Sec. 9.4. Pavement patching.

About this text

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Description of work.

(1) The extent of pavement patching consists of the repair of all pavement removed or damaged.

(2) Pavement patching includes repair of paved roads, streets, highways, walkways, driveways, patios, slabs on grade, and parking lots together with walls, curbing, gutters and headers, and other pavements and appurtenances. Pavement referred to under this code section refers to asphaltic, cementious, brick, cobble or other large stone pavement materials together with underlying construction, irrespective of its composition.

(b) Job conditions. The following actions are required:

(1) Traffic control.

a. Schedule and conduct work in a manner that will minimize inconvenience to vehicular and pedestrian traffic.

b. Provide flaggers, barricades, warning signs, warning lights, and other warning means as appropriate.

c. Flaggers, when utilized, must hold a valid Georgia DOT flagging certificate.

d. Maintain traffic on all roads and streets disturbed by sewer line construction unless prior arrangements are made with the city.

e. For road crossings, make two separate cuts so that at least one traffic lane is open at all times.

f. All traffic controls during construction must conform to Part VI of the Manual on Uniform Traffic Control Devices, ANSI D6.1e (latest edition).

(2) Weather limitations. Conduct all operations during weather conditions appropriate to the work being performed.

(3) Grade control. Establish and maintain lines and elevations that will assure finished pavement patch having desirable appearance, function and strength.

(c) Products.

(1) For products not described below, use materials and gradations which have locally exhibited a satisfactory record of previous usage, and which for finished visible surfaces will permit obtaining appearance, color and texture reasonably matching remaining adjacent pavement of the same type.

(2) Asphalt concrete. Bituminous plant mixture of asphalt cement and aggregates complying with 12.5 mm Superpave hot plant mix of Section 828 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(3) Soil cement material (pug mix). Soil cement mixture complying with Section 814.2.02 and placed in accordance with applicable provisions of Section 301 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(4) Graded aggregate base. Uniform graded aggregate material complying with Section 815 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(5) Bituminous prime. Cutback asphalt complying with Section 821 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(6) Bituminous tack coat. Asphalt material complying with Section 413, topics 413.01 through 413.04 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(7) Portland cement concrete. Concrete mix of Portland cement, aggregates, water, and air entraining admixture to produce the following properties. 4000 psi minimum compressive strength at 28 days per ASTM C39, four inches maximum slump per ASTM C143, and air content between three percent and six percent.

(8) Cold mix. Uniform bituminous mixture of aggregate, asphaltic material and, if it is required, mineral filler complying with 12.5 mm Superpave cold mix of Section 401 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems."

(d) Execution.

(1) Pavement cuts.

a. Saw cut trench edges in paved areas to neat, straight lines before starting to break the pavement slab.

b. Completely backfill the trench on half a road crossing before trenching the other half of pavement.

(2) Backfill placement.

a. Place trench backfill materials in layers not more than eight inches compacted thickness.

b. Commence backfill immediately after sanitary sewer is installed.

c. Complete new replacement base construction immediately after trench backfill.

d. For all city roads, see also the "utility construction" section of article 4 in this chapter.

(e) Inspection.

(1) Examine areas and conditions under which pavement patching will be conducted, giving special attention to stability of subbase.

(2) Do not proceed with pavement patching work until unsatisfactory conditions have been corrected.

(f) Preparation.

(1) Saw cut any ragged edges of existing pavement, or in the case of concrete work, remove existing pavement to nearest joint.

(2) Remove all loose material from underlying and adjacent surfaces.

(g) Strength and stability.

(1) Use materials and construction techniques as necessary to obtain strength, stability and durability of pavement patch at least equal to that of remaining adjacent pavement of the same type.

(2) As a minimum, conform to pavement patch details in the Catoosa County Engineering Technical Standards Manual.

(3) Accomplish pavement patching utilizing material types and thicknesses not less than that of remaining adjacent pavement.

(h) Placing.

(1) Construct pavement using methods and equipment in general use for the type of work being performed.

(2) Immediately after new base construction, cover pavement cut with steel plates or similar devices of sufficient thickness to span the cut without noticeable deflection.

Maintain plates in place for not less than 24 hours and not more than seven days and until the soil cement material (if used) has gained sufficient strength to withstand traffic loads. Traffic may resume after installation of metal plates.

(3) Upon removal of the metal plates or similar devices, provide new pavement surface in accordance with one of the following options: i) Immediately apply new permanent pavement surface materials indicated or ii) Immediately apply bituminous cold mixture over bond breaker paper over new base. Monitor performance and repair or replace materials regularly to maintain smooth traffic surface until placement of permanent pavement surface materials. At contractor's time selection prior to completion, remove cold mix and bond breaker paper and provide new permanent pavement surface materials. If performance or maintenance of cold mix patch is unsatisfactory in the opinion of the director of public works, remove materials and provide new permanent pavement surface materials within 72 hours of notice by the director of public works.

(4) Traffic control devices in lieu of cover plates are permitted for pavement patching longitudinal to the street centerline in excess of 20 feet. Use traffic barricades, warning signs and lights, flaggers, and other means as appropriate to continuously control traffic 24 hours per day. Use devices such that at least 12 feet wide, one-way through traffic access is provided at all times. Upon removal of traffic control devices, install permanent pavement surface.

(5) Contractor assumes all responsibility for maintaining repairing and/or replacing soil cement base that may be damaged during curing period.

(6) For existing surface of Portland cement concrete, furnish new Portland cement concrete structure thickness, including base and pavement surface, of not less than seven inches; except for sidewalks that are to be not less than four inches thick, and driveways are to be not less than six inches thick.

(7) Provide not less than eight inches thickness of new graded aggregate base for replacement of asphalt concrete pavement at driveways, sidewalks and parking lots.

(8) For repair of asphalt concrete pavement, clean base and adjacent surfaces and apply bituminous tack coat or bituminous prime (as appropriate) to such surfaces before placing new asphalt concrete surface.

(i) Finish.

(1) Accomplish pavement patching using materials and techniques which result in visible, finished surfaces having appearance, color, and texture reasonably matching remaining adjacent pavement of the same type.

(2) Do not permit the finished surface to have dips, objectionable roughness or discontinuity or non-draining areas.

(3) Do not create any unsafe pavement condition.

(j) Repairs.

(1) If pavement patch or adjacent pavement settles or shows evidence of other distress resulting from the work, cut pavement out, repair subgrade, and reconstruct patch.

(2) Do not place additional pavement material on top of unsatisfactory previously repaired surfaces.

(3) At expense of contractor, repair any pavement damaged beyond that minimum amount necessary to construct the work.

History

The history line the source prints at the end of the section.

(Ord. No. 2021-10, § 1, 6-28-2021)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fort-oglethorpe/zoning/appendix-a-chapter-7-article-9-9.4@2026-03-26-1d330c2c2c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Fort Oglethorpe Zoning Ordinance, Sec. 9.4 (Appendix A, Chapter 7, Article 9). Pavement patching | Georgia Commons