(a) Before grading is started, the construction areas shall be cleared of all trees, stumps, roots, weeds, logs, heavy vegetation, and other objectionable matter, and shall be grubbed to a depth below the proposed grade in cuts and the natural ground in fills so as to expose suitable subgrade. The objectionable matter shall be removed from within the right-of-way limits and disposed of in such a manner that it will not become incorporated within the fills, nor in any manner hinder proper operation of the storm drainage system.
(b) Suitable material may be used in the construction of embankments or at any other place needed. If rock is encountered, it shall be removed as determined by the developer's geotechnical engineer. Where boulders are encountered, they should be removed six inches below the proposed grade. Onsite materials may be used, provided they are used according to the recommendations of the geotechnical engineer. If imported fill is used to construct road embankments, the materials shall meet the following requirements:
(1) Standard proctor maximum dry density greater than 100 pounds per cubic foot within the top two feet of finished subgrade elevation; or 95 pounds per cubic foot below the top two feet.
(2) Liquid limit less than 60.
(3) Plasticity index less than 35.