4.6.4. Data Center

Sobre este texto

  • As posted on the county's website, retrieved 2026-11-23

Las notas de arriba, el texto de la sección y su línea de historia se muestran en inglés, tal como los publica la fuente y como los da el corpus.

A. Defined A facility dedicated to the housing of telecommunications exchanges, or computer or data processing equipment or systems. Data centers shall comply with the following regulations:

1. Buildings shall not exceed a height of seventy-five (75) feet, measured from structure pad level.

Height limitations shall not apply to accessory structures such as water towers, conveyer belts, smokestacks and other incidental and uninhabited parts of industrial uses.

2. Front, side, and rear yard setback: fifty (50) feet.

3. Minimum lot frontage: One hundred ten (110) feet adjoining a street.

4. Minimum lot width at building line: One hundred ten (110) feet.

5. Minimum lot acreage: Fifty (50) acres.

6. Minimum buffer requirements. In addition to required setbacks, buffers shall be required in accordance with the applicable zoning district.

7. Air conditioning units and HVAC systems. Air conditioning units and HVAC systems shall be thoroughly screened from view from the public right-of-way and from adjacent properties by using walls, fencing, roof elements, or landscaping. This requirement shall not apply where the equipment is more than 100 feet from adjacent property lines.

8. Front building facade. The front building facade of all principal buildings shall be oriented toward street fronts or adjacent arterial street fronts. This requirement shall not apply if the front of the building is greater than 500 feet from the public right-of-way or not visible from the public right-ofway.

9. Security fencing. Security fencing and walls shall not be located within the required buffer unless it complies with the general regulations pertaining to fencing. Fences and walls outside the required setback and buffer provided above shall not be subject to height limitations.

10. Accessory structures. Accessory structures shall be subject to the standards of the applicable zoning district. Notwithstanding other provisions of the code, guard houses and secured entry features shall be permitted at public road entrances.

11. Internal development roads may be public or private and are subject to the county engineering standards of the development regulations.

12. Water consumption and cooling systems. Data centers shall incorporate performance measures designed to limit potable water consumption, including the use of closed-loop or similar systems designed to minimize consumption and eliminate continuous discharge or evaporative loss.

Leer este código donde se publica (county website (glynncounty.org)) La fuente es el código de la ciudad tal como lo publica su editorial o su propio sitio web. Consúltelo allí para ver cambios posteriores.

Versión local-code:glynn-county/zoning/4.6.4@2026-11-23-d89405eee2

El asistente puede decir lo que dice esta sección en esta edición, citándola y enlazándola. No aplicará la ley a su situación, y nada de esto es asesoría legal.

Glynn County Zoning Ordinance, 4.6.4. Data Center | Georgia Commons