional engineer registered in the state. Construction inspections shall utilize the approved stormwater management plan for establishing compliance. The minimum number and schedule of inspections shall be based on the proposed design and established by the environmental management department during the project's preconstruction meeting. All inspections shall be documented with written reports that contain the following information:

(1) The name of the inspector, the date and location of the inspection, and a summary of the activities observed;

(2) A determination if the construction activities are in compliance with the approved stormwater management plan;

(3) Variations from the approved construction specifications; and

(4) Any other variations or violations of the conditions of the approved stormwater management plan.

If any violations are found, the applicant shall be notified in writing of the nature of the violation and the required corrective actions.

History

The history line the source prints at the end of the section.

(Ord. No. 2020-09, § 1, 12-10-2020)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fayette-county/zoning/104-562@2026-05-28-284aa7ea55

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Fayette County Zoning Ordinance, Sec. 104-562. Construction inspections of post-construction stormwater management system | Georgia Commons