A. Generally. No building permit, rezoning request or subdivision plan will be approved by the Director of Planning and Development unless the permit, request or plan is in compliance with the groundwater protection standards listed in Section 3.03.06.
B. Enforcement. Gordon County, its agent, officers and employees shall have authority to enter upon privately owned land for the purpose of performing their duties under this section and may make or cause to be made such examinations, surveys or sampling as the County deems necessary.
1. The Director of Planning and Development is hereby designated as the administrator and enforcement officer for this section.
2. The Director of Planning and Development shall have authority to enforce this section, issue permits hereunder, and address violations or threatened violations hereof by issuance of violation notices, administrative orders and civil and criminal actions. All costs, fees and expenses in connection with such actions may be recovered as damages against the violator.
3. Law enforcement officials or other officials having police powers shall have authority to assist the Director of Planning and Development in enforcement.
4. Any person who commits, takes part in or assists in any violation of any provision of this section shall be fined not more than two thousand five hundred dollars ($2,500.00) for each offense. Each violation shall be a separate offense and, in the case of a continuing violation, each day's continuance shall be deemed to be a separate and distinct offense.
5. The Director of Planning and Development shall have the authority to issue cease and desist orders in the event of any violation of this section. Cease and desist orders may be appealed to a court of competent jurisdiction, as identified in Section 3.03.07.
6. When a building or other structure has been constructed in violation of this section, the violator shall be required to remove the structure.
7. When removal of vegetative cover, excavation or fill has taken place in violation of this section, the violator shall be required to restore the affected land to its original contours and to restore vegetation, as far as practicable.
8. No person may begin the physical development of a lot or structure thereon, where an on-site sewage management system will be utilized, not install an on-site sewage management system or component thereof without having first applied for and obtained from the Board of Health a construction permit for the installation.
C. Permit review and site plan requirement. With the exception of certain exempted activities identified in Section 3.03.05(D), applications for a development permit within the groundwater recharge area district shall include a site plan. The following information is required for all site plans:
1. A map or maps, drawn to a scale of not less than one (1) inch equals fifty (50) feet, showing all planned improvements including the width, depth and length of all existing and proposed structures, roads, watercourses and drainageways, water lines, wastewater and stormwater facilities, and utility installations, shall be provided by the applicant.
2. Location, dimensions and area of all impervious surfaces, both existing and proposed, on the site.
3. The orientation and distance from the boundaries of the proposed site to the nearest bank of an affected perennial stream or water body.
4. Elevations of the site and adjacent lands within two hundred (200) feet of the site at contour intervals of no greater than five (5) feet.
5. Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally released hazardous or toxic materials.
6. Calculations of the amount of cut and fill proposed and cross-sectional drawings showing existing and proposed grades in areas of fill or excavation. Elevations, horizontal scale and vertical scale must be shown on cross-sectional drawings.
7. Activities to comply with site plan. All development activities or site work conducted after approval of the site plan shall conform with the specifications of said site plan. Significant changes to the site plan that would alter the amount and velocity of stormwater runoff from the site, increase the amount of impervious surface within the development, alter the overall density of development, result in a considerable increase in the amount of excavation, fill or removal of vegetation during construction or otherwise result in an alteration of the overall appearance of the development as proposed, can be amended only with the approval of the Director of Planning and Development. Minor changes, such as the realignment of streets or minor alterations to drainage structures and other infrastructure to meet unexpected conditions, are exempted from this requirement.
D. Exemptions to site plan requirements. The following activities and developments are exempt from the requirement for detailed site plans:
1. Single-family detached homes constructed within a subdivision of fewer than five
(5) parcels.
2. Repairs to a facility that is part of a previously approved and permitted development.
3. Construction of minor structures, such as sheds or additions to single-family residences.
E. Review procedures
1. The application shall be made to the Director of Planning and Development and will be reviewed within thirty (30) days.
2. The review period shall include the preparation of findings (approval, approval with conditions or disapproval) by the Director of Planning and Development.
3. The applicant will receive written notification of the findings of the Director of Planning and Development.
4. If the review process is not completed within thirty (30) days, the application is considered to be approved.
5. Decisions of the Director of Planning and Development may be appealed to the County.
F. Public notice and public hearing
1. Public notice of permit applications, through publication in local newspapers, is required.
2. A public hearing on the application, to be held before the County, may be scheduled if requested by a citizen.
3. Public announcement of the hearing shall be printed in a local newspaper of general circulation at least fifteen (15) days prior to the hearing.
4. A record of the proceedings shall be made and kept on file by the County.
5. Any person may testify at the hearing.
6. Decisions of the County may be appealed to a court of competent jurisdiction identified in Section 3.03.07.
G. Duration of permit validity
1. If construction described in the development permit has not commenced within twelve (12) months from the date of issuance, the permit shall expire.
2. If construction described in the development permit is suspended or abandoned after work has commenced, the permit shall expire twelve (12) months after the date that work ceased.
3. Written notice of pending expiration of the development permit shall be issued by the County.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.