Glynn County · Zoning Ordinance

Article 4 - USE PROVISIONS / 4.6 - Industrial Uses

4.6.4. Data Center

About this text

  • As posted on the county's website, retrieved 2026-11-23

A. Defined A facility dedicated to the housing of telecommunications exchanges, or computer or data processing equipment or systems. Data centers shall comply with the following regulations:

1. Buildings shall not exceed a height of seventy-five (75) feet, measured from structure pad level.

Height limitations shall not apply to accessory structures such as water towers, conveyer belts, smokestacks and other incidental and uninhabited parts of industrial uses.

2. Front, side, and rear yard setback: fifty (50) feet.

3. Minimum lot frontage: One hundred ten (110) feet adjoining a street.

4. Minimum lot width at building line: One hundred ten (110) feet.

5. Minimum lot acreage: Fifty (50) acres.

6. Minimum buffer requirements. In addition to required setbacks, buffers shall be required in accordance with the applicable zoning district.

7. Air conditioning units and HVAC systems. Air conditioning units and HVAC systems shall be thoroughly screened from view from the public right-of-way and from adjacent properties by using walls, fencing, roof elements, or landscaping. This requirement shall not apply where the equipment is more than 100 feet from adjacent property lines.

8. Front building facade. The front building facade of all principal buildings shall be oriented toward street fronts or adjacent arterial street fronts. This requirement shall not apply if the front of the building is greater than 500 feet from the public right-of-way or not visible from the public right-ofway.

9. Security fencing. Security fencing and walls shall not be located within the required buffer unless it complies with the general regulations pertaining to fencing. Fences and walls outside the required setback and buffer provided above shall not be subject to height limitations.

10. Accessory structures. Accessory structures shall be subject to the standards of the applicable zoning district. Notwithstanding other provisions of the code, guard houses and secured entry features shall be permitted at public road entrances.

11. Internal development roads may be public or private and are subject to the county engineering standards of the development regulations.

12. Water consumption and cooling systems. Data centers shall incorporate performance measures designed to limit potable water consumption, including the use of closed-loop or similar systems designed to minimize consumption and eliminate continuous discharge or evaporative loss.

Read this code where it is posted (county website (glynncounty.org)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:glynn-county/zoning/4.6.4@2026-11-23-d89405eee2